PLACEMENT OF FILL FOR THE CONSTRUCTION OF A RESIDENTIAL SUBDIVISION (OAK LAKE) IN ASCENSION PARISH
NAME OF APPLICANT:
DR Horton, Inc. Gulf Coast, c/o Hydrik Wetlands Consultants, Attn:
Michael Henry, 2323 Hwy190 East, Suite 2, Hammond, Louisiana 70401.
LOCATION OF WORK:
Approximately 0.7 acre south of I-10, Section 13 and 45, T10S-R3E, in
Gonzales, Louisiana, in Ascension Parish, within the Lake Maurepas Basin in
hydrologic unit (HUC 08070204), as shown on the attached drawings.
CHARACTER OF WORK:
The applicant has requested Department of the Army authorization to
clear, grade, excavate, and deposit fill from onsite to construct and maintain a
residential subdivision (Oak Lake) to include 163 lots, streets, house pads,
utilities, 2 storm water detention ponds, a park, recreational center, pool,
and two walking paths. Approximately 15,000
cubic yards of fill material from onsite will be redistributed to achieve
required grade elevation requirements.
The proposed project is situated on an approximately 55-acre tract that
has been determined to include approximately 8.03 acres of forested wetlands
and approximately 0.67 acre of other waters of the US. A preliminary analysis has determined that
the proposed project would directly impact approximately 7.14 acres of
jurisdictional forested wetlands and 0.56 acre of other waters of the US during
construction. It is anticipated that the
proposed action would have minimal impact on adjacent wetlands.
The
applicant has designed the project to avoid and minimize direct and secondary
adverse impacts to the maximum extent practicable. Any further reduction would limit usage of
the property and, therefore function deeming the project impracticable. As compensation for unavoidable wetland
impacts, the applicant proposes to mitigate in-kind wetland credits from a
Corps approved mitigation bank located in the watershed.