Borough of Avalon application for the permanent maintenance of the road to confined disposal facility (CDF) site located on Macchia’s (Graven’s) Island. Additional details are available in the Public Notice & Plans document.

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

Borough of Avalon application for the permanent maintenance of the road to confined disposal facility (CDF) site located on Macchia’s (Graven’s) Island. Additional details are available in the Public Notice & Plans document.

Borough of Avalon application for the permanent maintenance of the road to confined disposal facility (CDF) site located on Macchia’s (Graven’s) Island. Additional details are available in the Public Notice & Plans document.

On September 6, 2013, this office issued a verification of Nationwide Permits 16and 33 for A) the temporary construction of a 2156 linear foot temporary road through tidalmarsh and navigable waters for the removal of dredged materials from the Borough of Avalon's confineddisposal facility (CDF) site located on Macchia’s (Graven’s) Island and B) return waterdischarge associated with the removal of dredged materials. The work included the following:A) discharge of approximately 2.17 acre of fill within tidal marsh for the 2156 feet of roadconstruction; B) placement of a CDF outfall extending approximately 110 linear feet waterwardof the mean high water line; C) a timber matted equipment access extending approximately 90feet waterward of the mean high water line of Graven’s Thorofare, and D) the discharge of returnwater from the CDF. The approval was conditioned to require the removal of all fill andstructures in regulated areas (including fill in wetlands and structures waterward of the meanhigh water line) no later than February 8, 2015 with final restoration of all aquatic resources,including return of grades and final re-vegetation, to be completed no later than May 22, 2015.The approval was later modified on December 9, 2013 and October 24, 2014 to allow for revisedimpacts of a maximum of 2.035 acre of wetland fill and extension of time for complete removaland restoration of the road by June 15, 2016. It should also be noted that the project includedplacement of four culverted crossings of small tidal streams waterward of the mean high waterline. These crossings received advanced approval as temporary from the U.S. Coast Guard onOctober 13, 2013.

On June 15, 2016, this office received an application from the Borough of Avalon for the permanentmaintenance of the road to the CDF. The applicant has also mentioned that it is the intent of theapplicant that the road will be subject to inspection prior to future contracted use or specificproject. As necessary there would be need for routine maintenance work on the road surfacecourse to re-establish its thickness and width for safe use. They also mention that suchmaintenance would be limited to the wetland fill approved on December 9, 2013 as described onthe plans attached to this notice. The applicant continues that further modification to the CDF isalso proposed to create a ramp in both uplands and originally-approved road fill when access isrequired in order for vehicles to cross the CDF berm.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits