CONSTRUCT TWO WELLSITE AND ACCESS ROADS IN IBERVILLE PARISH
NAME OF
APPLICANT: Boardwalk
Louisiana Midstream, LLC, c/o Providence Engineering and Environmental,
Attn: Ms. Regina Staten, 1201 Main
Street, Baton Rouge, Louisiana 70802.
LOCATION OF
WORK:
In Iberville Parish, North 30.31322, West -91.304701, located approximately 3.3
miles south of Louisiana Highway 1, near Plaquemine, Louisiana, as shown on the
attached vicinity map.
CHARACTER OF
WORK: Clear,
grade, fill and/or excavate and construct two new 40 foot wide by 150 foot long
access roads, improve a 800 foot long section to 40 feet in width, three wings
off one drill pad, and two 350 foot by 350 foot drill pads. Approximately 31,605 cubic yards of earthen
fill material and 9,063 cubic yards of crushed limestone will be used for the
access roads, wings and drill pads. Approximately 6.35
acres of jurisdictional wetlands would be impacted by project implementation. The applicant proposes to purchase
compensatory mitigation acres at CEMVN approved mitigation banks in the area.
JOINT PUBLIC NOTICE
April 4, 2016
United States Army
Corps of Engineers
New Orleans District
Attn: Regulatory Branch
Post Office Box 60267
New Orleans, Louisiana 70160-0267
State of Louisiana
Department of Environmental Quality
Attn: Water Quality Certification Sec.
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
Project Manager: James W. Little, Jr.
(225) 342-3099 / fax: (225) 342-9439
James.little@usace.army.mil
Permit Application Number:
MVN-2016-00119-WII
Project Manager:
Elizabeth Johnson
(225) 219-3225 / fax: (225) 219-3156
WQC Application Number:
WQC 160328-01
Interested parties are hereby notified that a permit application has been received by the
New Orleans District of the U.S. Army Corps of Engineers pursuant to: [ ] Section 10 of the
Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [ X ] Section 404
of the Clean Water Act (86 Stat. 816; 33 USC 1344).
The application has also been mailed to the Louisiana Department of Environmental
Quality, for a Water Quality Certification (WQC) in accordance with statutory authority contained
in Louisiana Revised Statute 30:2074 A(3), and provisions of Section 401 of the Clean Water
Act (P.L. 95-17).
CONSTRUCT TWO WELLSITE AND ACCESS ROADS IN IBERVILLE PARISH
NAME OF APPLICANT: Boardwalk Louisiana Midstream, LLC, c/o Providence Engineering
and Environmental, Attn: Ms. Regina Staten, 1201 Main Street, Baton Rouge, Louisiana
70802.
LOCATION OF WORK: In Iberville Parish, North 30.31322, West -91.304701, located
approximately 3.3 miles south of Louisiana Highway 1, near Plaquemine, Louisiana, as shown
on the attached vicinity map.
CHARACTER OF WORK: Clear, grade, fill and/or excavate and construct two new 40 foot wide
by 150 foot long access roads, improve a 800 foot long section to 40 feet in width, three wings
off one drill pad, and two 350 foot by 350 foot drill pads. Approximately 31,605 cubic yards of
earthen fill material and 9,063 cubic yards of crushed limestone will be used for the access
roads, wings and drill pads. Approximately 6.35 acres of jurisdictional wetlands would be
impacted by project implementation. The applicant proposes to purchase compensatory
mitigation acres at CEMVN approved mitigation banks in the area.
The comment period for the Department of the Army Permit and the Louisiana
Department of Environmental Quality WQC will close 20 days from the date of this joint public
notice. Written comments, including suggestions for modifications or objections to the
proposed work, stating reasons thereof, are being solicited from anyone having interest in this
permit and/or this WQC request and must be submitted so as to be received before or by the
last day of the comment period. Letters concerning the Corps of Engineers permit application
must reference the applicant's name and the Permit Application Number, and be forwarded to
the Corps of Engineers at the address above, ATTENTION: REGULATORY BRANCH.
Individuals or parties may request an extension of time in which to comment on the proposed
work by writing, faxing, or e-mailing the Corps of Engineers Project Manager listed above. Any
request must be specific and substantively supportive of the requested extension, and received
by this office prior to the end of the initial comment period. The Section Chief will review the
request and the requestor will be promptly notified of the decision to grant or deny the request.
If granted, the time extension will be continuous to the initial comment period and, inclusive of
the initial comment period, will not exceed a total of 30 calendar days. Letters concerning the
Water Quality Certification must reference the applicant's name and the WQC Application
number and be mailed to the Louisiana Department of Environmental Quality at the address
above.
The application for this proposed project is on file with the Louisiana Department of
Environmental Quality and may be examined during weekdays between 8:00 a.m. and 4:30
p.m. Copies may be obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable
impacts, including cumulative impacts of the proposed activity on the public interest. That
decision will reflect the national concern for both protection and utilization of important
resources. The benefit which reasonably may be expected to accrue from the proposal must be
balanced against its reasonably foreseeable detriments. All factors which may be relevant to
the proposal will be considered including the cumulative effects thereof; among those are
conservation, economics, aesthetics, general environmental concerns, wetlands, historic
properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation,
shoreline erosion and accretion, recreation, water supply and conservation, water quality,
energy needs, safety, food and fiber production, mineral needs, considerations of property
ownership and, in general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state,
and local agencies and officials, Indian Tribes, and other interested parties in order to consider
and evaluate the impacts of this proposed activity. Any comments received will be considered
by the U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny
a permit for this proposal. To make this decision, comments are used to assess impacts on
endangered species, historic properties, water quality, general environmental effects, and other
public interest factors listed above. Comments are used in the preparation of an Environmental
Assessment and/or an Environmental Impact Statement pursuant to the National Environmental
Policy Act. Comments are also used to determine the need for a public hearing and to
determine the overall public interest of the proposed activity.
The New Orleans District is unaware of properties listed on the National Register of
Historic Places near the proposed work. The possibility exists that the proposed work may
damage or destroy presently unknown archeological, scientific, pre-historical, historical sites, or
data. Issuance of this public notice solicits input from the State Archeologist and State Historic
Preservation Officer regarding potential impacts to cultural resources.
Based on the South Louisiana Standard Local Operating Procedure for Endangered
Species (SLOPES), as signed on October 22, 2014, between the U.S. Army Corps of
Engineers, New Orleans and the U.S. Fish and Wildlife Service, the proposed project was
evaluated under the determination key on 25 March 2016 and it has been determined that the
6.35 acres of jurisdictional forested wetlands to be impacted is located outside areas that
contain Louisiana black bear (Ursus americanus luteolus ) critical habitat and areas with high
probability of supporting breeding females and determined that the activity is not likely to
adversely affect the species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the
Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal may
result in the destruction or alteration of N/A acres of EFH utilized by various life stages of red
drum and penaeid shrimp. Our initial determination is that the proposed action would not have
a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our
final determination relative to project impacts and the need for mitigation measures is subject to
review by and coordination with the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters,
the evaluation of the probable impacts will include the application of guidelines established by
the Administrator of the Environmental Protection Agency. Also, a certification that the
proposed activity will not violate applicable water quality standards will be required from the
Department of Environmental Quality, before a permit is issued.
Any person may request, in writing, within the comment period specified in this notice,
that a public hearing be held to consider this application. Requests for public hearings shall
state, with particularity, the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any other
parties whom you deem likely to have interest in the matter.
John M. Herman
Chief, Central Evaluation Section
Regulatory Branch
Enclosure
_
^
Project Center
Latitude: 30.31322°
Longitude: -91.304701°
2
0
Legend
Project Center
4
Miles
Vicinity Map
Section 404 Permit Application
Iberville Parish, Louisiana
Boardwalk Louisiana Midstream, LLC
Bayou Choctaw (PN 5950/5951)
Reference
Base map comprised of ESRI StreetMap USA data.
Drawn By
JCR
12/22/2015
Checked By
JTG
12/22/2015
Approved By
RS
12/22/2015
Project Number
1037-012
Drawing Number
1037-012-A006
1
Figure
Providence Engineering and Environmental Group LLC
4
Proposed Choctaw Storage
Well No. 31
NAD83
Lat: 30° 18' 50.10"N
Long: 91° 18' 12.52"W
N: 659,656
E: 3,290,254
NAD 27
Lat: 30° 18' 49.40"N
Long: 91° 18' 12.12"W
N: 598,948
E: 2,009,455
2,000
1,000
Legend
0
2,000
Feet
Project Area (7.36 acres)
NAD83
Lat: 30° 18' 44.54"N
Long: 91° 18' 20.09"W
N: 659,094
E: 3,289,590
NAD 27
Lat: 30° 18' 43.84"N
Long: 91° 18' 19.70"W
N: 598,386
E: 2,008,791
Site Location Map
Section 404 Permit Application
Iberville Parish, Louisiana
Boardwalk Louisiana Midstream, LLC
Bayou Choctaw (PN 5950/5951)
Drawn By
Checked By
Reference
Base map comprised of U.S.G.S. 7.5 minute topographic map, "Addis, LA"
dated 1992.
Approved By
JCR
12/22/2015
JTG
12/22/2015
RS
12/22/2015
Project Number
1037-012
Drawing Number
1037-012-A007
2
Figure
Providence Engineering and Environmental Group LLC
Proposed Choctaw Storage
Well No. 29
100
0
Legend
Proposed Area (7.36 acres)
Impacted Wetlands - Permanent Fill (6.09 acres)
PEM - 3.11 acres
PFO - 1.94 acres
PSS - 1.04 acres
Impacted Other Waters of the U.S. - 0.26 acre
Existing Roads and Well Pads
200
Feet
Proposed Well Pad (350' x 350')
Site Plan
Section 404 Permit Application
Iberville Parish, Louisiana
Boardwalk Louisiana Midstream, LLC
Bayou Choctaw (PN5950/5951)
Drawn By
Checked By
Approved By
JCR
12/22/2015
JTG
12/22/2015
RS
12/22/2015
Project Number
1037-012
Drawing Number
1037-012-A008
3
Figure
Providence Engineering and Environmental Group LLC
200
New Road
B'
D
D'
!
New Road
B
Wing
Wing
C
A'
C'
!
200
100
0
200
Feet
Legend
Proposed Impact - 7.36 acres
Proposed Well Pad (350' x 350')
Impacted Wetlands - Permanent Fill- 6.09 acres
PEM - 3.11 acres
PFO - 1.94 acres
PSS - 1.04 acres
Impacted Other Waters of the U.S. - 0.26 acre
!
Road Improvements
Wing
Well Location
Reference
Base map comprised of Google Imagery dated 03/14/2014.
Aerial Photograph
Section 404 Permit Application
Iberville Parish, Louisiana
Boardwalk Louisiana Midstream, LLC
Bayou Choctaw (PN5950/5951)
Drawn By
Checked By
Approved By
JCR
12/22/2015
JTG
12/22/2015
RS
12/22/2015
Project Number
1037-012
Drawing Number
1037-012-A009
4
Figure
Providence Engineering and Environmental Group LLC
A
Proposed 24" Culvert
?
Proposed 24" Culvert
?
Proposed 24" Culvert
200
100
0
Legend
Proposed Impact - 7.36 acres
Proposed Well Pad (350' x 350')
?
Proposed 24-Inch Culvert
200
Feet
Aerial Photograph
Section 404 Permit Application
Iberville Parish, Louisiana
Boardwalk Louisiana Midstream, LLC
Bayou Choctaw (PN5950/5951)
Drawn By
Checked By
Reference
Base map comprised of Google Imagery dated 03/14/2014.
Approved By
JCR
2/17/2016
JTG
2/17/2016
RS
2/17/2016
Project Number
1037-012
Drawing Number
1037-012-A015
10
Figure
Providence Engineering and Environmental Group LLC
?
Structural Clay
1
0
Crushed Limestone
2
Feet
1 inch = 2 feet
Typical Culvert
Cross Section
Section 404 Permit Application
Iberville Parish, Louisiana
Boardwalk Louisiana Midstream, LLC
Bayou Choctaw (PN 5950/5951)
Drawn By
JCR
2/17/2016
Checked By
JTG
2/17/2016
Approved By
RS
2/17/2016
Project Number
1037-012
Drawing Number
1037-012-A016
11
Figure
Providence Engineering and Environmental Group LLC
2
24" Culvert