You can copy from here when filling out the rest of the page.
State of Missouri - Proposed Reissuance of General Permit GP-34M Sand and Gravel Excavation Activities. In accordance with Title 33 CFR 325.2 and 325.7(e), as published in the November 13, 1986, Federal Register, the Kansas City District, U.S. Army, Corps of Engineers (as lead district), in conjunction with the St. Louis District, Rock Island District, Little Rock District, and Memphis District proposes to reissue GP-34M which would authorize the discharge of dredged or fill material in association with excavation of sand and gravel in waters of the United States within the State of Missouri.
State of Missouri - Proposed Reissuance of General Permit GP-34M Sand and Gravel Excavation Activities. In accordance with Title 33 CFR 325.2 and 325.7(e), as published in the November 13, 1986, Federal Register, the Kansas City District, U.S. Army, Corps of Engineers (as lead district), in conjunction with the St. Louis District, Rock Island District, Little Rock District, and Memphis District proposes to reissue GP-34M which would authorize the discharge of dredged or fill material in association with excavation of sand and gravel in waters of the United States within the State of Missouri.
PUBLIC NOTICE
US Army Corps
of Engineers
Kansas City District
Permit No. NWKGP-34M
Issue Date: June 15, 2016
Expiration Date: July 6, 2016
21-Day Notice
STATE OF MISSOURI
PROPOSED REISSUANCE OF GENERAL PERMIT 34 MISSOURI
SAND AND GRAVEL EXCAVATION ACTIVITIES
In accordance with Title 33 CFR 325.2 and 325.7(e), as published in the November 13, 1986, Federal Register,
the Kansas City District, U.S. Army, Corps of Engineers (as lead district), in conjunction with the St. Louis
District, Rock Island District, Little Rock District, and Memphis District (map enclosed) proposes to reissue
General Permit 34 Missouri (GP-34M, GP) which would authorize the discharge of dredged or fill material in
association with excavation of sand and gravel in waters of the United States within the State of Missouri. This
GP would be reissued under the authority of Section 404 of the Clean Water Act (33 USC 1344) and Section 10
of the Rivers and Harbors Act of 1899 (33 USC 403). The GP was originally issued December 18, 1995,
reissued on March 16, 2001, again on December 22, 2005, again on July 28, 2011, and expires on July 28, 2016.
In the preceding 5-year period, there were a total of 32 actions authorized under the provisions of this GP in the
Kansas City District and a total of 70 actions by all Districts.
Joint Public Notice. This public notice is issued jointly with the Missouri Department of Natural Resources,
Water Protection Program (MDNR, WPP). MDNR will use the comments to this notice in deciding whether to
grant Section 401 water quality certification. Commenters are requested to furnish a copy of their comments to
the Missouri Department of Natural Resources, Water Protection Program, 401 Certification, P.O. Box 176,
Jefferson City, Missouri 65102-0176.
Criteria for Authorization. Applications submitted for verification under NWKGP-34M (permit enclosed)
would be reviewed on a case-by-case basis to ensure that each activity authorized by the GP meets the cited
criteria included in the GP, special conditions, appendices, and project authorization page(s).
Proposed Changes for Reissuance of GP-34M: The Corps of Engineers (Corps) is proposing several changes
to GP-34M. Most of the proposed changes are in modifications to the special conditions of the permit. A
portion of which will make them align more closely with the State of Missouri's Sand and Gravel Removal
Guidelines, which are used by the MDNR, Land Reclamation Program (LRP) as a means to minimize adverse
impacts resulting from state permitted commercial in-stream sand and gravel removal activities. Therefore,
comments are solicited on the reissuance of the GP, reissuance with all or some of the proposed changes, or
reissuance with other proposed modifications.
Duration of GP-34M. The GP would expire 5 years from the date of reissuance unless it is modified,
suspended, revoked, or specifically extended. Upon its expiration, the GP would be considered for renewal.
The GP may be modified, suspended or revoked, in whole or in part, at any time if it is determined that the
cumulative effects of the activities would have a significant environmental impact or are otherwise not in the
public interest.
All individual verifications under this GP would expire upon expiration of the GP. This date would be noted
on the GP if it is reissued. Therefore, the maximum excavation period for any operations would be limited to
5 years. Prior to its expiration, the GP would be considered for renewal. If it is determined that reissuance of
the GP is in the public interest, a determination would be made to consider any on-going operations previously
authorized by the soon-to-be expired GP. Applicants with on-going operations would likely be required to
either reapply or may be allowed to proceed with their operation by conforming to the conditions of the
renewed permit.
The proposed GP, if reissued, would not obviate the need to obtain other Federal, state or local authorizations
required by law, would not grant any property rights or exclusive privileges, nor would it authorize any injury
to the property or rights of others.
Procedure for Applying. Individuals desiring to perform activities in accordance with the criteria of this GP
must notify the appropriate Corps of Engineer District according to the "Applicant Notification Requirements"
in Appendix I, 5. and in Special Condition p. of the enclosed permit. The notification must include detailed
drawings and sufficient information to determine if the proposed work conforms to the criteria and conditions
of the GP. An ENG Form 4345 and instructions (downloadable at
http://www.usace.army.mil/Missions/CivilWorks/RegulatoryProgramandPermits/ObtainaPermit.aspx) may
be used for this purpose. Copies of ENG Form 4345, instructions, or assistance may also be obtained by
writing or calling the appropriate Corps district.
If the Corps determines that the work would meet the provisions of the GP, and no extraordinary conditions
exist that would warrant submitting an application for an individual permit evaluation, the proponent would be
notified in writing to proceed. If the Corps determines that the subject work would not meet the provisions of
the GP, or that more than minimal impacts would result, or extraordinary conditions exist, the applicant would
be notified that an individual permit will be necessary.
Proposed Evaluation and Conformance Criteria. Individual requests for verification under the GP would
be evaluated based upon the stated activities by the applicant. If the applicant desiring to perform activities
in accordance with the criteria of this GP can comply with the conditions as shown in the GP, an on-site
investigation of the proposed activity may not be required. However, if the party requests a variance from
any conditions of the GP, an on-site investigation of the activity may be conducted by a federal or state
agency and variances would be allowed only if a site specific justification is determined.
All activities authorized by the GP would require notification to the appropriate district engineer. Following
notification, the Corps would be responsible for completing a project authorization page for each excavation
site authorized by the GP. An explanation of the project authorization page can be found in Appendix II, 2.
of the permit.
Compliance with other laws. No potential adverse environmental effects related to the operation of the GP
have been identified or are anticipated from the reissuance of this GP. All applicable statutes, regulations and
administrative policies and agreements, including the National Environmental Policy Act of 1969, will be
considered and satisfied in the decision to reissue the GP. All comments in response to this public notice
should be forwarded to the appropriate address identified under Additional Information.
Public Interest Review. The decision to reissue this GP will be based on an evaluation of the probable impact
of the proposed permit on the public interest. That decision will reflect the national concern for both protection
and utilization of important resources. The benefits which reasonably may be expected to accrue from the
issuance of the proposed permit must be balanced against the reasonably foreseeable detriments. All factors
which may be relevant to the proposed permit issuance will be considered including the cumulative effects
thereof; among those are conservation, economics, esthetics, general wildlife values, flood hazards, flood plain
values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water
quality, energy needs, safety, food production, mineral needs, and, in general, the needs and welfare of the
people.
Comments. Any interested party (particularly officials of any town, city, county, state or Federal agency, local
association, or individual) is invited to submit to the Kansas City District written facts or objections to the
proposed reissuance of this GP on or before the public notice expiration date. Comments, both favorable and
unfavorable, will be accepted and made a part of this record and will receive full consideration in determining
whether it would be in the public interest to reissue the GP.
Endangered Species. In compliance with the Endangered Species Act, a preliminary determination has been
made that the described work will not adversely affect species designated as threatened or endangered or
adversely affect critical habitat. This determination is based upon the inclusion of measures included in the
permit for protection of threatened or endangered species in likely project areas. The GP requires specific
Section 7 consultation concerning individual projects if impacts to threatened or endangered species are
anticipated. In order to complete our evaluation of this activity, comments are solicited from the U.S. Fish
and Wildlife Service and other interested agencies and individuals.
Public Hearing. Any person may request, in writing, prior to the expiration date of this public notice, that a
public hearing be held to consider this GP. Such requests shall state, with particularity, the reasons for holding
a public hearing.
Additional Information. Additional information about the proposed reissuance of this GP may be obtained
by contacting Mr. Mel B. Stanford, Regulatory Project Manager; U.S. Army Corps of Engineers, Truman
Regulatory Satellite Office, 15837 Truman Road, Warsaw, MO 65355; telephone: 816-389-3981,
FAX 660-438-6909, or via e-mail at mel.b.stanford@usace.army.mil. All comments to this public notice
should be directed to the above address.
Enclosures
Kansas City District
Missouri State Regulatory Office
515 East High Street, #202
Jefferson City, MO 65101
Telephone: 573-634-2248
FAX: 573-634-7960
Worth
Atchison
Nodaway
Harrison
Putnam
Scotland Clark
Schuyler
Mercer
Gentry
Kansas City District
Kansas City Regulatory Office
700
635 Federal
Federal Building
Building
601 East 12th Street
Kansas City, MO 64106-2896
Telephone: 816-389-3990
FAX: 816-389-2032
Sullivan
Grundy
Holt
Andrew
Dekalb
Buchanan
Clinton
Adair
Linn
Macon
Ray
Pike
Audrain
Lincoln
Boone
Moniteau
Cole
Henry
Morgan
Benton
Bates
Miller
St Clair
Montgomery
Callaway
St
Charles St Louis
(city)
Gasconade
St Louis
Franklin
Osage
Warren
Pettis
Cass
Ralls
Howard
Lafayette
Johnson
Hickory
Maries
Polk
Barton
Dallas
Washington
St Francois
Dent
Laclede
Reynolds
Texas
Webster
Wright
Jasper
Barry
Christian
Howell
Stone
Taney
Ozark
Scott
Carter
Douglas
Oregon
Cape
Girardeau
Bollinger
Wayne
Shannon
Lawrence
Perry
Iron Madison
Dade
Greene
Ste
Genevieve
Crawford
Pulaski Phelps
Cedar
St. Louis District
1222 Spruce Street
St. Louis, MO 63103-2833
Telephone: 314-331-8575
FAX: 314-331-8741
Jefferson
Camden
Vernon
Mcdonald
Marion
Monroe
Chariton
Randolph
Saline
Newton
Lewis
Shelby
Cooper
Kansas City District
Truman Regulatory Satellite Office
15837 Truman Road
Warsaw, MO 65355
Telephone: 660-438-6697
FAX: 660-438-6909
Rock Island District
Clock Tower Building
Post Office Box 2004
Rock Island, IL 61204-2004
Telephone: 309-794-5351
FAX: 309-794-5191
Caldwell Livingston
Carroll
Jackson
Knox
Daviess
Platte
Clay
U.S. Army Corps of Engineers Districts
in the
State of Missouri
Ripley
Stoddard
Mississippi
Butler
New
Madrid
Pemiscot
Little Rock District
Post Office Box 867
Little Rock, AR 72203-0867
Telephone: 501-324-5295
FAX: 501-324-6013
Dunklin
Memphis District
167 North Main, B202
Memphis, TN 38103-1894
Telephone: 901-544-3473
FAX: 901-544-0211
DEPARTMENT OF THE ARMY PERMIT
Permittee General Public
Permit No. NWKGP-34M, Sand and Gravel Excavation Activities
Issuing Office U.S. Army Engineer District, Kansas City
NOTE: The term "you" and its derivatives, as used in this permit, means the permittee or any future transferee. The
term "this office" refers to the appropriate district or division office of the Corps of Engineers having jurisdiction over
the permitted activity or the appropriate official of that office acting under the authority of the commanding officer.
You are authorized to perform work in accordance with the terms and conditions specified below, and with the plans
and drawings attached hereto which are incorporated in and made a part of this permit.
Project Description: Proposed and/or Completed Work: This permit authorizes the discharge of dredged and/or fill
material related to mechanical sand and gravel excavation as described in Appendix I. Discharges authorized are
limited to those which occur during the actual excavation process and those associated with preparation and restoration
of the site. These discharge activities include but are not limited to temporary stockpiling, access ramps, and
construction of berms for siltation control. Activity descriptions for temporary stockpiling, access ramps and road
crossings are provided below.
Temporary Stockpiling: Stockpiling will only be allowed during day time operational hours. This general permit
does not authorize the stockpiling of material overnight below the ordinary high water mark of the stream where the
sand and gravel mining is occurring. Those wishing to stockpile in a flood way should follow local floodplain
regulations.
Access Ramps and Stream Crossings: This general permit will allow the construction of access ramps up to
25 feet-wide. A variance may be considered on a case-by-case review that would cause no more than ½ acre loss of
waters of the United States. Access ramps must be appropriately constructed and maintained such that stream banks
are protected from erosion. Stream channel modifications must be kept to the minimum necessary to construct road
crossings, and require notification to the Corps (see Special Condition l.).
Note: The general permit does not authorize gravel from the mining area to be used for bank stabilization or siltation
control for any reason. This permit does not allow for sorting, washing, and crushing of excavated material within the
stream bed or on a sand/gravel bar or in such a manner as to allow wash water to re-enter the stream. A separate
permit and/or settling basin for the discharge of return water may be required under Section 402 of the Clean Water
Act from the Missouri Department of Natural Resources, Water Protection Program, Operating Permits Section.
(573-522-4502).
You must not excavate sand or gravel below the elevation of the water at the time of removal, unless specified
otherwise on the attached project authorization page(s) of this permit. Discharge of dredged or fill material below the
water line may require an individual Section 401 water quality certification.
Project Location: Waters of the United States within the State of Missouri; excluding the Missouri and Mississippi
Rivers, and waters designated by the State of Missouri as Outstanding National Resource Waters or Outstanding State
Resource Waters (see attached list, State Regulation 10 CSR 20-7.031 Water Quality Standards, Tables D and E).
ENG FORM 1721, Nov 86
EDITION OF SEP 82 IS OBSOLETE
(33 CFR 325 (Appendix A))
Permit Conditions:
General Conditions:
1. The time limit for completing the work authorized ends on July 28, 2021. If you find that you need more time to
complete the authorized activity, submit your request for a time extension to this office for consideration at least one
month before the above date is reached.
2. You must maintain the activity authorized by this permit in conformance with the terms and conditions of this
permit. You are not relieved of this requirement if you abandon the permitted activity, although you may make a good
faith transfer to a third party in compliance with General Condition 4 below. Should you wish to cease to maintain the
authorized activity or should you desire to abandon it without a good faith transfer, you must obtain a modification of
this permit from this office, which may require restoration of the area.
3. If you discover any previously unknown historic or archeological remains while accomplishing the activity
authorized by this permit, you must immediately notify this office of what you have found. We will initiate the federal
and state coordination required to determine if the remains warrant a recovery effort or if the site is eligible for listing
in the National Register of Historic Places.
4. If you sell the property associated with this permit, you must obtain the signature of the new owner in the space
provided and forward a copy of the permit to this office to validate the transfer of this authorization.
5. If a conditioned water quality certification has been issued for your project, you must comply with the conditions
specified in the certification as special conditions to this permit. For your convenience, a copy of the statewide
certification conditions is attached. If the attached prescribed conditions cannot be met, an individual certification
must be requested.
6. You must allow representatives from this office to inspect the authorized activity at any time deemed necessary to
ensure that it is being or has been accomplished in accordance with the terms and conditions of your permit.
Special Conditions:
See continuation sheets, pages 5 and 6, of this document.
Further Information:
1. Congressional Authorities: You have been authorized to undertake the activity described above pursuant to:
(x) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403).
(x) Section 404 of the Clean Water Act (33 U.S.C. 1344).
( ) Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972 (33 U.S.C. 1413).
-2-
2. Limits of this authorization.
a. This permit does not obviate the need to obtain other Federal, state, or local authorization required by law.
b. This permit does not grant any property rights or exclusive privileges.
c. This permit does not authorize any injury to the property or rights of others.
d. This permit does not authorize interference with any existing or proposed Federal project.
3. Limits of Federal Liability. In issuing this permit, the Federal Government does not assume any liability for the
following:
a. Damages to the permitted project or uses thereof as a result of other permitted or unpermitted activities or from
natural causes.
b. Damages to the permitted project or uses thereof as a result of current or future activities undertaken by or on
behalf of the United States in the public interest.
c. Damages to persons, property, or to other permitted or unpermitted activities or structures caused by the activity
authorized by this permit.
d. Design or construction deficiencies associated with the permitted work.
e. Damage claims associated with any future modification, suspension, or revocation of this permit.
4. Reliance on Applicant's Data: The determination of this office that issuance of this permit is not contrary to the
public interest was made in reliance on the information you provided.
5. Reevaluation of Permit Decision. This office may reevaluate its decision on this permit at any time the
circumstances warrant. Circumstances that could require a reevaluation include, but are not limited to, the following:
a. You fail to comply with the terms and conditions of this permit.
b. The information provided by you in support of your permit application proves to have been false, incomplete, or
inaccurate (See 4 above).
c. Significant new information surfaces which this office did not consider in reaching the original public interest
decision.
Such a reevaluation may result in a determination that it is appropriate to use the suspension, modification, and
revocation procedures contained in 33 CFR 325.7 or enforcement procedures such as those contained in 33 CFR 326.4
and 326.5. The referenced enforcement procedures provide for the issuance of an administrative order requiring you to
comply with the terms and conditions of your permit and for the initiation of legal action where appropriate. You will
be required to pay for any corrective measures ordered by this office, and if you fail to comply with such directive, this
office may in certain situations (such as those specified in 33 CFR 209.170) accomplish the corrective measures by
contract or otherwise and bill you for the cost.
-3-
6. Extensions. General condition 1 establishes a time limit for the completion of the activity authorized by this permit.
Unless there are circumstances requiring either a prompt completion of the authorized activity or a reevaluation of the
public interest decision, the Corps will normally give favorable consideration to a request for an extension of this time
limit.
Your signature below, as permittee, indicates that you accept and agree to comply with the terms and conditions of this
permit.
GENERAL PUBLIC (SIGNATURE NOT REQUIRED)
(PERMITTEE)
__________________________________
(DATE)
This permit becomes effective when the Federal official, designated to act for the Secretary of the Army, has signed
below.
_____________________________________
Mark D. Frazier
Chief, Regulatory Branch
Operations Division
__________________________________
(DATE)
When the structures or work authorized by this permit are still in existence at the time the property is transferred, the
terms and conditions of this permit will continue to be binding on the new owner(s) of the property. To validate the
transfer of this permit and the associated liabilities associated with compliance with its terms and conditions, have the
transferee sign and date below.
_____________________________________
(TRANSFEREE)
__________________________________
(DATE)
-4-
Special Conditions:
a. You must sign and return the attached "Compliance Certification" page after you complete the authorized work and
any required mitigation. Your signature will certify that you completed the work in accordance with this permit,
including general and specific conditions, and that any required mitigation was completed in accordance with the
permit conditions.
b. In addition to the general conditions of the permit, the following special condition applies to your project regarding
Section 10 of the Rivers and Harbors Act. The permittee understands and agrees that, if future operations by the
United States require the removal, relocation, or other alteration, of the structure or work herein authorized, or if, in the
opinion of the Secretary of the Army or his authorized representative, said structure or work shall cause unreasonable
obstruction to the free navigation of the navigable waters, the permittee will be required, upon due notice from the
Corps of Engineers, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to
the United States. No claim shall be made against the United States on account of any such removal or alteration.
c. If any part of the authorized work is performed by a contractor or other party, before starting work you must discuss
the terms and conditions of this permit with the contractor or party; and, you must give a copy of this entire permit to
the contractor or other party involved in the excavation activities. The permittee remains responsible for ensuring
compliance with all aspects of this permit.
d. You must limit excavation of sand or gravel deposits to unconsolidated areas containing primarily smaller material
(at least 85% is less than 3" in diameter) that is loosely packed and contains no woody perennial vegetation greater
than 1-1/2-inch in diameter, measured at breast height (4.5 feet). An undisturbed root zone buffer of 10 feet shall be
maintained around the trunk of woody perennial vegetation greater than 1-1/2 inch in diameter, measured at breast
height.
e. An undisturbed buffer of twenty-five (25) feet wide shall be maintained in an undisturbed condition landward of the
high bank for the length of the gravel removal site. Disturbed areas in this riparian zone shall be limited to maintained
access road(s) for ingress and egress only. No clearing within this riparian area is authorized in association with work
authorized by this permit.
f. You must maintain an undisturbed buffer of ten (10) feet (or as specified on the attached project authorization
page(s) of this permit) between the removal area and the water line at the time of excavation. An undisturbed buffer of
ten (10) feet shall also be maintained between the excavation area and the base of the high bank to protect bank
integrity; at no time may sand or gravel material be pushed or placed against the bank. A gap in the buffer
approximately 1 foot-wide shall be left on the downstream end of the gravel bar to drain the excavation area.
g. You must not excavate sand or gravel below the elevation of the water at the time of removal unless approved by the
Corps and subject to review by federal and state agencies. If the stream is dry at the time, you must not excavate
deeper than the lowest undisturbed elevation of the stream bottom adjacent to the site, unless specified otherwise on
the attached project authorization page(s) of this permit.
h. You must not relocate, straighten, cut off, shortened, widened, or otherwise modify water conveyance areas within
the channel. A "water conveyance area within the channel" is defined as that area between the high banks of the creek,
where water is flowing or, in the case of a dry stream, where water would flow after a rain event.
i. Within 30 days of the removal of excavation equipment from the site, you must re-vegetate or otherwise
protect from erosion, those stream bank areas disturbed by the removal operation (such as access points).
For long-term operations (longer than 30 days) or for sites that will be periodically revisited as gravel is
deposited, access points must be appropriately constructed and maintained such that stream banks and access
roads are protected from erosion.
-5-
Special Conditions (continued):
j. Any aggregate, fines, and/or oversized material removed from the site must be placed in an upland, non-wetland site
that has been approved by the landowner.
k. You must not excavate in those areas authorized by this general permit during the dates specified on the attached
project authorization page(s) in the block identified as "Seasonal Restrictions". This time period restriction is for the
purpose of protecting spawning habitat and juveniles indigenous to the cited stream.
l. You must limit vehicles and other equipment to removal sites and existing crossings. Streams must be crossed
perpendicular to the stream. You must obtain written approval from the Corps of Engineers, Regulatory Branch,
before constructing any temporary or permanent stream crossing(s). Use of off road vehicles in streams is also
regulated under Missouri State Law (RSMo 1991 Section 304.013).
m. Fuel, oil and other wastes and equipment containing such wastes shall not be stored nor released at any location
between the high banks or in a manner such that they could enter the stream channel. You must dispose of such
materials at authorized locations.
n. No activity is authorized under this general permit which is likely to jeopardize the continued existence of a
threatened or endangered species or a species proposed for such designation, as identified under the Federal
Endangered Species Act, or which is likely to destroy or adversely modify the habitat of such species. See
Appendix II, paragraph No. 1 for permitting requirements if these species are likely to be present or their habitat would
be adversely modified.
o. No activity which may affect Historic properties listed, or eligible for listing, in the National Register of Historic
Places is authorized, until the District Engineer has complied with the provisions of 33 CFR 325, Appendix C. All
prospective permittees must notify the District Engineer if the excavation activity may affect any historic properties
listed, determined to be eligible, or which the prospective permittee has reason to believe may be eligible for listing on
the National Register of Historic Places, and shall not begin the activity until notified by the District Engineer that the
requirements of the National Historic Preservation Act have been satisfied and that the activity is authorized.
Information on the location and existence of historic resources can be obtained from the State Historic Preservation
Office and the National Register of Historic Places.
p. You must provide notification to the appropriate Corps of Engineers district, as specified in Appendix I, before you
initiate any gravel removal activity and receive written confirmation of authorization under this general permit from
the Corps of Engineers before you start any excavation or related operations.
q. A variance to any permit conditions will reviewed on a case-by-case basis and coordinated with the appropriate
federal and/or state agencies as necessary.
-6-
APPENDIX I
CRITERIA FOR AUTHORIZATION BY GENERAL PERMIT NWKGP-34M
1. The appropriate District Engineer has the discretion to require an individual permit on a case-by-case basis for any
activity authorized herein.
2. This general permit applies to the general public and governmental agencies when such activities are performed to
provide immediate construction materials or materials stockpiled in an upland area for private use or commercial sale.
Excavation and dredging activities occurring in flowing or open water, such as hydraulic dredging, are not included in
this authorization.
3. Private property owners are authorized to remove up to a total of 100 cubic yards of gravel per year from any single
gravel bar location on their property, for their personal use, without regard to special condition n. (notification
requirements). Excavation activities for personal use must comply with all conditions of this permit. This does not
relieve any personal use applicant from notifying the appropriate Corps district if the activity may affect a Federally
threatened or endangered species or its habitat (see Appendix II, Endangered Species Consultation). If you have any
questions concerning threatened and endangered species possibly occurring in your project area, you should contact
the appropriate Corps of Engineers district or the U.S. Fish and Wildlife Service.
4. The cumulative impacts of this general permit may be reevaluated at the discretion of the Corps of Engineers at any
time, but will be reevaluated at least every five (5) years.
5. APPLICANT NOTIFICATION REQUIREMENTS. (does not apply to personal use activities under 100 cubic
yards, see Appendix I, paragraph 3, above)
If you wish to perform work under the authority of this General Permit, you must provide notification to the
appropriate Corps of Engineers district before you initiate any gravel removal activity. You must submit the following
information in this notification:
(1) A completed application form ENG 4345, or equivalent information.
(2) A clearly marked site location map.
(3) A drawing showing the details of the proposed work (Plan and Cross-sectional views of each excavation area).
Include the access roads to the site in your project drawings.
(4) An operation plan which describes how you will conduct the work, details how impacts to the stream and
riparian area will be avoided and/or minimized, and measures to restore the site (including gravel bars, stream
banks, and riparian areas) following completion of excavation.
You must receive written confirmation of authorization under this general permit from the Corps of Engineers before
you start any excavation or related operations. Completed activities considered for authorization after-the-fact under
the general permit must conform to all conditions of the permit. After-the-fact authorization under this general permit
will generally be limited to one activity per applicant.
Note to Commercial Operators: As set forth in the Land Reclamation Act, Chapter 444.770.3. RSMo, this Section
10 and 404 general permit may satisfy your permitting requirements with the Missouri Department of Natural
Resources' Land Reclamation Program (LRP). If your activity is authorized by this general permit, the Corps of
Engineers will forward a copy of this permit to the LRP. You should contact the LRP at 573-751-4041 to determine
whether or not an LRP permit is also required.
APPENDIX II
CORPS REVIEW PROCEDURES FOR AUTHORIZATION BY GENERAL PERMIT NWKGP-34M
(For Corps Use Only)
1. ENDANGERED SPECIES CONSULTATION. The excavation activity must not be located in any waterbody
identified as containing potential habitat for any Federally listed threatened or endangered species unless, following
coordination with the U.S. Fish and Wildlife Service, a "no effect" or "not likely to adversely affect" determination is
agreed upon between the Corps of Engineers and the U.S. Fish and Wildlife Service. These waterbody locations will
be maintained by the Corps of Engineers and will be referenced for each individual activity.
Activities authorized under this general permit may affect the following species and/or habitat; Northern long-eared
bat, Arkansas darter, Neosho madtom, Niangua darter, Topeka shiner, Curtis' pearly mussel, Fat pocketbook, Neosho
mucket, Pink mucket pearly mussel, Scaleshell, Sheepnose, Spectaclecase, Winged mapleleaf, Ozark hellbender,
Indiana bat and Hine's emerald dragonfly. The Corps of Engineers will maintain a list of waters where the activities
authorized under this permit may affect such listed species or designated critical habitat. If the proposed activity is
located in any water included in this list, the following conditions must be met and will be coordinated by the
appropriate Corps of Engineers District:
a. Each proposed activity within the range of the above species must be coordinated with the U.S. Fish and
Wildlife Service and Missouri Department of Conservation to allow for timely, site specific evaluation and
concurrence that the activity, as conditioned under the general permit, is not likely to adversely affect listed
species or designated critical habitat. A search will be conducted utilizing the U.S. Fish and Wildlife Service
Information for Planning and Conservation (IPaC) and Missouri Natural Heritage Program (MNHP) survey
websites.
b. Additional project specific conditions must be imposed if, through timely informal consultation between the
Service and the Corps, they are determined to be necessary to avoid the likelihood of adverse effects to listed
species or designated critical habitat.
c. In the event that the likelihood of adverse effects to listed species or designated critical habitat cannot be
avoided, authorization will not be provided under the general permit until such time as: i) formal consultation
between the Service and the Corps is provided; ii) a non-jeopardy Biological Opinion is issued; and iii) the
terms and conditions of any associated Incidental Take Statement are incorporated as enforceable conditions to
the project authorization under the general permit.
2. PROJECT DOCUMENTATION AND COMPLIANCE. The authorized work must be documented on the
attached Project Authorization Page(s) by the Corps of Engineers. A separate Project Authorization Page must be
completed for each separate excavation site. This allows multiple copies of this page to be attached to the general
permit, thereby documenting site specific requirements for several excavation locations conducted by a single
applicant. The Project Authorization Page(s) also serves to document site specific variances from special conditions e.
and i. of the general permit or to add special conditions for protection of Federally listed species. A separate plan view
depicting the relative location of several sites in relation to one another may also be attached to clarify site number
locations. Also, these data will be used as a tool to insure compliance with the conditions of the general permit.
THIS ENTIRE PAGE WILL BE COMPLETED BY THE CORPS OF ENGINEERS
VERIFICATION OF NWKGP-34M PROJECT AUTHORIZATION
1.
Identification Number and/or Site No. (Assigned by Corps)
2.
Corps Approving Official (Not Valid Unless Signed)
3.
Applicant (Company or Name)
4.
Responsible Person (If Different from Applicant)
5.
Detailed Location Description (A Drawing on the Reverse Side May Also Be Used in Addition to This Block)
6.
Minimum Buffer Strip Distances
Approving Official
6a. Excavation Area to Water Line
feet
6b. Excavation Area to Bank/Bank Vegetation
feet
6c. Other (specify)
feet
7.
Excavation Depth Information
(Note: You must not excavate sand or gravel below the elevation of the water at the time of removal unless authorized by the Corps and
subject to review by federal or state agencies. If authorization allows excavation below the elevation of the adjacent stream bottom,
justification is required such as presence of bed rock to prevent head cutting, excessive bedload, or other appropriate reasons.)
8.
Season Restrictions
(You must not excavate during time frames specified below)
Restricted Excavation Start Date through End Date, inclusive (mm/dd/yy)
8a.
8b.
8c.
8d.
9.
Comments, Site Specific Conditions, etc.
Approving Official
COMPLIANCE CERTIFICATION
GENERAL PERMIT NWKGP-34M
Special Condition "a." of this permit document requires that you submit a signed certification regarding the
completed work and any required mitigation. This certification page satisfies this condition if it is provided
to the Kansas City District at the address shown at the bottom of this page upon completion of the project.
APPLICATION NUMBER:
NAME:
ADDRESS:
PROJECT LOCATION: (Waters of US name; Section, Township, Range; County name, Missouri; additional
location information.)
a. I certify that the authorized work was done in accordance with the Corps authorization, including any general
or specific conditions.
b. I certify that any required mitigation was completed in accordance with the permit conditions.
c. Your signature below, as permittee, indicates that you have completed the authorized project as certified in
paragraphs a and b above.
__________________________________
(Permittee)
Return this certification to:
U.S. Army Corps of Engineers
(Office address)
___________________________________
(Date)