DREDGING, BULKHEAD AND SLIP EXPANSION IN TERREBONNE PORT COMMISSION SLIP IN TERREBONNE PARISH
NAME OF APPLICANT:
Terrebonne Port Commission, PO Box 6097, Houma, LA 70361
LOCATION OF WORK:
In the Terrebonne Port Commission Slip off of the Houma Navigation Canal,
Section 12, T17S-R17E, in Houma, Louisiana, in Terrebonne Parish, within the West
Central Louisiana Coastal in hydrologic unit (HUC 08090302), as shown on the
attached drawings (Latitude 29.561341 N, Longitude -90.698734 W).
CHARACTER OF WORK:
The applicant has requested Department of the Army authorization to install
11,460 linear feet of bulkhead and dredge approx. 125,500 cubic yards of
material from approx. 6.23 acres of Traditionally Navigable Waters of the US in
order to improve and expand the Terrebonne Port Commission Slip. Suitable dredged material will be utilized
on-site as backfill for the proposed and previously existing bulkhead. Excess dredged material will be placed at two
on-site spoil bank locations totaling approx. 86.7 acres of jurisdictional
wetlands which have been previously permitted for spoil placement and for which
compensatory mitigation has been collected per MVN-1997-00175-CT. The proposed project is situated on an
approximately 390 acres of which approx. 60 acres are Traditionally Navigable
Waters of the US and approx. 105 acres are jurisdictional wetlands which have
been previously authorized for the deposition of dredged material. It is anticipated that the proposed action
would have minimal impact on adjacent wetlands.
It is presumed that the applicant has designed the project to avoid and
minimize direct and secondary adverse impacts to the maximum extent
practicable. All discharge of dredged
material will be placed in previously authorized spoil placement
locations. The applicant proposes to
avoid additional direct impacts and minimize secondary impacts to wetlands by
remaining within the footprint of the previously authorized project site.