The applicant proposes to discharge 46,000 cubic yards of compacted clay and aggregate
Full Public Notice Project Plans
The applicant proposes to discharge 46,000 cubic yards of compacted clay and aggregate into 3.7 acre of forested wetlands as part of a project to construct a 4.1-acre brine well pad at the Axiall Starks Salt Dome Facility. The project area would be cleared of trees and final elevation of the well pad would be 4 feet above the existing grade.