The City of Houston is proposing to expand the Northeast Water Purification Plant.
Full Public Notice Project Plans Mitigation Plan
PROJECT DESCRIPTION:
The City of Houston (City) is proposing to expand the Northeast Water
Purification Plant (NEWPP), to bring the overall production capability of the
facility to 504 Million Gallons per day (MGD).
The proposed activities include the construction of a pump station,
water transmission lines, treatment facilities, and associated
appurtenances. The applicant is requesting
permission to place approximately 64,000 cubic yards (CY) of fill material into
39 acres of wetlands for initial site grading.
Additionally, nearly 30,000 CY of fill would be placed in 0.44 acre of
the Lake, for the construction of the intake and pump station structures. Permanent and temporary impacts to streams
include, 85 CY of fill into a stream and temporary impacts will include the
discharge of 151 CY of fill material into eight streams. All temporary impacts will be restored to
pre-project contours. The specific
components required for the expansion include:
• As
part of the expansion of the NEWPP the applicant is proposing to discharge fill
material into approximately 24 acres of palustrine emergent wetlands (PEM) and 6.2 acres of palustrine
scrub/shrub wetlands (PSS) within a 70-acre tract, which had previously been
mechanically cleared of vegetation. Authorization for the previous land clearing
activities was included in Department of the Army (DA) Permit Number 22414.
• The
expansion of the footprint of the facility beyond what was previously permitted
which would impact approximately 8.749 acres of palustrine forested wetlands (PFO) and
0.031 acre of an intermittent pond.
• The
existing security fence will be moved approximately 150 feet outward to the
property boundary and constructed within a 20-foot-wide zone that needs to be cleared for security
purposes. The City plans to maintain at
least a 20-foot forested wetland buffer between the fence and treatment facility.
• The
construction of approximately 1.5 miles of two 96-inch-diameter raw water lines
from a meter station to the NEWPP. The
installation of thelines would
impact approximately 0.343 acre of PFO, 0.1 acre of PSS, and 0.1 acre of PEM.
• An
offshore intake and pump station will be constructed in the Lake.
• The
construction of a causeway to provide access to the offshore pump station and
provide support for two 96-inch-diameter raw water lines.
• Associated
appurtenances and support facilities including an expansion to the electrical
supply system.