TIME EXTENSION AND PERMIT MODIFICATION, TO INCLUDE TURN LANES, FIREWATER INTAKE STRUCTURE AND SHORELINE PROTECTION ON THE CALCASIEU RIVER IN CAMERON & CALCASIEU PARISH

NAME OF APPLICANT: Cameron LNG, LLC, c/o T. Baker Smith, LLC, Attn: Mr. Brady Trahan, 107 Global Circle, Lafayette, Louisiana 70503.

LOCATION OF WORK: In Calcasieu and Cameron Parish, North 30.059583, West -93.331769, located off of the Calcasieu River Ship Channel, near Hackberry, Louisiana, as shown on the attached vicinity map.

CHARACTER OF WORK: Clear, grade, fill and excavate to construct two turn lanes on Louisiana Highway 27, and place rip-rap material along the shoreline for protection. Approximately 11,000 cubic yards of hauled-in material, 3,000 cubic yards of gravel and 3,000 cubic yards of concrete will be deposited onsite for the turning lanes; plus approximately 15,000 cubic yards of rock will be deposited in the Calcasieu River for shoreline protection. Approximately 0.8 acres of emergent wetlands and 0.2 acres of scrub/shrub wetlands will be impacted by the turning lanes and approximately 1.2 acres of scrub/shrub wetlands would be impacted by the placement of rip-rap along the shoreline. The applicant proposes to offset these wetland impacts by creating 3.0 acres of emergent wetlands by the placement of dredged spoil material via maintenance dredging from their ongoing facility operations.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas