State - KY: APPLICANT: Evansville Marine Service, Inc.; PROJECT PROPOSAL: To modify, clarify and document, an existing Department of Army (DA) permit which previously authorized structures and fleeting areas associated with the Green River Dry Dock and Repair Terminal.

This notice announces an application submitted for a Department of the Army (DA) permit, Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).

APPLICANT: Robert R. Aldrich Evansville Marine Service, Inc. P.O. BOX 6048 Evansville, IN 47719

LOCATION:The proposed project is located on theLeftDescending Bank of the Green River at Mile .6, in Henderson, Henderson County, Kentucky. Latitude:37.901582 Longitude:-87.496467 7.5 Minute Quad: Newburgh, IN - KY

PURPOSE:To modify, clarify and document, an existingDepartment of Army (DA) permit which previouslyauthorized structures and fleeting areas associatedwith the Green River Dry Dock and Repair Terminal.

DESCRIPTION OF WORK: The Green River Dry Dock and Repair Facility has an existing dry dock terminal on the Green River that has been in operation since the 1960’s. The existing DA permit, LRL-1981-00002, authorized the construction and operation of this terminal (see figure 1 of 3).

The proposed project would modify the existing DA authorization by installing four (4) new dolphins to replace the four (4) existing dolphins that were damaged or destroyed by barge traffic set loose by severe flooding on the Green River in July 2016. Each proposed dolphin would consist of one (1) vertical 24-inch by 0.500-inch wall by 90-foot long batter piles. The top of each proposed dolphin will be at elevation 383.0 feet Ohio River Datum (ORD), with the top of the dolphin approximately 41 feet above normal pool. All vertical and batter pilings would be driven to a depth of 40 feet below the river bottom. (see figure 3 of 3). The proposed dolphins would be located approximately 246 feet from the established sailing line which is 15 feet closer than the existing dolphins. By locating the new dolphins 15 feet further from the shore, the facility would be less susceptible to adverse impacts of sedimentation and improve service capability. The installation of the pipes for vertical and batter pilings, braces and stone is necessary to re-establish the dry dock terminal to a safe and workable condition. The existing dry dock and repair facility consists of an 80’ hinged ramp cantilevered to the work barge, (2) two work barges, 35’ x 100’, (2) dry docks, 100’ x 54’, and the fleeting of barges, up to a (3) three wide configuration along approximately 2300 linear feet of river. The maximum riverward extension of the facility, including the three wide barges, would be approximately 108’.

In addition to modifying the permit to incorporate the four new dolphins 15’ closer to the sailing line, this notice also serves to clarify what has been authorized under the existing DA permit with regards to the fleeting arrangements at and around the facility (see figure 2 of 3).

REVIEW PROCEDURES: A DA Permit cannot be issued if any legally required Federal, State, or local authorization or certification is denied.

Copies of this notice are sent to the appropriate Federal and State Fish and Wildlife Agencies. Their views and comments are solicited inaccordance with the Fish and Wildlife Coordination Act of 1956. Based on available information, the proposed activity will not destroy orendanger any Federally-listed threatened or endangered species or their critical habitats, as identified under the Endangered Species Act, and therefore, initiation of formal consultation procedures with the U.S. Fish and Wildlife Service is not planned at this time.

Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. A request for a public hearing must state the specificinterest which might be damaged by issuance of the DA Permit.

The National Register of Historic Places has been examined, and it has been determined that there are no properties currently listed on theRegister which would be directly affected by the proposed work. If we are made aware, as a result of comments received in response to thisnotice, or by other means, of specific archaeological, scientific, pre­ historical, or historical sites or structures which might be affected by the proposed work, the District Engineer will immediately take theappropriate action necessary pursuant to the National HistoricPreserva­tion Act of 1966 - Public Law 89-665 as amended (includingPublic Law 96-515).

The decision whether to issue a permit will be based on an evaluationof the probable impact of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utiliza­tion of important resources. The benefits which reasonably may be expected to accrue from the proposal must be balanced against itsreasonably fore­seeable detriments. All factors which may be relevantto the proposal will be considered; among those are conservation,economics, aesthetic values, general environmental concerns, historicvalues, fish and wildlife values, flood damage prevention, land use,navigation, recreation, water supply, water quality, energy needs,safety, food production, and in general, the needs and welfare of thepublic.The Corps of Engineers is soliciting comments from the public; Federal, State, and local agencies and officials; Indian tribes; and other interested parties in order to consider and evaluate the impactsof this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, commentsare used to assess impacts on endangered species, historic properties,water quality, general environmental effects, and the other publicinterest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statementpursuant to the National Environmental Policy Act. Comments are alsoused to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

Written statements received in this office on or before the closingdate will become a part of the official record and will be consideredin the determination on this permit request. Any objections which arereceived during this period will be forwarded to the applicant forpossible resolution before the determination is made whether to issueor deny the requested DA Permit. A permit will be granted unless itsissuance is found to be contrary to the public interest.Information pertaining to this application is available for publicexamination during normal business hours upon prior request. This public notice and drawings are available for viewing by clicking on the "Attachment" link above located in the upper right hand corner of this page.

If you desire to submit your comments by email, you must comply withthe following: a) In the subject line of your email, type in ONLY the Public NoticeID No. LRL-1981-00002-tmb.

Example: Subject: LRL-1981-00002-tmb

b) Provide your physical mailing address and telephone number.

c) Send your email to: lrl.regulatorypubliccomment@usace.army.mil.

d) If you are sending attachments greater than 1 Mb in size withyour email, you must send a hard copy (CD or paper) to the Corps’

physical address as well.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas