PIPELINE REPLACEMENT IN ST. MARY PARISH

NAME OF APPLICANT: Shell Pipeline Company, Post Office Box 2648, OSP 41082B, Houston, Texas 77252-2648.

LOCATION OF WORK: Bateman Island, crossing Atchafalaya River and Bayou Shaffer, located in near the community of Morgan City, in St. Mary Parish, Louisiana, as shown on the enclosed drawings.

Location: POB: Latitude: 29°40ʹ52ʺ N / Longitude: -91°13ʹ31ʺ W, POE: Latitude: 29°40ʹ47ʺ N / Longitude: -91°11ʹ21ʺ W, Hydrologic Unit Code for West of Bayou Shaffer: 08080101 – Atchafalaya River Basin, Hydrologic Unit Code for East of Bayou Shaffer: 08090302 – Terrebonne, West-Central Louisiana Coastal Basin

CHARACTER OF WORK: Atchafalaya River Segment: Cut and abandon 4,160 feet of an existing 22-inch Shell Pipeline, conduct drilling and excavation operations to install 1,120-foot long pipeline to connect to the new HDD pipeline and to the existing pipeline at Berwick Station, construct a 40-foot wide by 50-foot long bore pit within a 200-foot wide by 200-foot long work space connected to a 40-foot wide by 1,140-foot long excavated work space, place approximately 7,825 cubic yards excavated fill material in three temporary spoil placements, 980 cubic yards of wood chips along pipeline, and a total of approximately 365 cubic yards within a 30-foot wide by 75-foot long and a 30-foot wide by 230-foot long areas in the Atchafalaya River. Bateman Island Segment: Cut and abandon 4,160 feet of an existing 22-inch Shell Pipeline, conduct drilling and excavation operations to install 4,860 feet of the HDD pipeline, construct a 40-foot wide by 50-foot long bore pit within a 250-foot wide by 250-foot long work space and a 40-foot wide by 50-foot long bore pit within a 200-foot wide by 200-foot long work space connected to a 80-foot wide by 2,860-foot long excavated work space, which includes placing 1,275 cubic yards of wood chips in a 10-foot wide by 2,860-foot long temporary spoil placement area along the south side of an 30-foot wide existing right-of-way (ROW), and placing approximately 1,275 cubic yards of wood chips in a 10-foot wide by 2,860 foot long flotation channel within part of the ROW, 2,330 cubic yards of wood chips in a 30-foot wide by 2,860 foot long temporary spoil placement and 2,330 cubic yards of wood chips in a 15-foot wide by 2,860-foot long flotation channel, all on the north side of the ROW, place approximately 1,160 cubic yards of excavated fill material within temporary excavated workspace near bore pit area that is located within the 250-foot wide by 250-foot long work space, and 1,280 cubic yards of excavated fill material near bore pit area that is located within the 200-foot wide by 200-foot long work space. East of this work space, cut and abandon 5,175 feet of an existing 22-inch Shell Pipeline, install a 50-foot wide by 1,289-foot long excavated work space, place approximately 2,135 cubic yards of wood chips along 4,255-foot long HDD pipeline, and construct 40-foot wide by 54-foot long concrete dock, install four 5-pile clusters, and conduct clearing, grading, and chipping operations to place approximately 649 cubic yards of wood chips in a 200-foot wide by 350-foot long work space. Bayou Shaffer Segment: Place 240 cubic yards of rip rap within a 30-foot wide by 155-foot long area in Bayou Shaffer, cut and abandon 5,175 feet of an existing 22-inch Shell Pipeline, install 4,255-foot long HDD pipeline, install a 40-foot wide by 50-foot long bore pit within a 200-foot wide by 200-foot long work space connected to a 75-foot wide by 400-foot long work space, place approximately 3,300 cubic yards of excavated material near bore pit area, 3,485 cubic yards of wood chips within a 75-foot wide by 125-foot long temporary spoil placement. Approximately 1.84 acres of jurisdictional wetlands west of Atchafalaya River levee and 0.21 of an acre of open water in the Atchafalaya River would be permanently impacted via project implementation. Approximately 12.29 acres of jurisdictional wetlands east of the Atchafalaya River levee and 0.10 of an acre of open water in Bayou Shaffer in would be permanently impacted via project implementation. Temporary impacts include 0.46 of an acre of non-wetlands and 3.63 acres of temporary spoil placement work areas. Therefore, a total of 14.1 acres of jurisdictional wetlands would be permanently impacted via project implementation. The applicant agrees to compensate for wetland impacts by purchasing credits at a Department of the Army approved mitigation bank.

JOINT PUBLIC NOTICE April 4, 2016 United States Army Corps of Engineers New Orleans District Regulatory Branch Post Office Box 60267 New Orleans, Louisiana 70160-0267

State of Louisiana Department of Environmental Quality ATTN: Water Quality Certifications Post Office Box 4313 Baton Rouge, Louisiana 70821-4313

(504) 862-2284 Sara.B.Fortuna@usace.army.mil Project Manager Sara Fortuna Permit Application Number MVN-2015-01060-WKK

(225) 219-3225 Elizabeth.Hill@la.gov Project Manager Elizabeth Hill WQC Application Number WQC 160330-01

Interested parties are hereby notified that a permit application has been received by the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344). Application has also been made to the Louisiana Department of Environmental Quality, Water Quality Certifications, for a Water Quality Certification (WQC) in accordance with statutory authority contained in LRS30:2047 A(3), and provisions of Section 401 of the Clean Water Act (P.L.95-17). PIPELINE REPLACEMENT IN ST. MARY PARISH NAME OF APPLICANT: Shell Pipeline Company, Post Office Box 2648, OSP 41082B, Houston, Texas 77252-2648. LOCATION OF WORK: Bateman Island, crossing Atchafalaya River and Bayou Shaffer, located in near the community of Morgan City, in St. Mary Parish, Louisiana, as shown on the enclosed drawings. Location: POB: Latitude: 29°4052 N / Longitude: -91°1331 W, POE: Latitude: 29°4047 N / Longitude: -91°1121 W, Hydrologic Unit Code for West of Bayou Shaffer: 08080101 ­ Atchafalaya River Basin, Hydrologic Unit Code for East of Bayou Shaffer: 08090302 ­ Terrebonne, West-Central Louisiana Coastal Basin CHARACTER OF WORK: Atchafalaya River Segment: Cut and abandon 4,160 feet of an existing 22-inch Shell Pipeline, conduct drilling and excavation operations to install 1,120-foot long pipeline to connect to the new HDD pipeline and to the existing pipeline at Berwick Station, construct a 40-foot wide by 50-foot long bore pit within a 200-foot wide by 200-foot long work space connected to a 40foot wide by 1,140-foot long excavated work space, place approximately 7,825 cubic yards excavated fill material in three temporary spoil placements, 980 cubic yards of wood chips along pipeline, and a total of approximately 365 cubic yards within a 30-foot wide by 75-foot long and a 30-foot wide by 230-foot long areas in the Atchafalaya River. Bateman Island Segment: Cut and abandon 4,160 feet of an existing 22-inch Shell Pipeline, conduct drilling and excavation operations to install 4,860 feet of the HDD pipeline, construct a 40-foot wide by 50-foot long bore pit within a 250-foot wide by 250-foot

-2long work space and a 40-foot wide by 50-foot long bore pit within a 200-foot wide by 200-foot long work space connected to a 80-foot wide by 2,860-foot long excavated work space, which includes placing 1,275 cubic yards of wood chips in a 10-foot wide by 2,860-foot long temporary spoil placement area along the south side of an 30-foot wide existing right-of-way (ROW), and placing approximately 1,275 cubic yards of wood chips in a 10-foot wide by 2,860 foot long flotation channel within part of the ROW, 2,330 cubic yards of wood chips in a 30-foot wide by 2,860 foot long temporary spoil placement and 2,330 cubic yards of wood chips in a 15-foot wide by 2,860-foot long flotation channel, all on the north side of the ROW, place approximately 1,160 cubic yards of excavated fill material within temporary excavated workspace near bore pit area that is located within the 250-foot wide by 250-foot long work space, and 1,280 cubic yards of excavated fill material near bore pit area that is located within the 200-foot wide by 200-foot long work space. East of this work space, cut and abandon 5,175 feet of an existing 22-inch Shell Pipeline, install a 50-foot wide by 1,289-foot long excavated work space, place approximately 2,135 cubic yards of wood chips along 4,255-foot long HDD pipeline, and construct 40-foot wide by 54-foot long concrete dock, install four 5pile clusters, and conduct clearing, grading, and chipping operations to place approximately 649 cubic yards of wood chips in a 200-foot wide by 350-foot long work space. Bayou Shaffer Segment: Place 240 cubic yards of rip rap within a 30-foot wide by 155-foot long area in Bayou Shaffer, cut and abandon 5,175 feet of an existing 22-inch Shell Pipeline, install 4,255-foot long HDD pipeline, install a 40-foot wide by 50-foot long bore pit within a 200-foot wide by 200-foot long work space connected to a 75-foot wide by 400-foot long work space, place approximately 3,300 cubic yards of excavated material near bore pit area, 3,485 cubic yards of wood chips within a 75-foot wide by 125-foot long temporary spoil placement. Approximately 1.84 acres of jurisdictional wetlands west of Atchafalaya River levee and 0.21 of an acre of open water in the Atchafalaya River would be permanently impacted via project implementation. Approximately 12.29 acres of jurisdictional wetlands east of the Atchafalaya River levee and 0.10 of an acre of open water in Bayou Shaffer in would be permanently impacted via project implementation. Temporary impacts include 0.46 of an acre of non-wetlands and 3.63 acres of temporary spoil placement work areas. Therefore, a total of 14.1 acres of jurisdictional wetlands would be permanently impacted via project implementation. The applicant agrees to compensate for wetland impacts by purchasing credits at a Department of the Army approved mitigation bank. The comment period for the Department of the Army Permit and the Louisiana Department of Environmental Quality WQC will close 20 days from the date of this joint public notice. Written comments, including suggestions for modifications or objections to the proposed work, stating reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC request and must be mailed so as to be received before or by the last day of the comment period. Letters concerning the Corps of Engineers permit application must reference the applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers at the address above, ATTENTION: REGULATORY BRANCH. Similar letters concerning the Water Quality Certification must reference the applicant's name and the WQC Application number and be mailed to the Louisiana Department of Environmental Quality at the address above. Individuals or parties may request an extension of time in which to comment on the proposed work by writing or e-mailing the Corps of Engineers Project Manager listed above. Any request must be specific and substantively supportive of the requested extension, and received by this office prior to the end of the initial comment period. The Section Chief will review the request and the requestor will be promptly notified of the decision to grant or deny the request. If granted, the time extension will be continuous to the initial comment period and, inclusive of the initial comment period, will not exceed a total of 30 calendar days.

-3The application for this proposed project is on file with the Louisiana Department of Environmental Quality and may be examined during weekdays between 8:00 a.m. and 4:30 p.m. Copies may be obtained upon payment of costs of reproduction. Corps of Engineers Permit Criteria The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. The New Orleans District is unaware of properties listed on the National Register of Historic Places near the proposed work. The possibility exists that the proposed work may damage or destroy presently unknown archeological, scientific, prehistorical, historical sites, or data. Issuance of this public notice solicits input from the State Archeologist and State Historic Preservation Officer regarding potential impacts to cultural resources. The New Orleans District has determined that out of the 18.53 acre project footprint, 0.31 of an acre is located in waters known to be utilized by the pallid sturgeon (Scaphirhynchus albus) and the West Indian Manatee (Trichechus manatus) and 1.84 acres of jurisdictional wetlands utilized by the Louisiana Black Bear (Ursus americanus luteolus) and determined the activity is not likely to adversely affect these species based on the Standard Local Operating Procedure for Endangered Species in Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps of Engineers, New Orleans and U.S. Fish and Wildlife Service, Ecological Services Office. If this permit is issued, the applicant has agreed to the following conditions provided in the SLOPES manual: Standard Manatee Conditions for In-Water Activities, Appendix LBB-01 Conditions for General Activities That Would Occur within Louisiana Black Bear Breeding Habitat, and the Appendix LBB-03 Conditions for Activities That Would Occur within Louisiana Black Bear Critical Habitat.

-4This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the destruction or alteration of 0.31 of an acre of EFH utilized by various life stages of red drum and penaeid shrimp. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service. If the proposed work involves deposits of dredged or fill material into navigable waters, the evaluation of the probable impacts will include the application of guidelines established by the Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity will not violate applicable water quality standards will be required from the Department of Environmental Quality, Water Quality Certifications, before a permit is issued. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. The applicant has certified that the proposed activity described in the application complies with and will be conducted in a manner that is consistent with the Louisiana Coastal Resources Program. The Department of the Army permit will not be issued unless the applicant received approval or a waiver of the Coastal Use Permit by the Department of Natural Resources. You are requested to communicate the information contained in this notice to any other parties whom you deem likely to have interest in the matter.

Darrell S. Barbara Chief, Western Evaluation Section Enclosure

26 xx

BA

Y

O

U

SH

A

ER F F

END PROPOSED EXCAVATION/ PROPOSED POINT OF ENTRY X = 3,326,190' Y = 429,172' LAT = 29° 40' 48" LONG = 91° 11' 26"

PROPOSED EQUIPMENT ACCESS- 6,450'± X 30'±

FORESTED WETLANDS TO BE CLEARED, CHIPPED, & USED AS FILL DUE TO EQUIPMENT ACCESS- 200'± X 200'± (490± YDS/ 0.92± ACRES)

NAD 83 NAD 83

PROPOSED 22-INCH HDD PIPELINE

AVOCA, INC.

30'

FORESTED WETLANDS TO BE CLEARED, CHIPPED, & USED AS FILL DUE TO EQUIPMENT ACCESS- 20'± X 20'± (5± YDS/ 0.01± ACRES)

FORESTED WETLANDS TO BE CLEARED, CHIPPED, & USED AS FILL DUE TO EQUIPMENT ACCESS- 210'± X 75'± (185± YDS/ 0.35± ACRES)

EMERGENT WETLANDS/ EXISTING SHELL ROW UTILIZED DUE TO EQUIPMENT ACCESS- 2,820'± X 30'± (1.96± ACRES)

BEGIN PROPOSED EXCAVATION /PROPOSED TIE-IN/ P.O.E. X = 3,326,623' Y = 429,082' LAT = 29° 40' 47" LONG = 91° 11' 21"

NAD 83 NAD 83

EMERGENT WETLANDS/ EXISTING SHELL ROW UTILIZED DUE TO EQUIPMENT ACCESS- 185'± X 75'± (145± YDS/ 0.28± ACRES)

FORESTED WETLANDS TO BE CLEARED, CHIPPED, & USED AS FILL DUE TO EQUIPMENT ACCESS- 50'± X 10'± (5± YDS/ 0.01± ACRES)

SCALE: 1" = 200'

200'

100'

0'

200'

170' X 30' new ROW to be inspected from the HDD exit to the tiein with existing pipeline.

185' X 30' new ROW to be inspected from HDD exit to tie-in with existing pipeline.

1120' X 30' New ROW to be inspected. 400' X 30' new ROW to be inspected.

Only the 4 trenched areas of the proposed pipeline will be subject to physical inspection in the future. The areas are: § The 1120' segment from Berwick Station to the Atchafalaya River HDD entry tie-in. § The 170' tie-in of the Atchafalaya River exit to the existing pipeline on Bateman Island. § The 185' tie-in of the Bayou Shaffer HDD exit to the existing pipeline on Bateman Island. § The 400' tie-in of the Bayou Shaffer drill to the existing pipeline on Avoca Island. The type of equipment and clearing requirements will depend on the nature of the repair.

26 XX

26 XX

26 XX

26 XX

26 XX

26 XX

30' existing cleared ROW

Workspace 2860' X 80'

26 XX

26 XX

Workspace 58' X 50'

Dock details shown on Sheets 20 - 25

Workspace 1289' X 50'

26 XX

Workspace 400' X 75'

26 XX

26 XX

26 XX

26 XX

26 XX

26 XX

Existing 30', cleared ROW (NTS)

Existing 30' ROW

26 XX

26 XX

60-125'

60'- 85' 60'-85' 10' - 20'

XXXX 40' - 85' x 1' Timber mats will be used as needed to minimize impacts.

XXXXXXXXXXXXXXXX

26 XX

TOTAL PIPELINE RELOCATION IMPACTS

DOCK IMPACTS SHOWN ON SHEETS 20 - 25. TOTAL PROJECT IMPACTS ON SHEET 26.

26 XX

SHEET 20 OF 26 XXXX

Chipped material spread 4" or less in the 200' X 350' work area. All work will take place within the 200' X 350' work area.

XXX 22 & 23

X 24

X 24

21 OF 26 XXXX

22 OF 26 XXXX

23 OF 26 XXXX

200' x 1' xx

24 OF 26 XXXX

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Wetland Impacts - PFO 1/2R (BLH), 1.61 acres.

Pipeline replacement impacts shown on Sheet 19 of 26. COMBINED DOCK AND PIPELINE IMPACTS SHOWN ON SHEET 26. TOTAL DOCK IMPACTS

Chipped trees spread up to 4" above ground. Natural ground 25 OF 26 XXXXX

TOTAL PROJECT IMPACTS WEST OF LEVEE (Inside)

EAST OF LEVEE (Outside)

EXCAVATIONS Non-Vegetated Water 80 CYS Bottoms 0.01 ACS

Wetlands

4425 CY 0.623 ACS

Non-Wetlands

3400 CY 0.46 ACS

10,970 CY 2.897 ACS

Fill Excavated Material Non-Wetlands

2650 CY 0.15 ACS

Wetlands

5255 CY 0.3 ACS

10,970 CY 3.33 ACS

Wetlands

906 CY 1.84 ACS

6402 CY 12.29 ACS

Non-Wetlands

74 CY 0.15 ACS

82 CY 0.16 ACS

Chipped Trees

Rip Rap Non-Vegetated Water Bottoms

605 CY 0.31 ACS

Total Excavations

18,875 3.99 ACS

Total Fill

26,944 CY 18.53 ACS

SHEET 26 OF 26

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas