RIP-RAP, BOAT DOCK, AND FILL IN CALCASIEU PARISH
NAME OF APPLICANT: Amanda Clark, 8 River Road, Lake Charles, Louisiana 70601.
LOCATION OF WORK: Calcasieu River, 6 and 8 River Road, in the community of Lake Charles, in Calcasieu Parish, Louisiana, as shown on the enclosed drawings.
Location: Latitude: 30°14ʹ50.74ʺ N / Longitude: -93°13ʹ52.20ʺ W, Hydrologic Unit Code: 08080206 – Calcasieu Basin.
The work described below was partially completed prior to obtaining a Department of the Army permit and was in violation of Section 301 of the Clean Water Act. All legal issues concerning the unauthorized work have been deferred.
CHARACTER OF WORK: Install two sections of approximately 297-foot long rip-rap and 60-foot long of rip-rap, repair an existing 20-foot wide by 25-foot long T-shaped dock, and place approximately 814 cubic yards of hauled-in fill material in an approximately 167-foot wide by 130-foot long area, 469 cubic yards of hauled-in fill material in an approximately 60-foot wide by 115-foot long area, and 117 cubic yards of rip-rap for bankline stabilization. After-the-fact work includes placing approximately 266 cubic yards of hauled-in fill material in an approximately 80-foot wide by 80-foot long area. A total of approximately 0.49 of an acre of jurisdictional emergent wetlands would be permanently impacted via project implementation. The purpose of the spoil placement within jurisdictional emergent wetlands is to elevate the low lying areas to existing shoreline levels and provide flood protection for both properties. The applicant agrees to compensate for wetland impacts by purchasing credits at a Department of the Army approved mitigation bank. The applicant may be required to fully or partially restore the project site to preproject conditions, if issuance of a permit is determined to be contrary to the overall public interest.