The applicant proposes to modify a previously authorized barge slip.
Full Public Notice Project Plans
PROJECT DESCRIPTION: The applicant proposes to modify a previously
authorized barge slip by constructing 860-linear-foot of new bulkhead around an
existing inlet off of the Houston Ship Channel/Buffalo Bayou. Approximately 2,500 cubic yards of material
is proposed to be discharged to back fill behind the new bulkhead. Additionally, the applicant proposes to
mechanically and/or hydraulically dredge approximately 30,000 cubic yards of
material to a depth of 30 feet below mean low tide (MLT) from the current depth
of 12 feet below MLT. The applicant also
proposes to modify the previous authorization by adding seven existing dredged
material placement areas to their authorization. The seven areas to be added as dredged
material placement options are: 1) House
Tract, 2) East West Clinton, 3) Targa, 4) East West Jones, 5) Glanville Pinto,
6) Kirby, and 7) HMS. The dredged material
for this project is proposed to be placed in one of the 10 placement areas
listed on the project plans. The
preferred placement areas are either Kirby or Lost Lake as they are the closest
placement areas to the project site.