Lake of the Ozarks - Reissuance of General Permit GP-38M - Shoreline Development Activities. The U.S. Army Corps of Engineers, Kansas City District has reissued GP-38M for shoreline development activities at the Lake of the Ozarks under authority of Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) and Section 404 of the Clean Water Act (33 USC 1344). This GP is issued and is in effect for 5 years, from July 5, 2016 until July 5, 2021, unless revoked or specifically extended.
Lake of the Ozarks - Reissuance of General Permit GP-38M - Shoreline Development Activities. The U.S. Army Corps of Engineers, Kansas City District has reissued GP-38M for shoreline development activities at the Lake of the Ozarks under authority of Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) and Section 404 of the Clean Water Act (33 USC 1344). This GP is issued and is in effect for 5 years, from July 5, 2016 until July 5, 2021, unless revoked or specifically extended.
PUBLIC NOTICE
Permit No. NWKGP-38M
Issue Date: July 5, 2016
US Army Corps
of Engineers
Kansas City District
______________________________________________________________________________
LAKE OF THE OZARKS
REISSUANCE OF GENERAL PERMIT 38 MISSOURI
SHORELINE DEVELOPMENT ACTIVITIES
The U.S. Army Corps of Engineers, Kansas City District HAS REISSUED General Permit
NWKGP-38M (GP-38M, GP) for shoreline development activities at the Lake of the Ozarks,
under authority of Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) and
Section 404 of the Clean Water Act (33 USC 1344).
Duration of this General Permit: This GP is issued and is in effect for five (5) years, from July 5,
2016, until July 5, 2021, unless revoked or specifically extended.
Notification Procedures: The Corps of Engineers (Corps) has coordinated the GP operating and
management procedures with Ameren Missouri, whereby Ameren Missouri assumes the role as
the agency of notification and the responsibilities for issuing verification that a particular project
falls within the limits and conditions of the GP. The Corps will monitor this verification process
and applicant compliance with the permit conditions, and will coordinate enforcement of the
permit conditions.
Individuals desiring to undertake work authorized by this general permit must notify and receive
verification from Ameren Missouri. You must contact Ameren Missouri, Shoreline Management
Office, 3 Willmore Lane, P.O. Box 993, Lake Ozark, Missouri 65049, telephone 573-365-9208.
The application must include detailed drawings with dimensions (location map, plan view, cross
sections), with elevations specified in Union Electric datum (UED), and include sufficient
information to determine if the proposed work conforms to the criteria and conditions of the GP.
Applicants unfamiliar with preparing drawings and identifying the Ordinary High Water Mark
(OHWM) are encouraged to contract with a qualified consultant. Applicants are also encouraged
to provide photographs (with date of photograph and camera direction recorded) with their
application as this may facilitate quicker review of the application.
If Ameren Missouri determines that the proposed work meets the provisions of the GP, and no
extraordinary conditions exist that warrant evaluation as a Department of the Army (DA)
individual permit, the proponent will be notified to proceed subject to compliance with any
verification special conditions and/or mitigation requirements. All activities verified as
authorized by this GP must comply with the general and special conditions of the enclosed copy
of the GP.
APPLICANT: General Public
PROJECT LOCATION: Lake of the Ozarks (Lake); the area lakeward of the OHWM, elevation
658.5 feet UED, in Benton, Camden, Miller, and Morgan Counties, Missouri. Work in adjacent
wetlands and tributaries of the Lake, landward/upstream of the OHWM, is not authorized by this
permit, except for specific temporary impacts.
AUTHORITY: Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) and
Section 404 of the Clean Water Act (33 USC 1344).
ACTIVITY: Proposed and/or Completed Work: The excavation and/or discharge of dredged
or fill material for the following structures or projects, including the structures, subject to the
general and special conditions of this General Permit (GP), and the criteria in the attached
appendices. (Note: Appendices are permit attachments.)
Appendix I
Appendix II
Appendix III
Appendix IV
Appendix V
Appendix VI
Appendix VII
Bulkheads/Seawalls and Bank Stabilization
Boat Ramps
Miscellaneous Structures and Activities
Dredging/Excavation for Docks, Access Channels, and Structures
Utilities
Fish Habitat
Sediment and Debris Removal
ADDITIONAL INFORMATION: Additional information about this GP may be obtained by
contacting Mr. Mel B. Stanford, Regulatory Project Manager; U.S. Army Corps of Engineers,
Truman Regulatory Satellite Office, 15837 Truman Road, Warsaw, Missouri 65355; at telephone
816-389-3981, (FAX 660-438-6909), or via e-mail at mel.b.stanford@usace.army.mil.
A copy of the permit is posted and may be obtained from our website at:
http://www.nwk.usace.army.mil/Missions/Regulatory-Branch/General-Permits/.
Enclosure
DEPARTMENT OF THE ARMY PERMIT
Permittee General Public
Permit No. NWKGP-38M, Shoreline Development Activities
Issuing Office U.S. Army Engineer District, Kansas City
NOTE: The term "you" and its derivatives, as used in this permit, means the permittee or any future transferee.
The term "this office" refers to the appropriate district or division office of the Corps of Engineers having
jurisdiction over the permitted activity or the appropriate official of that office acting under the authority of the
commanding officer.
You are authorized to perform work in accordance with the terms and conditions specified below, and with the
plans and drawings attached hereto which are incorporated in and made a part of this permit.
Project Description: Proposed and/or Completed Work: The excavation and/or discharge of dredged or
fill material for the following structures or projects, including the structures, subject to the general and
special conditions of this General Permit (GP), and the criteria in the attached appendices.
Appendix I
Appendix II
Appendix III
Appendix IV
Appendix V
Appendix VI
Appendix VII
Bulkheads/Seawalls and Bank Stabilization
Boat Ramps
Miscellaneous Structures and Activities
Dredging/Excavation for Docks, Access Channels, and Structures
Utilities
Fish Habitat
Sediment and Debris Removal
Project Location: Lake of the Ozarks (Lake); lakeward of the ordinary high water mark (OHWM),
elevation 658.5 feet Union Electric datum (UED), in Benton, Camden, Miller, and Morgan Counties,
Missouri. Work in adjacent wetlands and tributaries of the Lake, landward/upstream of the OHWM, is
not authorized by this permit, except for specific temporary impacts.
Permit Conditions:
General Conditions:
1. The time limit for completing the work authorized ends on 2 years from each permit verification. If you find
that you need more time to complete the authorized activity, submit your request for a time extension to this office
for consideration at least one month before the above date is reached.
2. You must maintain the activity authorized by this permit in conformance with the terms and conditions of this
permit. You are not relieved of this requirement if you abandon the permitted activity, although you may make a
good faith transfer to a third party in compliance with General Condition 4 below. Should you wish to cease to
maintain the authorized activity or should you desire to abandon it without a good faith transfer, you must obtain a
modification of this permit from this office, which may require restoration of the area.
3. If you discover any previously unknown historic or archeological remains while accomplishing the activity
authorized by this permit, you must immediately notify this office of what you have found. We will initiate the
Federal and state coordination required to determine if the remains warrant a recovery effort or if the site is eligible
for listing in the National Register of Historic Places.
ENG FORM 1721, Nov 86
EDITION OF SEP 82 IS OBSOLETE
(33 CFR 325 (Appendix A))
4. If you sell the property associated with this permit, you must obtain the signature of the new owner in the space
provided and forward a copy of the permit to this office to validate the transfer of this authorization.
5. If a conditioned water quality certification has been issued for your project, you must comply with the
conditions specified in the certification as special conditions to this permit. For your convenience, a copy of the
certification is attached if it contains such conditions.
6. You must allow representatives from this office to inspect the authorized activity at any time deemed necessary
to ensure that it is being or has been accomplished in accordance with the terms and conditions of your permit.
Special Conditions: See continuation sheets, pages 4 through 7 of this document.
Further Information:
1. Congressional Authorities: You have been authorized to undertake the activity described above pursuant to:
(X) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403).
(X) Section 404 of the Clean Water Act (33 U.S.C. 1344).
( ) Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972 (33 U.S.C. 1413).
2. Limits of this authorization.
a. This permit does not obviate the need to obtain other Federal, state, or local authorization required by law.
b. This permit does not grant any property rights or exclusive privileges.
c. This permit does not authorize any injury to the property or rights of others.
d. This permit does not authorize interference with any existing or proposed Federal project.
3. Limits of Federal Liability. In issuing this permit, the Federal Government does not assume any liability for the
following:
a. Damages to the permitted project or uses thereof as a result of other permitted or unpermitted activities or from
natural causes.
b. Damages to the permitted project or uses thereof as a result of current or future activities undertaken by or on
behalf of the United States in the public interest.
c. Damages to persons, property, or to other permitted or unpermitted activities or structures caused by the
activity authorized by this permit.
d. Design or construction deficiencies associated with the permitted work.
e. Damage claims associated with any future modification, suspension, or revocation of this permit.
4. Reliance on Applicant's Data: The determination of this office that issuance of this permit is not contrary to the
public interest was made in reliance on the information you provided.
5. Reevaluation of Permit Decision. This office may reevaluate its decision on this permit at any time the
circumstances warrant. Circumstances that could require a reevaluation include, but are not limited to, the
following:
2
a. You fail to comply with the terms and conditions of this permit.
b. The information provided by you in support of your permit application proves to have been false, incomplete,
or inaccurate (See 4 above).
c. Significant new information surfaces which this office did not consider in reaching the original public interest
decision.
Such a reevaluation may result in a determination that it is appropriate to use the suspension, modification, and
revocation procedures contained in 33 CFR 325.7 or enforcement procedures such as those contained in 33 CFR
326 .4 and 3 26. 5. The referenced enforcement procedures provide for the issuance of an administrative order
requiring you to comply with the terms and conditions of your permit and for the initiation of legal action where
appropriate. You will be required to pay for any corrective measures ordered by this office, and if you fail to
comply with such directive, this office may in certain situations (such as those specified in 33 CFR 209 .170)
accomplish the corrective measures by contract or otherwise and bill you for the cost.
6. Extensions. General condition 1 establishes a time limit for the completion of the activity authorized by this
permit. Unless there are circumstances requiring either a prompt completion of the authorized activity or a
reevaluation of the public interest decision, the Corps will normally give favorable consideration to a request for an
extension of this time limit.
Your signature below, as permittee, indicates that you accept and agree to comply with the terms and
conditions of this permit.
GENERAL PUBLIC- SIGNATURE NOT REQUIRED
(PERMITTEE)
(DATE)
This permit becomes effective when the Federal official, designated to act for the Secretary of the Army,
has signed below.
5 July 2016
(DATE)
(DISTRICT COMMANDER)
BY: MARK. D. FRAZIER
Chief, Regulatory Branch
Operations Division
When the structures or work authorized by this permit are still in existence at the time the property is transferred,
the terms and conditions of this permit will continue to be binding on the new owner(s) of the property. To
validate the transfer of this permit and the associated liabilities associated with compliance with its terms and
conditions, have the transferee sign and date below.
(TRANSFEREE)
(DATE)
3
Special Conditions:
a. You must complete, sign and return the attached "Compliance Certification" to the Corps of
Engineers (Corps) after you complete the authorized work and any required mitigation. Your signature
will certify that you completed the work in accordance with this General Permit (GP), including general
and specific conditions, and that any required mitigation was completed in accordance with the GP
conditions. If the work completed is less than that authorized, you must provide a drawing describing the
extent of the work completed.
b. If any part of the authorized work is performed by a contractor, before starting work you must discuss
the terms and conditions of this GP with the contractor; and, you must give a copy of this entire GP to the
contractor. The permittee remains responsible for ensuring compliance with all aspects of this GP.
c. You must use clean, uncontaminated materials for fill in order to minimize excessive turbidity by
leaching of fines, as well as to preclude the entrance of deleterious and/or toxic materials into the waters
of the United States by natural runoff or by leaching. Placement of unprotected earthen and gravel fill,
broken concrete where more than 25 percent is 12 inches in diameter or less, concrete rubble with
exposed rebar, tires, railroad ties, vehicles/vehicle bodies, construction/demolition debris, asphalt, and
similar materials are not authorized by this GP.
d. You must dispose of excess concrete and wash water from concrete trucks and other concrete mixing
equipment in a non-wetland area above the ordinary high water mark (OHWM) and at a location where
the concrete and wash water cannot enter the water body or an adjacent wetland area. Excess concrete
may not be used to grout existing riprap or to pave existing shoreline, lakeward of the OHWM, under this
GP authorization.
e. You must excavate, dredge and/or fill in the watercourse in a manner that will minimize increases in
suspended solids and turbidity which may degrade water quality and damage aquatic life outside the
immediate area of operation. Also, care must be taken to keep machinery out of the Lake to the
maximum extent practicable.
f. You must immediately remove and properly dispose of all debris during every phase of the project in
order to prevent the accumulation of unsightly, deleterious and/or toxic materials in or near the water
body.
g. You must not dispose of any construction debris or waste materials below the OHWM of any water
body, in a wetland area, or at any location where the materials could be introduced into the water body or
an adjacent wetland as a result of runoff, flooding, wind, or other natural forces. All excavated lakebed
sediments must be placed and stabilized at a location landward of elevation 662.0 feet UED, where the
material cannot enter any water body, including wetlands, by erosion.
h. You must store all construction materials, equipment, and/or petroleum products, when not in use,
above anticipated high water levels, and in such a way that they shall not enter waters of the United States
(U.S.). Petroleum products spilled into any water or on the banks where the material may enter waters of
the U.S. should be immediately cleaned up and disposed of properly. Any such spills of petroleum
should be reported as soon as possible, but no later than 24 hours after discovery to MDNR's
Environmental Emergency Response number at (573) 634-2436.
i. You must restrict the clearing of timber and other vegetation to the absolute minimum required to
accomplish the work. Clearing, grading and replanting should be planned and timed so that only the
smallest area necessary is in a disturbed, unstable or un-vegetated condition.
4
Special Conditions (continued):
j. You must not excavate or discharge fill or dredged material lakeward of the OHWM from March 15 to
June 15 unless you obtain written approval in advance from the Corps, Regulatory Branch or Ameren
Missouri, as specified in condition "r" below. In addition, you must excavate during periods of low water
levels.
Note: Placement of riprap as a bank stabilization technique (without excavation) is exempted from this
condition unless specifically stated on the project verification sheet.
k. Upon completion of earthwork operations, you must implement Best Management Practices and seed,
replant or otherwise protect from erosion all fills in the water or on shore, and other areas on shore
disturbed during construction. If seeding does not successfully vegetate the disturbed areas by the end of
the first growing season, you must implement alternate measures, such as placing riprap, slope terracing
with untreated timbers, gabions or concrete blocks, or additional vegetative plantings, to protect the
disturbed areas from further erosion. You must contact the Corps or Ameren Missouri, as specified in
condition "r" below, prior to beginning work on any additional erosion control measures so that a
determination can be made whether further authorization is required.
l. For the construction, repair, or maintenance of any structure in or over the Lake, you must use lumber
products treated with wood preservatives in strict compliance with the Registration Documents issued by
the U.S. Environmental Protection Agency (USEPA) under the Federal Insecticide, Fungicide and
Rodenticide Act (FIFRA) and in accordance with standards issued by American Wood Protection
Association or the International Code Council. The prohibited products have been determined to release
toxins into the water when placed in direct contact.
m. You must not use the backfill area of the bulkhead/seawall, or any other authorized fill area, for on-site
sewage disposal structures. You must contact the Missouri Department of Natural Resources and the
Department of Health and Senior Services, which may refer you to a county or local agency, for current
laws and regulations regarding sewer and septic system installation.
n. All work must be conducted such that it does not interfere with access to and use of any existing
authorized structure. Structures that obstruct or that constitute a hazard to navigation are not authorized
by this GP.
o. An Ameren Missouri permit must be obtained for any structure/fill/excavation on projects lands. This
GP does not authorize any structure/fill/excavation for which the Corps or Ameren Missouri previously
denied authorization or for which the structure/fill/excavation is not in compliance with the conditions of
a Department of the Army (DA) permit authorization or verification (Nationwide permit (NWP), GP,
Letter of Permission (LOP), or Standard permit (SP)), or an Ameren Missouri approval (in accordance
with Ameren Missouri's Shoreline Management Guidelines). Such structures/fills/excavations may be
subject to enforcement action in accordance with Ameren Missouri realty rights.
Structures/fills/excavations that otherwise would be authorized by this GP, but that were constructed on
the same property in association with, and integral to, any other unauthorized work (violation), such as
unpermitted excavation in the Lake, are not authorized by this GP until the violation is resolved.
p. No activity is authorized under this GP which is likely to jeopardize the continued existence of a
threatened or endangered species or a species proposed for such designation, as identified under the
Federal Endangered Species Act (ESA), or which is likely to destroy or adversely modify the habitat of
such species. Permittees shall notify the Corps if any listed species or designated critical habitat might be
affected or is in the vicinity of the project, or is located in the designated critical habitat. Authorization of
an activity by this GP does not authorize the "take" of a threatened or endangered species as defined
under the ESA. In the absence of a separate authorization from the U.S. Fish and Wildlife Service, both
lethal and non-lethal "takes" of protected species are in violation of the ESA.
5
Special Conditions (continued):
q. No activity which may affect Historic properties listed, or eligible for listing in the National Register of
Historic Places is authorized, until the District Commander has complied with the provisions of 33 CFR
325, Appendix C. All prospective permittees must notify the Corps if the activity may have the potential
to affect any historic properties listed, determined to be eligible to be listed, or which the prospective
permittee has reason to believe may be eligible for listing on the National Register of Historic Places, and
shall not begin the activity until notified by the Corps that the requirements of the National Historic
Preservation Act have been satisfied and that the activity is authorized. Information on the location and
existence of historic resources can be obtained from the State Historic Preservation Office and the
National Register of Historic Places.
r. You must provide written notification to Ameren Missouri or the Corps, and receive written verification
of authorization by this GP, before you begin any work in the Lake. No existing work is authorized until
written verification is provided by Ameren Missouri or the Corps.
s. Variances from permit conditions and construction criteria may be authorized by this GP at the issuing
authority's discretion, subject to both Ameren Missouri and Corps concurrence to accommodate factors,
including but not limited to, rock outcrops, smooth transitions to adjacent authorized structures or other
special site circumstances. This applies to all appendices.
t. In accordance with the Water Resources Development Act of 1976, the Corps does not regulate floating
and fixed, private and commercial boat docks, and dock mooring cables and access walkways, on the
Lake, provided the docks were placed so as not to interfere with navigation. However, Ameren Missouri
approval is required for all docks at the Lake.
u. Bridges over navigable waters of the United States, such as the Lake, are not regulated under Section
10 of the Rivers and Harbors Act. However, the discharge of fill material in any water of the United
States for bridges requires Corps authorization under Section 404 of the Clean Water Act. Ameren
Missouri approval is required for all bridges in or over the Lake.
v. The maintenance, repair, and restoration of existing and proposed structures or fill is authorized,
including minor deviations, provided there is no significant change in the structure.
w. Structures completed prior to December 18, 1968, and discharges of dredged or fill material in waters
of the United States prior to July 1, 1977, are authorized by a Nationwide Permit as cited under Activities
Occurring Before Certain Dates (33 CFR 330.3).
x. Impacts to the Lake of the Ozarks should be avoided or minimized where possible. All approved
encroachments may be subject to the completion of mitigative measures such as rock blankets, anchored
cedar trees or other fish habitat, and/or utilize an approved mitigation provider as required on the project
verification sheet. Mitigation requirements for dredging projects may include the installation of a single
anchored cedar tree or other fish attraction device for each 10 cubic yards of excavation material removed
from the Lake. The trees must have an approximately four-inch diameter trunk, anchored with a
noncorrosive material of concrete or rock, and placed as close to the impact area as possible, where the
lakebed is at or lower than elevation 647.0 feet UED. If there are no suitably deep areas near the impact
area, the permittee must contact the Fisheries Management Staff of the Missouri Department of
Conservation, Camdenton Service Center (telephone 573-346-2210) for alternative locations. Alternate
mitigation measures to replace or augment may be required, as noted on the project verification sheet.
NOTE: This permit does not authorize work in adjacent wetlands or in tributaries to the Lake of the
Ozarks upstream, or landward of the OHWM, except for limited, temporary site access as described in
Appendix IV.
6
Special Conditions (continued):
y. The permittee understands and agrees that, if future operations by the United States require the removal,
relocation, or other alteration, of the structure or work herein authorized, or if, in the opinion of the Secretary
of the Army or his authorized representative, said structure or work shall cause unreasonable obstruction to
the free navigation of the navigable waters, the permittee will be required, upon due notice from the Corps of
Engineers, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to
the United States. No claim shall be made against the United States on account of any such removal or
alteration.
7
COMPLIANCE CERTIFICATION
Special condition "a" of this permit document requires that you submit a signed certification
regarding the completed work and any required mitigation. This certification page satisfies this
condition if it is provided to the Kansas City District at the address shown at the bottom of this page
upon completion of the project.
APPLICATION NUMBER (assigned by Kansas City District or Ameren Missouri): ____________________
APPLICANT NAME: ________________________________________________________________
ADDRESS: _________________________________________________________________________
____________________________________________________________________________________
PROJECT LOCATION: In the Lake of the Ozarks, at lake mile
, Cove/Arm
,
subdivision and lot
; in the NE NW SE SW (CIRCLE ONE) of Section , Township
north, Range
west,
County, Missouri.
PRIMARY CONTRACTOR NAME/ADDRESS: _________________________________________
____________________________________________________________________________________
a. I certify that the authorized work was done in accordance with the Corps GP authorization, including
any general or specific conditions.
b. I certify that any required mitigation was completed in accordance with the permit conditions.
c. I certify that I have obtained the required permit(s) from Ameren Missouri.
d. Your signature below, as permittee, indicates that you have completed the authorized project as
certified in paragraphs "a" and "b" above.
_______________________________________
(PERMITTEE)
______________________________
(DATE)
List the Name, Address and Telephone No. of all other contractors involved in the project below:
Return this certification to both of the following offices:
U.S. Army Corps of Engineers
Truman Regulatory Satellite Office
15837 Truman Road
Warsaw, Missouri 65355
Ameren Missouri
Shoreline Management Office
3 Willmore Lane, P.O. Box 993
Lake Ozark, Missouri 65049
8
APPENDIX I
Bulkheads/Seawalls and Bank Stabilization
A. EXISTING STRUCTURES and FILL, including but not limited to:
1. The Corps, at its discretion, may investigate any bulkhead/seawall, or other structure or fill
that was placed in the Lake that is unauthorized and resolve the violation according to rules in 33
CFR 326. The resolution may include in some cases an after-the-fact authorization, area
restoration, corrective or mitigative measures, or legal action. The Corps may also conduct
compliance inspections of the project area.
2. The previous placement of clean rock or riprap in a revetment for bank stabilization, of a size
and quality capable of withstanding expected erosional forces, including minor excavation or
grading to prepare a base for the revetment, is authorized by this GP, provided the work did not
fill, drain, or prevent the flow of water into any adjacent wetlands. Clean concrete rubble that
has been broken to a well-graded mix of pieces with all exposed reinforcing metal removed may
be used with or instead of rock.
B. PROPOSED STRUCTURES and FILL, including but not limited to:
1. The proposed placement of clean rock or riprap in a revetment for bank stabilization, of a
suitable size to withstand expected erosional forces, including minor excavation or grading to
prepare a base for the revetment, is authorized by this GP, provided the work will not fill, drain,
or prevent the flow of water into any adjacent wetlands. Clean concrete rubble that has been
broken to a well-graded mix of pieces with all exposed reinforcing metal removed may be used
with or instead of rock.
2. Proposed bulkheads/seawalls require a minimum of 24 inches of vertical erosion, constructed
such that the most lakeward face of the footing or wall is no more than 3 feet lakeward of the toe
of the bank, and where the construction will not fill, drain or prevent the flow of water into any
adjacent wetlands, are authorized by this GP.
3. This GP does not authorize any bulkheads/seawalls lakeward of the OHWM, where the walls
could be, using standard construction methods, constructed such that the lakeward toe of the
footing is at or above the OHWM.
4. Minor deviations from criteria 2 and 3 above may be authorized by this GP at the issuing
authority's discretion, subject to both Ameren Missouri and Corps concurrence, to accommodate
rock outcrops, smooth transitions to adjacent authorized structures or other special site
circumstances.
5. All approved encroachments may be subject to the completion of mitigative measures such as
rock blankets, anchored cedar trees or other fish habitat, and/or utilize an approved mitigation
provider as required on the project verification sheet.
APPENDIX II
Boat Ramps
EXISTING and PROPOSED, including but not limited to:
1. Boat ramps or launching tracks constructed of concrete, brick, stone, gravel, and/or similar
materials are authorized by this GP subject to the following criteria:
a. The discharge of fill material or structural components lakeward of the OHWM does not
exceed 50 cubic yards of concrete, rock, crushed stone or gravel into forms; precast
concrete slabs or bricks; steel rods, rails, and other approved construction materials. A
variance may be authorized.
b. The boat ramp does not exceed 30 feet-wide.
c. No more than one boat ramp is constructed per single family residence or for any single
property having 4 housing units or less (e.g., apartments, condominiums, and extended
family complexes). For larger developments, no more than one boat ramp per 100 linear
feet of lake frontage is authorized.
d. Excavation is limited to the area necessary for site preparation and all excavated material
is disposed of in an upland area landward of an authorized bulkhead/seawall on the
subject property, or placed and stabilized at a location landward of elevation 662.0 feet
UED, such that the material cannot enter any water body, including wetlands, by erosion.
e. No material is placed in wetlands or shallow water areas of the Lake that typically
support aquatic vegetation for any part of the year.
f. Dredging/excavation to provide access to deeper water from a proposed boat ramp may
be authorized by this GP. Criteria for authorization of dredging/excavation to restore
access to existing boat ramps are in Appendix IV.
g. The boat ramp must be well maintained and monitored for erosive undermining to ensure
safe use. Boat ramps determined to be a hazard must be repaired or removed from the
Lake and the shoreline restored.
h. A variance may be authorized for existing and proposed boat ramps, including but not
limited to consideration for private or commercial use, size, location, and construction
materials.
2. All approved encroachments may be subject to the completion of mitigative measures such as
rock blankets, anchored cedar trees or other fish habitat, and/or utilize an approved mitigation
provider as required on the project verification sheet.
APPENDIX III
Miscellaneous Structures and Activities
EXISTING and PROPOSED, including but not limited to:
1. EXISTING: This GP authorizes, including but not limited to, existing recreational decks,
fixed docks, wharfs, fishing piers/docks, approved handicap accessible structures, breakwaters,
bulkhead/seawall supports, mooring piles, small pedestrian/recreational bridges, steps,
sidewalks/walkways, walkway piers, sand beaches with retaining structures, roads and road
crossings; minor recreational, ornamental, other similar and associated structures. The Corps, at
its discretion, may investigate any bulkhead/seawall, or other structure or fill that was placed in
the Lake that is unauthorized and resolve the violation according to rules in 33 CFR 326. The
resolution may include in some cases an after-the-fact authorization, area restoration, corrective
or mitigative measures, or legal action.
2. PROPOSED: This GP authorizes, including but not limited to, the proposed construction of
fixed docks, fishing piers/docks, handicap accessible structures (subject to an approved variance
of the conditions below), breakwaters, bulkhead/seawall supports, mooring piles, small
pedestrian/recreational bridges, steps, dock walkways, walkways perpendicular to the shoreline,
walkway piers, sand beaches with retaining structures; minor recreational, ornamental, and other
similar and associated structures; are subject to the following conditions:
a. For concrete or solid-fill structures; including but not limited to anchors, walkways,
wharfs and associated structures; the volume of fill placed below the OHWM must not
exceed 10 cubic yards, and the structure must be no more than 8 feet-wide.
b. For structures on piles; including but not limited to fixed docks, walkways, wharfs and
associated structures; or otherwise cantilevered over the Lake, the bottom surface of the
structure must be at elevation 660.0 feet UED, or higher.
c. Fishing piers must be 6 feet or less in width, and must not extend more than 30 feet
lakeward of the OHWM perpendicular from the shoreline.
d. Sand beaches may be maintained as needed including the placement of additional sand.
Sand lost lakeward from a beach may be recovered and replaced on the beach.
e. The size, extent, and location of all structures on a single property must be in
conformance with this GP and approved by Ameren Missouri in accordance with the
Ameren Missouri Shoreline Management Permit requirements.
f. Breakwaters, constructed as an integral part of an Ameren Missouri approved boat dock,
are considered part of the dock and do not require Corps permit authorization. For other
breakwaters, approval must be obtained from the joint Ameren Missouri/Corps permit in
accordance with Ameren Missouri Shoreline Management Permit requirements.
g. Bridges must be constructed in such a way that they do not impede navigation, prohibit
boat passage, or restrict anglers.
APPENDIX III (continued, page 2 of 2)
Miscellaneous Structures and Activities
3. Permittees must install and maintain lighting, signage, or buoys as recommended or required
by the Missouri State Water Patrol, Ameren Missouri Shoreline Management Permit
requirements, and other agencies with jurisdiction as applicable.
4. Utility connections to approved structures must be in accordance with applicable building
codes and industry standards in accordance with Ameren Missouri Shoreline Management
Permit requirements and other agencies with jurisdiction as applicable.
5. All structures must be well maintained and must be repaired or removed from the Lake within
6 months of damage by storm, high or low water, ice, collision, or other event.
6. This GP does not authorize construction lakeward of the OHWM or the permanent mooring
in the Lake of the Ozarks, of any structure that will be used as living quarters or for overnight
habitation.
7. Fences constructed lakeward of the OHWM are not authorized by this GP.
APPENDIX IV
Dredging/Excavation for Docks, Access Channels, and Structures
EXISTING and PROPOSED, including but not limited to:
1. Restoring use of or access to authorized boat ramps and boat docks existing prior to March
30, 2007: Excavation is limited to the exact authorized foot print of the dock. The sides of
excavation area must be graded to have a final slope of 1 vertical (V) on 3 horizontal (H).
Variances in the requirement for side slopes of 1V on 3H will be granted or required where
completion of the grading would undermine the structural integrity of any permitted structure
such as bulkheads/seawalls and piers, or to prevent the encroachment into or erosion of wetlands,
vegetated shallows or other environmentally sensitive areas.
2. Dredging/excavation associated with authorized boat ramps and boat docks permitted or
installed after March 30, 2007 (see attached typical plan view and cross sectional drawing):
Excavation for docks permitted or installed after 2007 is limited to 900 square feet, in an area
where the existing lakebed for the entire proposed excavation area is elevation 655.5 feet UED or
deeper, and in areas where the excavation may be accomplished such that the excavation,
including required side slopes of 1V on 3H, will occur no closer than 25 feet to the OHWM. An
approved variance to the 900 square feet limit is allowed for community docks.
3. Excavation must not be conducted any deeper than elevation 652.0 feet UED, except when
approved on the GP verification sheet for the operation of a boat lift. Variances for boat lift
operation will allow excavation to a bottom limit of 650.0 feet UED, and are limited to the
absolute minimum area required for normal lift operation.
4. Access channel excavation for access to docks is limited to a single channel in any narrow
cove, and no permittee shall have exclusive use of any excavated access channel. Where
possible, the channel must be centered over the deepest existing channel in the cove. Channel
width is limited to 15 feet-wide with a channel bottom elevation of 652.0 feet UED. Channel
side slopes must be graded to have a final slope of between 1V on 2H and 1V on 3H. The
transition zone between the 15 foot wide channel and authorized docks must be no longer than
the width of the dock. Variances in location or alignment may be granted or required where the
variance would address substantial public interests or where the variance would minimize
adverse impacts to the aquatic ecosystem.
5. Access channel excavation for access to boat ramps must be no deeper than the lowest
elevation of the boat ramp, or elevation 652.0 feet UED, whichever is higher. This GP does not
authorize the excavation of access channels for boat ramps constructed after the issuance of this
GP, where the preconstruction lakebed elevation is 655.5 feet UED, or higher. Channel width is
limited to the width of the boat ramp, or 15 feet, whichever is narrower. Channel side slopes
must be graded to have a final slope of between 1V on 2H and 1V on 3H. A variance to these
conditions may be approved depending upon site conditions.
6. All dredged or excavated material must be placed in an upland area, above the elevation 662
feet UED contour, where and in such a manner that it will not re-enter the Lake. Large woody
debris providing aquatic habitat should not be removed unless it poses a navigational or other
safety hazard. The proposed excavation or disposal of dredged material must not promote the
erosion of wetland areas and excavation is prohibited in wetlands and vegetated shallows.
APPENDIX IV (continued, page 2 of 3)
Dredging/Excavation for Docks, Access Channels, and Structures
7. The temporary placement of fill in the Lake, adjacent wetlands, or any tributary to the Lake,
for the construction of an access road to the excavation area may be authorized. Where the
lakebed sediments will not support the excavation equipment, removable mats may be used. Mat
use is recommended for all excavation projects to minimize adverse impacts to the lakebed
habitat. Only the minimum amount of excavation and fill necessary to construct the temporary
road is authorized, the fill must be removed upon completion of the project and the area returned
to previous contours. The use of rock fill is authorized for temporary access road provided it is
removed following the excavation activity or spread out over the existing contours to provide
shallow water habitat.
8. Each verification of this GP authorizes the one-time excavation of the area on the verification
sheet. This GP does not authorize excavation of the same work area within three years following
the completion of any authorized excavation project.
9. All approved structures and encroachments may be subject to the completion of mitigative
measures such as rock blankets, anchored cedar trees, or other fish habitat, and/or utilize an
approved mitigation provider as required on the project verification sheet.
APPENDIX IV (continued, page 3 of 3)
Dredging/Excavation for Docks, Access Channels, and Structures
APPENDIX IV
Dredging and/or Excavation
Boat Dock, Boat Hoist, and Access Channel
BOAT DOCK AREA
BOAT HOIST AREA
SIDE SLOPES
25'
ACCESS CHANNEL
MIN
B
OHWM
A
A
B
LAKE OF THE OZARKS
TYPICAL PLAN VIEW
BOAT DOCK, HOIST, AND ACCESS CHANNEL EXCAVATION AREAS
OHWM
EL 655.5' MAX
EL 650.0' MAX
EL 652.0' MAX
LAKE BED
25'
MIN
BOAT HOIST AREA
BOAT DOCK AREA
SIDE SLOPES
1V ON 3H
CROSS SECTION A - A
BOAT DOCK AND BOAT HOIST EXCAVATION AREAS
LAKE BED
15' MAX
SIDE SLOPES
1V ON 2-3H
CROSS SECTION B - B
BOAT DOCK ACCESS CHANNEL EXCAVATION AREA
NOTE: Drawings Not-To-Scale
EL 655.5' MAX
EL 652.0' MAX
KEY: EL ELEVATION, UNION ELECTRIC DATUM (UED)
OHWM ORDINARY HIGH WATER MARK, ELEVATION 658.5' UED
MAX MAXIMUM
MIN - MINIMUM
APPENDIX V
Utilities
EXISTING and PROPOSED, including but not limited to:
1. Water intake structures, including fixed and portable pumps, and intake lines attached to
floating platforms. The pump system and installation must be in accordance with Ameren
Missouri Shoreline Management Permit Requirements, including electrical installation, specified
screen mesh size, maximum water velocity at the screen to minimize impingement and
entrainment of fish at pump intakes, and annual water usage. Pump systems must be designed to
preclude the spillage of fuel and lubricants or the arcing of electricity into the Lake. Proposed
submersible pumps are not authorized by this permit. Portable pumps must be removed from the
Lake when not in use.
2. Dry hydrants for fire protection shall have screened intakes, be permanently fixed by burying
in the lakebed and bank, and located adjacent to boat ramps or roads accessible without crossing
wetlands.
3. Heat pump coils and lines containing liquid for the dissipation or pickup of thermal energy
permanently installed with the coils on or supported off the lakebed. System antifreeze must be
non-toxic to aquatic life. The supply lines shall lay on the lakebed and must be buried or
otherwise protected from damage entering and exiting the Lake. The coils and lines must be of
sufficient depth to avoid being a hazard to navigation during times of low lake levels. The
system and installation, including any electrical device installed in the Lake for circulation, must
be in accordance with Ameren Missouri Shoreline Permitting requirements.
4. Submerged utility lines that are buried (including placement by directional boring) or laid on
the bottom of the waterway, provided the entering and exiting portions of the line are secured or
trenched into the bottom and the bank to avoid damage to the line. On-shore alignment markers
may be required, as shown on the verification page.
5. Aerial transmission lines by commercial utility companies for telephone, cable television, and
electrical power transmission lines require pre-application notification to Ameren Missouri, the
Corps and the Missouri State Water Patrol, prior to authorization by this GP and will be installed
in accordance with Ameren Missouri Shoreline Management Permit requirements.
APPENDIX VI
Fish Habitat
EXISTING and PROPOSED, including but not limited to:
1. The placement of anchored brush piles or cedar trees; or natural or man-made fish attraction
devices; rock blankets lakeward of existing approved bulkheads/seawalls, or other structures
constructed of materials consistent with the special conditions of this GP, for the purpose of
providing fish habitat, are authorized.
2. No structures are to be placed in areas that are known to support emergent or submergent
vegetation during the growing season.
3. Anchoring systems must be designed to prevent the structure from floating into the normal
motor boat propeller zone, and to prevent less buoyant structures from moving along the lakebed
by lake currents. Anchoring cables/lines must be of a material that will not decompose before
the structure decomposes.
APPENDIX VII
Sediment and Debris Removal
EXISTING and PROPOSED, including but not limited to:
1. Excavation of accumulated sediments and debris (e.g., soil, rock, gravels, upland vegetation
and debris, and lake drift debris) from the Lake deposited as a result of a discrete event or natural
occurrences which negatively impact shallow and deep water habitat. The removal of materials
is limited to the minimum necessary to restore the area to previous condition/contours; to restore
the integrity and natural functions of the waterway, shallow or deep water habitat, or lakebed;
and to maintain the pool configuration and capacity of the Lake from siltation.
2. Each project verification by this GP authorizes a one-time excavation of the area only as
specified on the permit verification sheet. The length, width, and depth of the excavation area
shall be identified and marked on-site. Excavation shall be confined to that area between the
property lines as extended lakeward onto Ameren Missouri property and not extend beyond
center-line of the cove. Excavation depth will be restricted to approximately elevation 652.0 feet
UED. Minor variances may be authorized. The permit document will contain project area
drawings with site dimensions and corresponding elevations. You must restrict the excavation to
the authorized area only as specified in the permit.
3. Excavation of sediment and debris in the vicinity of and within existing structures (e.g.,
bridges, culverted road crossings, water intake structures, and boat ramps) for maintenance
purposes to restore use or access. Sediment/debris removal may not extend more than 200 feet
from an existing structure. The 200 foot limit does not apply to maintenance dredging to remove
accumulated sediments blocking or restricting outfall and intake structures or maintenance
dredging to remove accumulated sediments from channels associated with outfall and intake
structures. The placement of new or additional riprap, or similar approved stabilization measures
may be authorized as necessary to protect the structure and/or lessen the probability of future
sediment deposition into the Lake. Any bank stabilization measures or other work below the
OHWM not directly associated with a structure will require a separate authorization.
4. All dredged or excavated material must be placed in an upland area, above the elevation 662
feet UED contour, where and in such a manner that it will not re-enter the Lake. Large woody
debris providing aquatic habitat should not be removed unless it poses a navigational or other
safety hazard.
5. You must take preventative measures to minimize future deposition into the Lake. The
measures may include temporary and permanent sediment and erosion controls such as bank
stabilization, rock check dams, armoring drainage channels and roadside ditches, or approved
bioengineered solutions.
6. Sand from beaches may be recaptured and redeposited to restore beaches. See
Appendix III, 2. d.
NWKGP-38M PROJECT AUTHORIZATION/VERIFICATION SHEET
KANSAS CITY DISTRICT - CORPS OF ENGINEERS
1. Verification No. (Corps use only)
2. Verification date:
3. Permittee and mailing address:
4. Agent/Contractor and mailing address:
Phone:
Phone:
5. Project location: In the Lake of the Ozarks, at lake mile __________________, Cove/Arm____________________, subdivision and
lot ______________________ _____________ ; in the NE NW SE SW (circle one) of Section _______, Township _______, Range
_______, _______________ County, Missouri.
Coordinates ( __UTM, __Lat./Long., __Decidegrees):
6. Authorized work (As shown on attached drawing(s)):
(Cite applicable GP appendices and list dimensions.)
7. Special conditions/cautions:
8. Verification by :
(Name, signature and title)
Ameren Missouri project ID number : _____________________________
STATE
QF MISSOURI
Jeremiah W. Qay) Nixon, Governor · Sara Parker Pauley, Direcror
DEPARTMENT OF NATURAL RESOURCES
,
.
I
'
~~~~~~~~~~~~~~~~~~~~···-~
\VWw.dnr. mo.gov
JUN 112016
Colonel Andrew D. Sexton
U.S. Army Corps of Engineers
Kansas City District
700 Federal Building
601
12th St., Ste. 635
Kansas City, MO 64106-2824
RE: Proposed Reissuance of General Permit 38 Missouri, Lake of the Ozarks Shoreline
Development Activities, NWK-GP-38M/CEK002855
Dear Colonel Sexton:
The Department of Natural Resources (DNR), Water Protection Program, has reviewed your
request for Clean Water Act Section 401 Water Quality Certification (WQC) to accompany the
U.S. Army Corps of Engineers' (USA CE) Permit No. NWK GP-38M in which the USACE in
cooperation with Ameren Missouri are proposing to reissue General Permit 38 Missouri
(GP-38M).
GP-38M is being reissued under the authority of Section 404 of the Clean Water Act
(33 USC 1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403). The
general permit authorizes various shoreline development activities including excavation,
dredging, construction and fill activities, structures, bank stabilization and additional work as
stated in the general permit. GP-38M was originally issued June 7, 2000 and was reissued
July 1, 2006 and July 1, 2011. The current five-year authorization expires on June 30, 2016.
From July 1, 2011 to May 11, 2016, 4, 198 verifications have been made for GP-38M. The
reissuance would extend the authorization for an additional five years; from July 1, 2016 until
June 30, 2021.
The project location is in the Lake of the Ozarks, lakeward of the ordinary high water mark at
elevation 658.5 feet Union Electric Datum (UED) and waters landward of the ordinary high
water mark extending up to elevation 662.0 feet UED in Benton, Camden, Miller and Morgan
Counties, Missouri. Work in adjacent wetlands and tributaries of the Lake of the Ozarks,
landward/upstream of elevation 662.0 feet UED are not authorized by GP-38M.
Ameren Missouri owns the majority of the shoreline property around the lake, and in most
locations possesses flowage easements extending beyond the property line. Ameren Missouri
under Article 41 of its Federal Energy Regulatory Commission license issues permits for use and
occupancy of project lands and waters.
0
Rt.·t·,,~·kd
Paper
Colonel Andrew D. Sexton
Page Two
This WQC is being issued under Section 401 of Public Law 95-217, The Clean Water Act of
1977 and subsequent revisions. This office certifies the proposed project will not cause the
general or numeric criteria to be exceeded nor impair beneficial uses established in the Water
Quality Standards, 10 CSR 20-7 .031, provided the following conditions are met:
1.
After avoidance and minimization measures have been employed, mitigation shall be
required for stream and wetland impacts to jurisdictional waters below 662.0 feet UED.
For projects that positively impact the environment such as shoreline/streambank
stabilization through bioengineering, mitigation may be waived. Mitigation for loss of
aquatic resources shall be in conformance with the April 10, 2008 joint regulation
"Compensatory Mitigation for Losses of Aquatic Resources; Final Rule" [USACE: 33 CFR
Part 332 and U.S. Environmental Protection Agency: 40 CFR Part 230] and with guidance
located on-line at
www.nwk.usace.army.mil/Missions/RegulatoryBranch/StateofMissouri.aspx.
2.
Any extensions of the authorization granted under GP-38M shall not exceed beyond five
years from the issuance date of the Clean Water Act Section 404 Department of the Army
Permit certified by this action.
3.
If the permittee transfers a permit to a new owner, the permittee shall ensure that the new
property owner is positively advised of the responsibilities under the permit.
4.
As part of sediment removal activities, sand and gravel shall not be commercially sold.
Removed sediment shall be disposed of at an upland site. The applicant shall not dispose
of waste materials, water, or garbage below the ordinary high water mark of any other
water body, in a wetland area, or at any location where the materials could be introduced
into the water body or an adjacent wetland as a result of runoff, flooding, wind, or other
natural forces.
5.
Antidegradation requirements dictate all appropriate and reasonable Best Management
Practices related to erosion and sediment control, project stabilization and prevention of
water quality degradation are applied and maintained; for example, preserving vegetation,
shoreline/streambank stability and basic drainage. Applicants will be responsible for
ensuring permit requirements and relevant WQC conditions are met.
6.
Best Management Practices shall be used during all phases of the project to limit the
amount of discharge of water contaminants to waters of the state. The project shall not
involve more than normal stormwater or incidental loading of sediment caused by
construction disturbances.
7.
Conduct project activity at low flows and water levels to limit the amount of sediment
disturbance caused by the heavy equipment.
Colonel Andrew D. Sexton
Page Three
8.
Care shall be taken to keep machinery out of the water way as much as possible. Fuel, oil
and other petroleum products, equipment, construction materials and any solid waste that
are part of the on-shore operation, when not in use, shall be stored above anticipated high
water levels. All precautions shall be taken to avoid the release of wastes or fuel to streams
and other adjacent waters as a result of this operation.
9.
Petroleum products spilled into any water or on the banks where the material may enter
waters of the state shall be immediately cleaned up and disposed of properly. Any such
spills of petroleum shall be reported as soon as possible, but no later than 24 hours after
discovery to DNR's Environmental Emergency Response number at (573) 634-2436.
10.
With the exception of invasive species, clearing of vegetation/trees shall be the minimum
necessary to accomplish the activity. Cleared areas shall be restored to a stable condition
to protect water quality as soon as possible. Seeding, mulching and needed fertilization
should be within three days of final contouring. To ensure erosion and deposition of soil in
waters of the state are not occurring, on-site inspections of these areas should be conducted
as necessary to ensure successful revegetation and stabilization.
11.
Only clean, nonpolluting fill shall be used. The following materials are not suitable for
shoreline/streambank stabilization and shall not be used due to their potential to cause
violations of the general criteria of the Water Quality Standards (10 CSR 20-7.031
(4)(A)-(H)):
a. Earthen fill, gravel, fragmented asphalt, broken concrete where the material does not
meet the specifications stated in the "Missouri Nationwide Permit Regional
Conditions" (www.nwk.usace.army.mil/Portals/29/docs/regulatory/nationwidepermits/
2012/MORegCon.pdf), since these materials are usually not substantial enough to
withstand erosive flows;
b. Concrete with exposed rebar;
c. Tires, vehicles or vehicle bodies, construction or demolition debris are solid waste and
are excluded from placement in the waters of the state;
d. Liquid concrete, including grouted riprap, if not placed as part of an engineered
structure; and
e. Any material containing chemicals that would result in violation of Missouri's Water
Quality Standards.
12.
No project shall accelerate shoreline/streambank erosion.
13.
No project shall fill jurisdictional springs.
14.
Acquisition of a WQC shall not be construed or interpreted to imply the requirements for
other permits are replaced or superseded, including Clean Water Act Section 402 National
Pollutant Discharge Elimination System Permits. Permits or any other requirements shall
Colonel Andrew D. Sexton
Page Four
remain in effect. Land disturbance activities disturbing one or more acres of total area for
the entire project may require a stormwater permit. Instructions on how to apply for and
receive the on-line land disturbance permit are located at
www.dnr.mo.gov/env/wpp/epermit/help.htm. Questions regarding permit requirements
may be directed to DNR's Southwest Regional Office at (417) 891-4300.
15.
Contact DNR for current laws and regulations regarding sewer and on-site/septic system
installation. The Missouri Statutes divide regulatory authority for sewer and septic systems
between DNR and the Department of Health and Senior Services. The Department of
Health and Senior Services have further delegated their authority to certain county health
departments.
16.
Projects could encounter sites of conservation concern, including those that have not been
recorded. To determine the potential for species of concern within or near a project, please
visit:
· Department of Conservation's "Natural Heritage Review" website at
http://mdcgis.mdc.mo.gov/heritage/newheritage/heritage.htm, and
· U.S. Fish and Wildlife Service's "Information, Planning and Conservation" website at
http://ecos.fws.gov/ipac/.
If the proposed project encounters and will potentially affect a species of concern, please
report it to the Department of Conservation and the U.S. Fish and Wildlife Service.
17.
Water supply intakes or other activities, which may be affected by suspended solids and
turbidity increases caused by work in the watercourse, shall be investigated and sufficient
notice given to the owners to allow preparation for any changes in water quality.
18.
Copies of Ameren permits no longer need to be sent to DNR. Should DNR request review
of the program or specific permits authorized by this WQC, Ameren shall then provide this
information.
19.
Representatives from DNR shall be allowed on the project property to inspect the
authorized activity at any time deemed necessary by DNR to ensure compliance with the
above conditions.
You may appeal to have the matter heard by the Administrative Hearing Commission (AHC).
To appeal, you must file a petition with the AHC within 30 days after the date this decision was
mailed or the date it was delivered, whichever date was earlier. If any such petition is sent by
registered mail or certified mail, it will be deemed filed on the date it is mailed; if it is sent by
any method other than registered mail or certified mail, it will be deemed filed on the date it is
received by the AHC.
Colonel Andrew D. Sexton
Page Five
This WQC is part of the USACE's permit. Water Quality Standards must be met during any
operations authorized. If you have any questions, please contact Mr. Mike Irwin by phone at
(573) 522-1131, by e-mail at mike.irwin@dnr.mo.gov, or by mail at the Department of Natural
Resources, Water Protection Program, P.O. Box 176, Jefferson City, MO 65102-0176. Thank
you for working with DNR to protect our environment.
Sincerely,
WATER PROTECTION PROGRAM
CM~C:i:;l<
Operating Permits Section
CW:mip
c:
Mr. Jesse Cochran, Kansas City Regional Office
Mr. Kevin Hess, Southwest Regional Office
Mr. John Hoke, Watershed Protection Section
Ms. Anna Nowack, Watershed Protection Section
Ms. Corinne Rosania, Kansas City Regional Office
Mr. Mel Stanford, U.S. Army Corps of Engineers, Kansas City District
Ms. Terrie Williams, Kansas City Regional Office