The applicant proposes to drill multiple carbon dioxide injection and secondary recovery oil and gas wells from 8 pad locations.
Full Public Notice Project Plans
The applicant proposes to drill multiple carbon dioxide
injection and secondary recovery oil and gas wells from 8 pad locations. Well pads will be constructed in 3
phases. Each construction phase includes
a proposed road, refurbishment, and the installation of 12-foot elevated pipe
racks above the marsh, alongside existing roads. Phase 1 would result in the displacement of
approximately 2 acres of tidally-influenced wetlands and 5.84 acres of open
water. Phase 2 would result in the
displacement of approximately 2.2 acres of tidally-influenced wetlands and 1.89
acres of open water. Phase 3 would
result in the displacement of approximately 1.63 acres of wetlands and 0.29
acre of open water.