PROPOSED BAYOU FRANCOIS FLOODWAY PROJECT NEAR CLOUATRE DITCH

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

PROPOSED BAYOU FRANCOIS FLOODWAY PROJECT NEAR CLOUATRE DITCH, NEAR SORRENTO, LOUISIANA IN ASCENSION PARISH

NAME OF APPLICANT: East Ascension Parish Consolidated Gravity Drainage District, c/o ELOS Environmental, Inc., Attn: Mr. Rob Van Vrancken, 43177 East Pleasant Ridge Road, Hammond, Louisiana 70403.

LOCATION OF WORK: Located along and near the convergence of Bayou Francois and Clouatre Ditch, in Section 16, Township 10 South, Range 3 East, within the Lake Pontchartrain Basin, near Sorrento, Louisiana, in ASCENSION Parish, as shown on the enclosed drawings (Latitude 30.20718 N Longitude -90.86745 W).

CHARACTER OF WORK: The applicant has requested a Department of the Army authorization to clear, grade, excavate, and deposit fill material to construct an approximate 1,100-foot x 150-foot wide x 1.5-foot deep ditch near the convergence of Bayou Francois and Clouatre Ditch. The applicant has stated that the proposed project purpose to help alleviate backwater flooding caused by heavy rainfall events which causes Bayou Francois to revert flow to Clouatre Ditch causing severe flooding to residential and businesses along Clouatre Ditch. The project is to provide an alternate route for floodwater to drain from Clouatre Ditch to Bayou Francois during rising water levels. According to the applicant, during normal water conditions, the proposed floodway will remain above the mean water level and Clouatre Ditch will maintain its natural route into Bayou Francois. Approximately 473 cubic yards of stone filled mats would be placed as rip rap to armor and protect existing underground pipelines. Approximately 7,179 cubic yards of native material would be excavated and placed along an existing upland spoil bank located along Bayou Francois. Approximately 2.0 acres of jurisdictional swamp would be directly impacted by ditch excavation and approximately 0.18 acre of jurisdictional wetlands would be directly impacted as a result of stone mat placement. The applicant has stated that the project will only cause temporary impacts to wetlands and is proposing to plant wetland tree species along the floodway once construction has been completed. The applicant is requesting a one year growing season before impacts are assessed.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas