The District Engineers for the Albuquerque, Omaha and Sacramento Districts of the U.S. Army Corps of Engineers (Corps) hereby issue Regional General Permit (RGP) No. 96 for Natural Disaster Mitigation and Flood-Related Activities in Colorado. The purpose of this public notice is to notify interested parties of the availability of the permit effective immediately.
SUMMARY: The District Engineers for the Albuquerque, Omaha and Sacramento Districts of the U.S. Army Corps of Engineers (Corps) hereby announce the availability of Regional General Permit (RGP) No. 96 for Natural Disaster Mitigation and Flood-Related Activities in Colorado.
AUTHORITY: Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) and Section 404 of the Clean Water Act (33 U.S.C. 1344).
AREA OF COVERAGE: This RGP is applicable to all waters of the U.S. within State of Colorado, including, but not limited to, rivers, creeks, lakes, ponds, reservoirs and wetlands.
SCOPE OF ACTIVITIES: This permit authorizes the discharge of dredged or fill material into waters of the U.S. associated with certain natural disaster mitigation and flood-related activities within the State of Colorado. This RGP may apply to localized or widespread events and includes, but is not limited to, the following activities:
• repair and reconstruction of existing roads
• repair and construction of temporary levees
• protection and repair of bridge embankments
• protection and repair of utility structures
• stabilization and protection of stream banks
• protection and restoration of intake structures
• construction of debris catchment facilities
• restoration/cleanup of mud/rockslides
Work may not proceed under this RGP until the permittee has submitted a pre-construction notification (PCN) to the District Engineer and received a written permit verification from the Corps.
LENGTH OF AUTHORIZATION: This RGP will expire five years from the date of issuance.
OTHER GOVERNMENTAL AUTHORIZATIONS: The State of Colorado has certified the activities authorized by this permit under Section 401 of the Clean Water Act. For projects located on Southern Ute Indian Lands, the permittee must obtain an individual water quality certification (WQC) from the U.S. Environmental Protection Agency. For projects located on Ute Mountain Ute Indian Lands, the permittee must obtain a WQC from the Ute Mountain Ute Tribe. Please refer to RGP 96 General Condition 34 for more information on how to apply for an individual WQC for projects located in Indian Country.
Regional General Permit 96
NATURAL DISASTER MITIGATION
& FLOOD-RELATED ACTIVITIES IN COLORADO
Effective Date: August 1, 2016
Expiration Date: July 31, 2021
In accordance with Section 404 of the Clean Water Act (33 U.S.C. 1344) and Section 10
of the Rivers and Harbors Act of 1899 (33 U.S.C. 403), the District Engineers for the
Albuquerque, Omaha and Sacramento Districts of the U.S. Army Corps of Engineers
(Corps) hereby issue Regional General Permit (RGP) 96 for Natural Disaster Mitigation and
Flood-Related Activities in Colorado.
NOTE: The term "you" and its derivatives, as used in this RGP, means the permittee or any
future transferee. The term "this office" refers to the appropriate district or division office of
the Corps of Engineers having jurisdiction over the permitted activity or the appropriate
official of that office acting under the authority of the commanding officer.
You are authorized to perform work in accordance with the terms and conditions specified
below.
LOCATION: This permit is applicable to all jurisdictional waters of the United States within
State of Colorado, including, but not limited to, rivers, creeks, lakes, ponds, reservoirs
and wetlands.
Certain waterways are given special consideration. These special aquatic resources
include, but are not limited to, occupied and critical habitat for fish species protected by
the Endangered Species Act. The Corps will also carefully review projects located in
streams designated by the Colorado Department of Parks and Wildlife (CPW) as Gold
Medal Waters and may consult with CPW prior to permit verification.
NOTIFICATION AND APPROVAL PROCEDURES: Work may not proceed under this
RGP until the permittee has submitted a pre-construction notification (PCN) to the District
Engineer in accordance with the notification procedures below and received a written
permit verification from the Corps.
The PCN must be received within one (1) year following the date of the natural disaster
unless, after case-by-case review, the Corps determines that there is a legitimate reason
for the delay (see General Condition 1).
For assistance in determining the appropriate regulatory office, please visit the website:
http://www.nwo.usace.army.mil/Missions/Regulatory-Program/Colorado/, or call one of
the following Colorado Regulatory offices:
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
Denver Regulatory Office
(Omaha District)
9307 South Wadsworth Blvd.
Littleton, CO 80128-6901
Phone: (303) 979-4120
Grand Junction Regulatory Office
(Sacramento District)
400 Rood Ave., Room 224
Grand Junction, CO 81501-2563
Phone: (970) 243-1199
Southern Colorado Regulatory Office
(Albuquerque District)
200 S. Santa Fe Ave., Suite 301
Pueblo, CO 81003
Phone: (719) 543-6914
Durango Regulatory Office
(Albuquerque and Sacramento District)
1970 E 3rd Ave., Suite 109
Durango, CO 81301
Phone: (970) 259-1764
PCNs must include, at a minimum, the following information:
1.
Name, address and telephone number of the person(s) responsible for the work,
the owner of the affected lands (if different from the permittee), and the
contractor(s) that will be performing the work, if applicable;
2.
A written description of the proposed work, including:
a.
Purpose and need for the project;
b.
Type, composition, and quantity of material to be excavated or placed
(including temporary material used for cofferdams, etc.);
c.
Length, width, and depth of fill area and/or excavation area;
d.
A discussion of the direct and indirect adverse environmental effects of the
activity;
e.
Location of the source of any imported fill material;
f.
Location of the disposal site for excavated material;
g.
Type of equipment to be used;
h.
Identification/delineation of wetlands;
i.
The receiving site for excess water (drainage projects); and
j.
Any other pertinent, supporting data;
3.
A location map indicating the location of the proposed work and a legal description
(section, township, range and county, and latitude and longitude);
4.
A set of 8.5 by 11-inch drawings showing the details of the proposed work (plan
and cross sectional views showing elevations and dimensions);
Page 2 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
5.
Pre-construction photos depicting the physical setting (to be compared to postconstruction site conditions from the same photo points). Photos should contain
figure labels with time, date, bearing, and a general description of the site; and
6.
If applicable, a compensatory mitigation plan for proposed wetland fill or drainage
activities (see General Conditions 5-7 below).
The PCN must clearly describe the project so that the Corps can determine whether or
not the work is necessitated by natural disaster conditions (e.g., flood, fire, mud/rockslide)
and complies with the terms and conditions of the RGP.
After reviewing the PCN and determining that the proposed work complies with the terms
and conditions of the RGP, the Corps will issue a permit verification authorizing the work
to proceed. If the District Engineer determines that the proposed work does not meet the
terms and conditions of this RGP or that it does not fall within the intended scope of this
RGP, the Corps may verify authorization of the work under one or more nationwide
permits or other regional general permits or determine that the work is exempt from
regulation under Section 404(f)(1) of the Clean Water Act.
For any activity that the District Engineer determines to have more than minimal
environmental effects, individually or cumulatively, or that may be contrary to the public
interest, a standard individual permit may be required.
Authorization of work under this RGP does not supersede the Food Security Act
regulations and requirements for applicable projects.
SCOPE OF WORK: This RGP authorizes the discharge of dredged or fill material into
waters of the U.S. associated with certain natural disaster mitigation and flood-related
activities within the State of Colorado. This RGP may apply to localized or widespread
events and includes, but is not limited to, the following activities:
repair and reconstruction of existing roads
repair and construction of temporary levees
protection and repair of bridge embankments
protection and repair of utility structures
stabilization and protection of stream banks
protection and restoration of intake structures
construction of debris catchment facilities
restoration/cleanup of mud/rockslides
GENERAL CONDITIONS: To qualify for this RGP, the prospective permittee must comply
with the following general conditions (GC), in addition to any regional or case specific
conditions imposed by the Division Engineer or District Engineer:
1.
The time limit for requesting a permit verification for work under this RGP is
one (1) year following the natural disaster event. In rare cases, the Corps may
accept requests for permit verification beyond the one-year time frame, provided
Page 3 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
the permittee can document a legitimate reason for the delay. Reasonable
considerations for accepting requests more than one year after the date of the
natural disaster may include but are not limited to:
a.
Delays in funding under a designated federal disaster recovery program;
b.
Scale and nature of the natural disaster (e.g., fire vs. flood);
c.
Overall speed and status of recovery efforts in the disaster area;
d.
Legal issues (e.g., land disputes); and
e.
Existence of a federal or state-sponsored long-term monitoring program for
identifying critical needs as they develop within a catastrophically disturbed
watershed (commonly for burn scar areas where watersheds evolve rapidly
within a few years after intense disturbances).
2.
The time limit for completing the work authorized by this RGP is one (1) year
from the date of permit verification, unless otherwise specified in the Corps
verification letter. If additional time is required to complete the authorized activity,
a written request for a time extension, including justification for the request, must
be submitted to the Corps at least 45 days prior to the expiration of the verification.
3.
Impacts to aquatic resources authorized by this RGP must be limited to the
minimum necessary in order to accomplish the purpose of the project. The
maximum limits are as follows:
a.
One (1) acre of permanent impacts to non-wetland jurisdictional areas. In
rare cases, the Corps may increase this limit to a maximum of two (2) acres
if, after consultation with other federal and state agencies, the Corps
determines that the adverse environmental impacts are minimal; and
b.
One-half (½) acre of permanent impacts to wetlands. This limit cannot be
waived.
4.
Channel restoration work will be limited to restoring the area to pre-flood contours
and conditions unless a determination has been made, and the Corps agrees,
that a realignment of the channel or changes in grades are necessary for
restoration. Straightening of stream channels is prohibited.
5.
Compensatory mitigation is required for all projects involving the loss of greater
than 1/10 acre of wetlands. For wetland losses of 1/10 acre or less, the Corps
may determine on a case-by-case basis that compensatory mitigation is required.
6.
For projects that require compensatory mitigation, the permittee shall develop a
compensatory mitigation plan. The mitigation plan must be approved by the
Corps, in coordination with other applicable resource agencies, prior to permit
verification. In urgent situations, approval of mitigation plans by the Corps may
Page 4 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
be subsequent to permit verification, since sufficient time may not be available to
approve mitigation before the work must take place.
7.
In general, the compensatory mitigation should be located within the same
watershed as the impact site, and should be located where it is most likely to
successfully replace lost functions and services at an areal or functional
compensatory mitigation ratio of no less than 1:1, as determined by the Corps.
Mitigation proposals should be submitted following the guidance as specified in
the Mitigation Rule, found at 33 C.F.R. Part 332, Compensatory Mitigation for
Losses of Aquatic Resources, 10-Apr-08 (http://www.usace.army.mil
/CECW/Documents/cecwo/reg/news/final_mitig_rule.pdf).
8.
You must maintain the activity authorized by this permit in good condition and in
conformance with the terms and conditions of this permit. You are not relieved of
this requirement if you abandon the permitted activity, although you may make a
good faith transfer to a third party in compliance with General Condition 9 below.
Should you wish to cease to maintain the authorized activity or should you desire
to abandon it without a good faith transfer, you must obtain a modification of this
RGP from this office, which may require restoration of the area.
9.
If you sell the property associated with this permit, you must obtain the signature of
the new owner and forward a copy of the permit to this office to validate the transfer
of this authorization.
10. You must allow representatives from this office to inspect the authorized activity at
any time deemed necessary to ensure that it is being or has been accomplished in
accordance with the terms and conditions of your permit.
11. No activity is authorized under this permit which is likely to jeopardize the
continued existence of a threatened or endangered species or a species
proposed for such designation, as identified under the Endangered Species Act,
or which is likely to destroy or adversely modify the critical habitat of such species.
When appropriate, the Corps will consult with the U.S. Fish and Wildlife Service
(USFWS) on specific requests to perform work under this RGP when a project
may affect a threatened or endangered species.
12. An activity which may affect historic properties listed, or eligible for listing, in the
National Register of Historic Places is not authorized by this permit until the Corps
has complied with Appendix C of 33 CFR 325 and the latest Corps interim
guidance with respect to Appendix C. The permittee must notify the Corps if the
activity may affect any historic properties listed, determined to be eligible for
listing, or which the permittee has reason to believe may be eligible for listing in
the National Register of Historic Places, and will not begin the activity until notified
by the Corps that the requirements of the National Historic Preservation Act have
been satisfied and that the activity is authorized.
13. If you discover any previously unknown historic or archeological remains while
accomplishing the activity authorized by this RGP, you must stop work and
Page 5 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
immediately notify us of what you have found. We will initiate the federal and state
coordination required to determine if the remains warrant a recovery effort or if the
site is eligible for listing in the National Register of Historic Places.
14. All fill must be of suitable materials free from toxic pollutants in toxic amounts and
placed in such a manner that the material will not be eroded by expected high
flows (in most cases in-stream material is not suitable fill, as it will erode during
high flows). If the use of streambed material is authorized for bank stabilization
and erosion control, it must be stabilized with vegetation or appropriate rock
protection. The following materials are prohibited or restricted as fill material
under this permit:
a.
Vehicle bodies, farm machinery and metal junk, including appliances,
containers and barrels (including plastic barrels) are prohibited;
b.
Asphalt cannot be used for bank stabilization or erosion control, and old or
used asphalt cannot be used as a fill material;
c.
Biodegradable building materials, including wood debris, sheet rock, roofing
materials, and chemically treated materials subject to leaching when placed
in an aquatic environment are prohibited;
d.
Trees and treetops are prohibited unless properly anchored;
e.
Tires are prohibited; and
f.
The use of clean brick and broken concrete will be allowed on a case-by-case
basis (broken concrete must be free of exposed rebar and old asphalt).
15. All fill material must be obtained from a non-wetland source.
16. All temporary fills in waters of the United States, including sandbags, straw or hay
bales with string or wire, must be completely removed and the area restored to
pre-project conditions and contours within 30 days of the end of the flood event.
17. Temporary levees, temporary access roads, and other temporary fills must
involve the least damaging alternative and have minimum impact to waters of the
United States. Appropriate measures must be taken to maintain near normal
downstream flows to minimize additional flooding. Construction of permanent
levees or access roads is not authorized by this permit.
18. All areas disturbed by construction, which will not be riprapped, will be
seeded/planted for protection against subsequent erosion and to minimize
adverse impacts to fish and wildlife resources (this includes both herbaceous and
woody species that are indigenous to the area).
Page 6 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
19. The clearing of vegetation, including trees located in or immediately adjacent to
waters of the United States, will be limited to that which is absolutely necessary
for construction of the project.
20. Equipment for handling and conveying materials during construction will be
operated to prevent dumping or spilling the materials into the water except as
approved herein. Construction equipment will not be operated in flowing water to
the maximum extent practicable.
21. All dredged or excavated materials, with the exception of that authorized herein,
will be placed on an upland site above the ordinary high water line in a confined
area, not classified as a wetland, to prevent the return of such materials to the
waterway.
22. Concrete trucks will be washed at a site and in such a manner that washwater
cannot enter a waterway or wetland.
23. During construction, petroleum products, chemicals, or other deleterious
materials will not be allowed to enter or be deposited, in waters of the United
States. Precautions will be taken to prevent entry of these materials into waters
of the United States. Any unauthorized release of petroleum products, chemicals,
or other deleterious materials into waters of the United States will be reported
immediately to the Colorado Environmental Release and Incident Reporting Line
at 1-877-518-5608.
24. All work in the waterway will be performed in such a manner so as to minimize
increases in suspended solids and turbidity which may degrade water quality and
damage aquatic life outside the immediate area of operation.
25. All earthwork operations on the bank will be carried out in such a manner that
sediment runoff and soil erosion to the waterbody are controlled.
26. If and when the Corps has been notified that a dredging or filling activity is
adversely affecting fish or wildlife resources or the harvest thereof and the Corps
subsequently directs remedial measures, the permittee will comply with such
directions to suspend or modify the activity to the extent necessary to mitigate or
eliminate the adverse effect as required.
27. If the Corps is notified that work being performed does not comply with or fall
within the scope of this General Permit, the responsible party will take immediate
steps, as directed by the Corps, to bring the work into compliance with this permit.
28. The Corps may include special conditions in the permit verification in order to
ensure avoidance, minimization or compensation for adverse environmental
impacts associated with the work.
29. Any activity authorized under this permit may not occur in a component of the
National Wild and Scenic River system, or in a river officially designated by
Page 7 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
Congress as a "study river" for possible inclusion in the system, while the river is
in an official study status.
30. An activity may not impair reserved tribal rights, including, but not limited to,
reserved water rights and treaty fishing and hunting rights.
31. For any activity that the Corps determines to have more than minimal adverse
environmental effects, individually or cumulatively, or may be contrary to the
public interest, an individual permit may be required.
32. The State of Colorado has certified the activities authorized by this permit under
Section 401 of the Clean Water Act.
If the project is located on the following Indian Lands, the applicant must obtain
an individual water quality certification (WQC) under Section 401 of the Clean
Water Act and provide a copy of the WQC to the Corps:
a.
Southern Ute Indian Lands. WQCs for projects located on Southern Ute
Indian Lands must be obtained from the U.S. Environmental Protection
Agency (EPA). For assistance, contact the EPA at: EPA, EPR-EP, Aquatic
Resources Protection and Accountability Unit, 1595 Wynkoop Street,
Denver, Colorado 80202-1129, 303-312-6909, or visit the webpage:
http://www.epa.gov/region8/water/wqc.html.
b.
Ute Mountain Ute Indian Lands. WQCs for projects located on Ute Mountain
Ute Indian Lands must be obtained from the Ute Mountain Ute Tribe. For
assistance, contact the Ute Mountain Ute Environmental Programs
Department, 520 Sunset Blvd. or P.O. Box 448, Towoac, Colorado 81334,
970-564-5430 (fax 970-565-2651), or visit the webpage:
http://www.utemountainuteenvironmental.org.
FURTHER INFORMATION:
1.
2.
Congressional Authorities. You have been authorized to undertake the activity
described above pursuant to:
a.
Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403)
b.
Section 404 of the Clean Water Act (33 U.S.C. 1344)
Limits of this authorization:
a.
This permit does not obviate the need to obtain other federal, state, or local
authorizations required by law.
b.
This permit does not grant any property rights or exclusive privileges.
c.
This permit does not authorize any injury to the property or rights of others.
Page 8 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
d.
3.
This permit does not authorize interference with any existing or proposed
federal project.
Limits of Federal Liability. In issuing this permit, the federal government does not
assume any liability for the following:
a.
Damages to the permitted project or uses thereof as a result of other permitted
or unpermitted activities or from natural causes.
b.
Damages to the permitted project or uses thereof as a result of current or future
activities undertaken by or on behalf of the United States in the public interest.
c.
Damages to persons, property, or to other permitted or unpermitted activities
or structures caused by the activity authorized by this permit.
d.
Design or construction deficiencies associated with the permitted work.
e.
Damage claims associated with any future modification, suspension, or
revocation of this permit.
4.
Reliance on Permittee's Data. The determination of this office that issuance of this
permit is not contrary to the public interest was made in reliance on the information
you provided.
5.
Reevaluation of Permit Decision. This office may reevaluate its decision on this
permit at any time the circumstances warrant. Circumstances that could require a
reevaluation include, but are not limited to, the following:
a.
You fail to comply with the terms and conditions of this permit.
b.
The information provided by you in support of your pre-construction notification
proves to have been false, incomplete, or inaccurate (See 4 above).
c.
Significant new information surfaces which this office did not consider in
reaching the original public interest decision.
Such a reevaluation may result in a determination that it is appropriate to use the
suspension, modification, and revocation procedures contained in 33 CFR 325.7 or
enforcement procedures such as those contained in 33 CFR 326.4 and 326.5. The
referenced enforcement procedures provide for the issuance of an administrative
order requiring you to comply with the terms and conditions of your permit and for
the initiation of legal action where appropriate. You will be required to pay for any
corrective measures ordered by this office, and if you fail to comply with such
directive, this office may in certain situations (such as those specified in 33 CFR
209.170) accomplish the corrective measures by contract or otherwise and bill you
for the cost.
Page 9 of 10
Regional General Permit 96: Natural Disaster Mitigation and Flood-Related Activities in Colorado
6.
Extensions. General Condition 2 establishes a time limit for the completion of the
activity authorized by this permit. Unless there are circumstances requiring either
a prompt completion of the authorized activity or a reevaluation of the public interest
decision, the Corps will normally give favorable consideration to a request for an
extension of this time limit.
This permit becomes effective when the federal official, designated to act for the Secretary
of the Army, has signed below.
signed by STEINLE.ALLAN.EDWARD.1231814503
STEINLE.ALLAN.EDWARD.12 Digitally
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI,
ou=USA, cn=STEINLE.ALLAN.EDWARD.1231814503
31814503
Date: 2016.09.13
10:08:38 -06'00'
_____________________________________
___________________________
Allan Steinle, Chief
Albuquerque District Regulatory Division
Page 10 of 10
Date