PROJECT NAME: Washington Branch Wetland Mitigation Bank.
COUNTY: Wilkes County.
NEAREST NAMED WATERBODY: Little River.
OVERALL PROJECT PURPOSE: Commercial wetland compensatory mitigation bank.
PROJECT NAME: Washington Branch Wetland Mitigation Bank.
COUNTY: Wilkes County.
NEAREST NAMED WATERBODY: Little River.
OVERALL PROJECT PURPOSE: Commercial wetland compensatory mitigation bank.
DEPARTMENT OF THE ARMY
U.S. CORPS OF ENGINEERS
SAVANNAH DISTRICT
1590 ADAMSON PARKWAY, SUITE 200
MORROW, GEORGIA 30260-1777
October 3, 2018
Regulatory Branch
SAS-2016-00808
PUBLIC NOTICE
Savannah District
The District Engineer has received a Prospectus describing the establishment and
operation of a proposed wetland compensatory mitigation bank (Washington Branch
Wetland Mitigation Bank) for Federal and State permits as described below:
Application Number: SAS-2016-00808
Sponsor: Mr. Gregory Smith
Washington Branch, LLC
1305 Lakes Parkway, Suite 110
Lawrenceville, Georgia 30043
Agent:
Mr. Gregory Smith
Corblu Ecology Group, LLC
1305 Lakes Parkway, Suite 110
Lawrenceville, Georgia 30043
This public notice does not imply, on the parts of the US Army Corps of Engineers
(USACE) or other agencies, either favorable or unfavorable opinion of the work to be
performed, but is issued to solicit comments regarding the factors on which final
decisions will be based.
Location of Proposed Work: The project site is an approximately 126-acre property
located along the floodplain immediately east of the Little River and west of Evans
Road, in southern Wilkes County, Georgia (centered at approximately latitude 33.6353,
longitude -82.7628). See the enclosed Vicinity Map and USGS Topographic Map.
Description of Mitigation Bank: The Sponsor proposes to establish a commercial
wetland mitigation bank on the property. Historical land use on the property includes
timber harvesting, including clearing and grubbing for agricultural purposes, as well as
surface leveling to accommodate these uses. The project as currently proposed
involves approximately 30.63 acres of wetland vegetative enhancement, 52.55 acres of
wetland preservation and the establishment of approximately 43 acres of upland buffer.
The Sponsor is not proposing specific hydrologic enhancements, though some minor
grading to reestablish topographic complexity is contemplated. The vegetative
community would be improved by removing nuisance and exotic vegetation followed by
supplemental planting of appropriate wetland tree species. Based on the Savannah
District's 2018 Standard Operating Procedure for Compensatory Mitigation, successful
completion of mitigation activities within the proposed bank would result in a total of
17.94 credits from slope wetland units and 10.95 credits from riverine wetland units.
See the enclosed Mitigation Areas Map. The Sponsor has also included additional
baseline data collected, to better inform feasibility of the proposed mitigation actions,
which are not specifically addressed in this notice, as they are beyond the scope of the
project Prospectus.
Geographic Service Area: The proposed Geographic Service Area (GSA) is the
defined area within which this bank can reasonably be expected to provide appropriate
compensation for impacts to aquatic resources. The GSA for this bank would include
the Little River watershed, Hydrologic Unit Code (HUC) 03060105, the Broad River
(HUC 03060104), the Tugaloo River (HUC 03060102), and the Upper Savannah River
(HUC 03060103) as the Primary service area, and the Upper Oconee River (HUC
03070101), as the Secondary service area in Georgia. See the enclosed Service Area
Map.
Oversight: This mitigation bank may be considered one of a number of practicable
alternatives available to applicants to compensate for unavoidable impacts associated
with permits issued under the authority of Sections 404 and 401 of the Clean Water Act
for projects located within the prescribed GSA.
Oversight of this compensatory mitigation bank would be by a group of Federal and
State agency representatives collectively referred to as the Interagency Review Team
(IRT). The IRT shall be chaired by the Savannah District, USACE and is comprised of
representatives from the US Environmental Protection Agency, US Fish and Wildlife
Service, and the Georgia Department of Natural Resources, Environmental Protection
Division.
The actual approval of the use of this mitigation bank for a specific project is the
decision of the USACE pursuant to Section 10 of the Rivers and Harbors Act and
Section 404 of the Clean Water Act. The USACE provides no guarantee that any
particular individual or general permit would be granted authorization to use this
compensatory mitigation bank to compensate for unavoidable impacts associated with a
proposed permit, even though mitigation from this bank may be available.
Authority: A public notice regarding the proposed mitigation bank is required
pursuant to Title 33 Code of Federal Regulations Parts 325 and 332, and Title 40 Code
of Federal Regulations Part 230, entitled "Compensatory Mitigation for Losses of
Aquatic Resources, Final Rule", published in the Federal Register on April 10, 2008.
2
Consideration of Public Comments: The USACE is soliciting comments from the
public; federal, state, and location agencies and officials; Native American Tribes; and
other interested parties in order to consider and evaluate this proposed mitigation bank.
The Prospectus can be seen at the US Army Corps of Engineers, Savannah District,
Regulatory Branch, 1590 Adamson Parkway, Suite 200, Morrow, Georgia 30260-1777,
and/or via the Savannah District's "Bank & ILF Sites" link on the Regulatory In-lieu Fee
and Bank Information Tracking System (RIBITS) website. Written comments received
will be considered by the USACE in evaluating this proposal. Comments are used to
assess impacts on endangered species, historic properties, conservation, economics,
aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife
values, flood hazards and flood plain values (in accordance with Executive Order
11988), land use, navigation, shore erosion and accretion, recreation, water supply and
conservation, water quality, energy needs, safety, food and fiber production, mineral
needs, consideration of property ownership, and, in general, the needs and welfare of
the public.
Preliminary review, provided by the bank's sponsor, indicates that: 1) No species of
fish, wildlife, or plant (or their critical habitat) listed as endangered or threatened under
the Endangered Species Act of 1973 (PL 93-205) would be affected; and 2) No cultural
or historical resources considered eligible or potentially eligible for listing on the National
Register of Historic Places would be affected according to a website review of known
listed properties. Additional information may change any of these preliminary findings.
Comment Period: Anyone wishing to comment on this proposal should submit
comments in writing to the Commander, US Army Corps of Engineers, Savannah
District, Regulatory Branch, Attention: Mr. Adam F. White, 1590 Adamson Parkway,
Suite 200, Morrow, Georgia 30260-1777, no later than 30 days from the date of this
notice. Please refer to the mitigation bank name (Washington Branch Wetland
Mitigation Bank) and the Regulatory Branch file number (SAS-2016-00808) in your
comments.
If you have any further questions concerning this matter, please contact
Adam F. White, Project Manager, Piedmont Branch at 678-422-2730 or
adam.f.white@usace.army.mil.
4 Encls
1. Vicinity Map
2. USGS Topographic Map
3. Mitigation Areas Map
4. Service Area Map
3
Legend
rr-----,
u_____J Counties
c:::J WBMB Boundary
...0::
l
Rayle
l
,
,...,
Point
2Zl
278
Norwood
Camak
~
t,
~
\
Warren
Warrenton
Directions to Washington Branch Mitigaiton Bank:
Travelling east on 1-20 from Atlanta, take exit 148
for GA-22 East. In approximately 2 miles, tum right
onto GA-278/Broad Street. In 1 mile, turn left onto
:,.-f" State Route 47. After 7 miles, turn right onto Hallford
Road, then rigthonto Evans Road after 0.7 miles.
The site is approximately 1 mile down on the right.
N
i
Washington Branch Mitigation Bank
Wilkes County, Georgia
0
2.5
5
1 in = 5 miles
10
Miles
Figure 1
Vicinity Map
II
corblu
ECOLOGY GROUP
zd
ll~
H
... q
~!
<'l
I
.7
-·\
\.~'t--~~.--......----ir--"7"'7,:,....
'-. . . . . <'
·..} '--.....
""
Washington Branch Mitigation Bank
Wilkes County, Georgia
0
1,000 2,000
4,000
- - = = = = - - - · Feet
1 in = 2,000 ft
Figure 5
USGS Topographic Map
II
corblu
ECOLOGY GROUP
North Carolina
Gilmer
Pickens
Franklin
Banks
Jackson
Hart
Madison
Barrow
Elbert
Clarke
Cobb
Oglethorpe
Oconee
Wilkes
Morgan
Putnam
Pike
Lamar
Upson
*
Talor
Laurens
Washington Branch Mitigation Bank
-
Pri mary Service Area
-
Secondary Service Area
Dodge
Washington Branch Mitigation Bank
Wilkes County, Georgia
--c:::===-----
0
12.5
25
1 inch = 25 miles
50
Miles
Figure 4
Service Area Map
41
corblu
ECOLOGY GROUP
c::::J
WBMB Boundary
Mitigation Areas
~ Enhancement - 30.63 Acres
C]
Preservation - 52.55 Acres
. . Upland buffer 43.01 Acres
N
i
Washington Branch Mitigation Bank
Wilkes County, Georgia
--c::=====-----
0
250
500
1 in = 500 ft
1,000
Feet
Figure 14
Mitigation Areas Map
II
corblu
ECOLOGY GROUP