The applicant proposes to deepen the BIH.
Full Public Notice Project Plans
The applicant proposes to deepen the BIH from the
authorized depth of -42 feet below mean lower low water (MLLW) to a depth of
-52 feet below MLLW. The BIH entrance
channel and Jetty Channel are proposed to be deepened to -54 feet below
MLLW. No channel widening is proposed. Where necessary, the top cut of the channel
may be extended, or varied, in order to maintain the current channel side
slopes. Dredging is proposed to be
conducted using a cutter head dredge or hopper dredge.
Dredged material is proposed to be placed into designated
upland confined dredge material placement areas (DMPAs) 2, 3, 4A, 4B, 5A, 5B, 7
and/or 8; the New Work ODMDS; and placed for beneficial use to promote beach
renourishment, by placing material onto a feeder berm offshore of South Padre
Island.
The project was originally proposed as a federal
channel improvement project. The applicant
is seeking a Department of Army Permit to conduct the work evaluated in the BIH
Channel Improvement Project Final Integrated Feasibility Report, dated July
2014. This would allow the applicant to
conduct the initial deepening of the channel with private (non-federal)
funds. The Corps may elect to enter into
an Assumption of Maintenance agreement at some point, after initial work is
completed.