| ID Number | Applicant | Post Date | Expiration | Status |
|---|---|---|---|---|
| 1764783 | Mr. Dick Campbell | 2019-02-22 | 2019-03-25 | |
| 1761263 | Mr. Bill Cunningham | 2019-02-20 | 2019-03-20 | |
| 1759398 | Mr. Alan Verner | 2019-02-15 | 2019-03-15 | |
| 1758490 | Special Public Notice: Seeking comments regarding specifics of the proposed "waters of the United States" definition | 2019-02-14 | 2019-04-15 | |
| 1740685 | Stewart Tate | 2019-01-28 | 2019-02-28 | |
| 1736066 | (missing) | 2019-01-18 | 2019-02-19 | |
| 1735396 | Mr. Dick Evans | 2019-01-18 | 2019-02-18 | |
| 1728629 | Ms. Linda McGregor | 2019-01-10 | 2019-02-10 | |
| 1721803 | Mr. Tim Evans | 2018-12-27 | 2019-01-27 | |
| 1719336 | Mr. Matthew Sheahan | 2018-12-18 | 2019-12-18 | |
| 1712351 | (missing) | 2018-12-13 | 2019-01-14 | |
| 1687512 | (missing) | 2018-11-09 | 2018-12-10 | |
| 1686414 | The Corps is soliciting written comments on the proposed "Draft Monitoring Guidelines & Performance Standards for Freshwater Wetlands and Non-Tidal Streams | 2018-11-08 | 2018-12-08 | |
| 1679354 | PROJECT NAME: PGP 58 Lake Blackshear. COUNTY: Crisp | 2018-11-01 | 2018-12-01 | |
| 1669775 | Mr. Surendra Gupta | 2018-10-23 | 2018-11-24 | |
| 1664336 | Counties: All. Nearest Named Waterbody: N/A. Overall Project Purpose: The Savannah District Regulatory Branch has been working with the Federal Highway Administration (FHWA) | 2018-10-17 | 2018-11-15 | |
| 1663424 | Mr. Mark Shugart | 2018-10-16 | 2018-11-16 | |
| 1655943 | County: Georgia. Overall Project Purpose: These RPs authorize the maintenance | 2018-10-05 | 2018-11-06 | |
| 1652643 | (missing) | 2018-10-03 | 2018-11-05 | |
| 1648376 | (missing) | 2018-09-28 | 2018-10-29 | |
| 1642030 | (missing) | 2018-09-21 | 2018-10-31 | |
| 1642016 | (missing) | 2018-09-21 | 2018-10-30 | |
| 1630021 | Mr. Jay Liebe | 2018-09-12 | 2018-10-15 | |
| 1624127 | Project Name: SAS-1997-15260 Southbridge at Berwick Plantation Counties: Region 1 | 2018-09-07 | 2018-10-07 | |
| 1624065 | Project Name: SAS-2017-00911 Jekyll Island Phase 2 Shoreline Restoration Project Counties: Region 1 | 2018-09-07 | 2018-10-07 | |
| 1622532 | (missing) | 2018-09-06 | 2018-10-07 | |
| 1619690 | (missing) | 2018-09-04 | 2018-10-05 | |
| 1618355 | (missing) | 2018-08-31 | 2018-10-01 | |
| 1616778 | (missing) | 2018-08-30 | 2018-09-29 | |
| 1616200 | PROJECT NAME: SAS-2000-08330. COUNTY: Gwinnett. NEAREST NAMED WATERBODY: Yellow River. OVERALL PROJECT PURPOSE: The proposed project involves the construction of a 153 | 2018-08-29 | 2018-09-27 | |
| 1614586 | (missing) | 2018-08-28 | 2018-09-29 | |
| 1605151 | SAS-2017-00921-ESA | 2018-08-17 | 2019-08-16 | |
| 1604486 | PROJECT NAME: Bard Manufacturing Facility Expansion. COUNTY: Morgan. NEAREST NAMED WATERBODY: Fourmile Branch. OVERALL PROJECT PURPOSE: Construction of an approximately 97 | 2018-08-16 | 2018-09-17 | |
| 1592244 | (missing) | 2018-08-02 | 2018-09-01 | |
| 1632991 | (missing) | 2018-07-26 | 2018-08-25 | |
| 1580544 | (missing) | 2018-07-20 | 2018-08-06 | |
| 1580483 | (missing) | 2018-07-20 | 2018-08-04 | |
| 1577063 | (missing) | 2018-07-17 | 2018-08-17 | |
| 1570149 | (missing) | 2018-07-09 | 2018-08-09 | |
| 1567834 | (missing) | 2018-07-05 | 2018-08-04 | |
| 1557769 | (missing) | 2018-06-22 | 2018-07-21 | |
| 1553790 | (missing) | 2018-06-18 | 2018-07-18 | |
| 1548984 | (missing) | 2018-06-13 | 2018-07-14 | |
| 1545506 | (missing) | 2018-06-08 | 2018-07-09 | |
| 1545242 | Project Name: SAS-2018-00375 Savannah River Lakes PGPs 2-14 Reissuance County: Work and activities are authorized in and adjacent to the portions of Hartwell | 2018-06-08 | 2018-07-09 | |
| 1542771 | (missing) | 2018-06-06 | 2018-07-05 | |
| 1534925 | (missing) | 2018-05-30 | 2018-06-29 | |
| 1532993 | (missing) | 2018-05-25 | 2018-06-25 | |
| 1532975 | (missing) | 2018-05-25 | 2018-06-25 | |
| 1522167 | (missing) | 2018-05-15 | 2018-06-15 | |
| 1519352 | (missing) | 2018-05-11 | 2018-05-28 | |
| 1518071 | (missing) | 2018-05-10 | 2018-06-09 | |
| 1518008 | Project Name: SAS-2016-00695 Rayonier Bulkhead Extension and Outfall Removal Counties: Region 1 | 2018-05-10 | 2018-06-09 | |
| 1513693 | Project Name: SAS-2006-00840 PGPs 2-14 Hartwell | 2018-05-07 | 2018-06-04 | |
| 1505944 | (missing) | 2018-04-27 | 2019-05-27 | |
| 1505290 | Project Name: SAS-2012-00521 Inshore Reefs. Counties: Chatham | 2018-04-27 | 2018-05-26 | |
| 1501891 | (missing) | 2018-04-24 | 2018-06-01 | |
| 1500403 | NAME: SAS-2015-00742 Addendum to The Reserve at Sea Island Beach | 2018-04-23 | 2018-05-22 | |
| 1495464 | GA DNR General Permits for transportation | 2018-04-17 | 2018-05-17 | |
| 1490713 | Blue Creek Mitigation Bank Modification | 2018-04-11 | 2018-04-25 | |
| 1490519 | (missing) | 2018-04-11 | 2018-04-26 | |
| 1488481 | (missing) | 2018-04-09 | 2018-05-10 | |
| 1482131 | (missing) | 2018-04-02 | 2018-05-01 | |
| 1478628 | (missing) | 2018-03-28 | 2018-04-27 | |
| 1475758 | PROJECT NAME: SAS-2018-00217 COUNTY: Hall NEAREST NAMED WATER BODY: Lake Lanier OVERALL PROJECT PURPOSE: The applicant’s stated purpose is “to develop an e-commerce distribution site | 2018-03-26 | 2018-04-26 | |
| 1473470 | (missing) | 2018-03-22 | 2018-04-21 | |
| 1470685 | PROJECT NAME: The Reserve at Sea Island Beach. COUNTY: Glynn. NEAREST NAMED WATERWAY: Atlantic Ocean. OVERALL PROJECT PURPOSE: To stabilize the eroding beach south of the existing south groin | 2018-03-20 | 2018-04-19 | |
| 1445367 | (missing) | 2018-02-20 | 2018-03-22 | |
| 1436329 | PROJECT NAME: SAS-2002-03090. COUNTY: Clayton. NEAREST NAMED WATERBODY: Sullivan Creek. OVERALL PROJECT PURPOSE: Construction a new concrete batch plant | 2018-02-08 | 2018-03-12 | |
| 1433583 | PROJECT NAME: SAS-2017-00724. COUNTY: Coweta. NEAREST NAMED WATERBODY: Turkey Creek. OVERALL PROJECT PURPOSE: Construction of 1.2 million square foot (sf) (Phase I) and 1.9 million sf (Phase II) commercial-industrial warehouse facilities and associated infrastructure | 2018-02-06 | 2018-03-09 | |
| 1431352 | (missing) | 2018-02-02 | 2018-03-03 | |
| 1430931 | PROJECT NAME: Regional Permit 90 | 2018-02-02 | ||
| 1430251 | (missing) | 2018-02-01 | 2018-04-02 | |
| 1429106 | (missing) | 2018-01-31 | 2018-03-01 | |
| 1427739 | PROJECT NAME: Riverside West Business Park. COUNTY: Douglas. NEAREST NAMED WATERBODY: Sweetwater Creek. OVERALL PROJECT PURPOSE: Construction of a light industrial business park | 2018-01-30 | 2018-03-01 | |
| 1420860 | PROJECT NAME: SAS-2018-00035. COUNTY: Cherokee. NEAREST NAMED WATERBODY: Clark Creek. OVERALL PROJECT PURPOSE: Construction of one 300 | 2018-01-22 | 2018-02-22 | |
| 1406285 | (missing) | 2017-12-29 | 2018-01-29 | |
| 1396197 | (missing) | 2017-12-13 | 2018-01-13 | |
| 1396171 | (missing) | 2017-12-13 | 2017-12-26 | |
| 1387087 | (missing) | 2017-12-04 | 2018-01-04 | |
| 1378473 | (missing) | 2017-11-21 | 2017-12-22 | |
| 1373987 | (missing) | 2017-11-16 | 2017-12-16 | |
| 1363625 | (missing) | 2017-11-06 | 2017-12-06 | |
| 1356260 | (missing) | 2017-10-27 | 2017-11-28 | |
| 1354874 | PROJECT NAME: Locust Grove Phase II. COUNTY: Henry County. NEAREST NAMED WATER BODY: Indian Creek. OVERALL PROJECT PURPOSE: to construct an approximately 3.4 million square foot industrial-distribution development | 2017-10-26 | 2017-11-27 | |
| 1353539 | (missing) | 2017-10-25 | 2017-10-25 | |
| 1352523 | (missing) | 2017-10-24 | 2017-11-08 | |
| 1351927 | (missing) | 2017-10-24 | 2017-11-24 | |
| 1340220 | (missing) | 2017-10-12 | 2017-11-11 | |
| 1339741 | (missing) | 2017-10-11 | 2017-11-10 | |
| 1331394 | (missing) | 2017-10-02 | 2017-11-03 | |
| 1331157 | PROJECT NAME: Regional General Permit 90 | 2017-10-02 | 2017-11-02 | |
| 1309537 | (missing) | 2017-09-13 | 2017-09-08 | |
| 1303035 | (missing) | 2017-09-08 | 2017-09-23 | |
| 1295351 | (missing) | 2017-08-30 | 2017-09-30 | |
| 1291649 | Project Name: SAS-2007-00378 County: Troup Nearest Named Waterbody: Shoal Creek | 2017-08-28 | 2017-09-29 | |
| 1276393 | (missing) | 2017-08-11 | 2017-09-11 | |
| 1268710 | (missing) | 2017-08-04 | 2017-08-04 | |
| 1261346 | (missing) | 2017-07-28 | 2017-10-28 | |
| 1257523 | (missing) | 2017-07-25 | 2017-08-28 | |
| 1245421 | (missing) | 2017-07-12 | 2017-08-12 | |
| 1231482 | PROJECT NAME: Mose Coleman Drive Extension. COUNTY: Toombs. NEAREST NAMED WATER BODY: Little Rocky Creek. OVERALL PROJECT PURPOSE: Improvement of capacity for local traffic access to the south of US-280 | 2017-06-28 | 2017-07-28 | |
| 1220529 | (missing) | 2017-06-20 | 2017-07-20 | |
| 1218812 | PROJECT NAME: SAS-2016-01046. COUNTY: Fulton. NEAREST NAMED WATER BODY: Morning Creek. OVERALL PROJECT PURPOSE: The proposed project involves the construction of two commercial warehouse facilities | 2017-06-19 | 2017-07-20 | |
| 1218393 | (missing) | 2017-06-19 | 2017-07-20 | |
| 1214446 | (missing) | 2017-06-14 | 2017-07-14 | |
| 1211326 | Savannah River Basin Comprehensive Study (SRBCS) Interim #2 | 2017-06-12 | 2017-07-13 | |
| 1198487 | (missing) | 2017-05-31 | 2017-07-01 | |
| 1197674 | (missing) | 2017-05-31 | 2017-06-15 | |
| 1189012 | PROJECT NAME: Wayne County Board of Education - Martha Rawls Elementary School (SAS-2013-00588). COUNTY: Wayne County. NEAREST NAMED WATERBODY: Coleman Branch. OVERALL PROJECT PURPOSE: Construction of a new playfield immediately east of and adjacent to the Martha Rawls Elementary School | 2017-05-22 | 2017-06-23 | |
| 1181253 | (missing) | 2017-05-12 | 2017-06-12 | |
| 1180882 | (missing) | 2017-05-12 | 2017-06-12 | |
| 1180304 | (missing) | 2017-05-11 | 2017-05-25 | |
| 1177082 | (missing) | 2017-05-09 | 2017-06-09 | |
| 1176301 | (missing) | 2017-05-08 | 2017-06-06 | |
| 1151340 | PGP for Georgia Power Lakes | 2017-04-13 | 2017-04-13 | |
| 1142965 | PROJECT NAME: SAS-2017-00090 COUNTY: Jackson NEAREST NAMED WATER BODY: Holders Creek OVERALL PROJECT PURPOSE: To construct a large scale industrial warehouse and manufacturing within Jackson County | 2017-04-05 | 2017-05-05 | |
| 1139847 | (missing) | 2017-04-04 | 2017-06-03 | |
| 1131175 | (missing) | 2017-03-27 | 2017-04-27 | |
| 1130694 | (missing) | 2017-03-27 | 2017-04-27 | |
| 1127836 | PROJECT NAME: Regional Permit 99. COUNTY: Fannin | 2017-03-23 | 2017-03-21 | |
| 1127556 | Georgia Land Trust In-Lieu Fee Program | 2017-03-23 | 2017-04-23 | |
| 1125620 | (missing) | 2017-03-21 | 2017-04-19 | |
| 1124145 | (missing) | 2017-03-20 | 2022-03-20 | |
| 1108686 | (missing) | 2017-03-09 | 2017-04-09 | |
| 1105455 | (missing) | 2017-03-07 | 2017-04-07 | |
| 1103834 | (missing) | 2017-03-06 | 2017-04-06 | |
| 1093238 | (missing) | 2017-02-23 | 2017-03-23 | |
| 1091103 | (missing) | 2017-02-22 | 2017-03-24 | |
| 1084341 | (missing) | 2017-02-15 | 2017-03-15 | |
| 1080350 | (missing) | 2017-02-10 | 2017-03-10 | |
| 1077903 | (missing) | 2017-02-09 | 2017-02-09 | |
| 1062313 | (missing) | 2017-01-27 | 2017-01-25 | |
| 1056730 | (missing) | 2017-01-23 | 2017-02-23 | |
| 1051319 | (missing) | 2017-01-17 | 2017-01-17 | |
| 1050139 | (missing) | 2017-01-13 | 2017-02-13 | |
| 1048782 | (missing) | 2017-01-12 | 2017-02-13 | |
| 1048455 | (missing) | 2017-01-12 | 2017-01-12 | |
| 1048440 | (missing) | 2017-01-12 | 2017-02-13 | |
| 1031511 | PROJECT NAME: Smith Dock. COUNTY: Chatham. NEAREST NAMED WATERWAY: Wilmington River. OVERALL PROJECT PURPOSE: To Construct a Single-Family Residence | 2016-12-15 | 2017-01-15 | |
| 1029894 | (missing) | 2016-12-14 | 2017-01-16 | |
| 1024722 | (missing) | 2016-12-08 | 2017-01-08 | |
| 1007361 | (missing) | 2016-11-17 | 2016-12-16 | |
| 1003497 | (missing) | 2016-11-14 | 2016-12-15 | |
| 1001304 | (missing) | 2016-11-10 | 2016-12-09 | |
| 1000855 | (missing) | 2016-11-09 | 2016-11-09 | |
| 999590 | (missing) | 2016-11-08 | 2016-12-08 | |
| 990707 | (missing) | 2016-10-31 | 2016-11-28 | |
| 988799 | (missing) | 2016-10-27 | 2016-11-28 | |
| 982348 | U.S. Army Corps of Engineers Charleston District Public Notice PROJECT NAME: Jasper Ocean Terminal COUNTY: Jasper County WATERWAY & LOCATION: Savannah River. The proposed project is located approximately 5 miles east of U.S. Highway 17 on the northern bank of the Savannah River in Jasper County | 2016-10-21 | 2016-11-21 | |
| 982302 | (missing) | 2016-10-21 | 2016-11-21 | |
| 969906 | (missing) | 2016-10-11 | 2016-12-11 | |
| 965308 | (missing) | 2016-10-05 | 2016-11-04 | |
| 963343 | PROJECT NAME: Palmetto-Weldon Industrial (SAS-2009-00587). COUNTY: Coweta. NEAREST NAMED WATERBODY: Persimmon Creek. OVERALL PROJECT PURPOSE: Construction of a 57-acre industrial development composed of an approximately one-million square foot warehouse | 2016-10-04 | 2016-11-03 | |
| 962877 | PROJECT NAME: Proposed Programmatic General Permit 98 and Regional Permit 99 for TVA Lakes. COUNTY: Fannin | 2016-10-04 | 2016-11-03 | |
| 960370 | (missing) | 2016-09-30 | 2016-10-17 | |
| 960198 | PROJECT NAME: Camp Creek Business Center (SAS-2002-15750). COUNTY: Fulton. NEAREST NAMED WATERBODY: Camp Creek. OVERALL PROJECT PURPOSE: 400-acre multi-phase | 2016-09-30 | 2016-10-31 | |
| 958382 | PROJECT NAME: Welch | 2016-09-28 | 2016-10-28 | |
| 951056 | (missing) | 2016-09-21 | 2016-10-20 | |
| 948808 | (missing) | 2016-09-19 | 2016-10-18 | |
| 935104 | (missing) | 2016-09-06 | 2016-10-06 | |
| 929940 | PROJECT NAME: J. Strom Thurmond Lake. COUNTY: Columbia. NEAREST NAMED WATERWAY: J. Strom Thurmond Lake. OVERALL PROJECT PURPOSE: A proposed update to the Shoreline Management Plan | 2016-08-30 | 2016-09-26 | |
| 927636 | (missing) | 2016-08-26 | 2016-09-27 | |
| 927198 | (missing) | 2016-08-26 | 2016-09-17 | |
| 924886 | PROJECT NAME: SAS-2007-01245. COUNTY: Dawson. NEAREST NAMED WATERBODY: Mill Creek. OVERALL PROJECT PURPOSE: The project involves the construction of a commercial-retail development providing a total of 1 | 2016-08-24 | 2016-09-08 | |
| 915469 | (missing) | 2016-08-16 | 2016-09-15 | |
| 906267 | (missing) | 2016-08-05 | 2016-08-20 | |
| 873587 | (missing) | 2016-07-27 | 2016-08-26 | |
| 855085 | (missing) | 2016-07-25 | 2016-08-24 | |
| 839410 | (missing) | 2016-07-15 | 2016-08-16 | |
| 831899 | GA DOT I75 | 2016-07-08 | 2016-08-08 | |
| 831696 | (missing) | 2016-07-08 | 2016-08-08 | |
| 822912 | (missing) | 2016-07-01 | 2016-08-01 | |
| 796144 | USACE Savannah PGP Georgia Power Lakes | 2016-06-10 | 2016-07-10 | |
| 789487 | USACE Nationwide Permits for Comments (SEW) | 2016-06-02 | 2016-08-01 | |
| 784479 | Mr. Eric Hines SHORELINE STABILIZATION | 2016-05-27 | 2016-06-26 | |
| 781671 | Mr. Jason Patrick Expansion of a Warehouse Facility. | 2016-05-25 | 2016-06-24 | |
| 757772 | (missing) | 2016-05-12 | 2016-06-13 | |
| 744800 | Avian Vacuolar Myelinopathy Plan for J. Strom Thurmond Lake | 2016-04-28 | 2016-05-31 | |
| 741527 | (missing) | 2016-04-25 | 2016-05-20 | |
| 740806 | (missing) | 2016-04-22 | 2016-05-21 | |
| 722116 | (missing) | 2016-04-15 | 2016-05-15 | |
| 720313 | (missing) | 2016-04-13 | 2016-05-13 | |
| 707389 | (missing) | 2016-03-29 | 2016-04-29 | |
| 704067 | (missing) | 2016-03-24 | 2016-04-22 | |
| 703861 | (missing) | 2016-03-24 | 2016-04-24 | |
| 682812 | PROJECT NAME: CVP Rail Yard. COUNTY: Wayne. NEAREST NAMED WATERWAY: Penholloway Creek OVERALL PROJECT PURPOSE: The applicants stated purpose of the proposed project is to establish a rail yard complex that will accommodate CCR and other non-hazardous waste streams | 2016-03-01 | 2016-04-05 | |
| 648694 | PROJECT NAME: Wessles Tract Warehouse and Logistics Facility_Knowlton | 2016-02-02 | 2016-03-03 | |
| 645539 | PROJECT NAME: CVP Rail Yard. COUNTY: Wayne. NEAREST NAMED WATERBODY: Penholloway Creek OVERALL PROJECT PURPOSE: The applicants stated purpose of the proposed project is to establish a rail yard complex that will accommodate CCR and other non-hazardous waste streams | 2016-01-28 | 2016-03-04 | |
| 643351 | (missing) | 2016-01-15 | 2016-02-16 | |
| 643325 | (missing) | 2016-01-15 | 2016-02-16 | |
| 642936 | PROJECT NAME: I-16/I-75 Interchange Reconstruction COUNTY: Bibb NEAREST NAMED WATERWAY: Ocmulgee River OVERALL PROJECT PURPOSE: Georgia Department of Transportation proposes to improve I-16 and I-75 in Macon | 2016-01-13 | 2016-02-13 | |
| 639932 | PROJECT NAME: Central Virginia Properties (CVP) Rail Yard. COUNTY: Wayne. NEAREST NAMED WATERBODY: Little Penholoway Creek. OVERALL PROJECT PURPOSE: Establish a rail yard complex to accommodate Coal Combustion Residuals (CCR) and other non-hazardous waste streams | 2016-01-05 | 2016-02-03 | |
| 639875 | (missing) | 2016-01-04 | 2016-02-04 | |
| 639852 | PROJECT NAME: Central Virginia Properties Rail Yard. COUNTY | 2016-01-04 | 2016-02-03 | |
| 639585 | (missing) | 2015-12-30 | 2016-01-30 | |
| 637909 | (missing) | 2015-12-23 | 2016-01-22 | |
| 637738 | (missing) | 2015-12-22 | 2016-01-21 | |
| 637724 | (missing) | 2015-12-22 | 2016-01-21 | |
| 637008 | (missing) | 2015-12-16 | 2016-01-15 | |
| 637000 | (missing) | 2015-12-16 | 2016-01-15 | |
| 633799 | (missing) | 2015-12-11 | 2015-12-11 | |
| 632935 | (missing) | 2015-12-04 | 2016-01-04 | |
| 632124 | (missing) | 2015-12-02 | 2016-01-04 | |
| 632096 | (missing) | 2015-12-02 | 2016-01-01 | |
| 631564 | (missing) | 2015-11-30 | 2015-12-30 | |
| 630166 | (missing) | 2015-11-17 | 2016-02-15 | |
| 628719 | PROJECT NAME: Lakeside Dam Rehabilitation. COUNTY: Bibb. NEAREST WATERBODY: Lakeside Reservoir (Impoundment of Boggy Branch). OVERALL PROJECT PURPOSE: To rehabilitate the existing dam servicing Lakeside Reservoir | 2015-11-12 | 2015-12-14 | |
| 626767 | (missing) | 2015-10-30 | 2015-12-29 | |
| 625939 | (missing) | 2015-10-26 | 2015-11-09 | |
| 623097 | (missing) | 2015-10-14 | 2015-11-16 | |
| 622912 | (missing) | 2015-10-13 | 2015-11-13 | |
| 622488 | (missing) | 2015-10-08 | 2015-12-11 | |
| 620937 | (missing) | 2015-09-29 | 2015-10-29 | |
| 620642 | (missing) | 2015-09-25 | 2015-10-25 | |
| 616690 | (missing) | 2015-09-11 | 2015-10-12 | |
| 616197 | (missing) | 2015-09-03 | 2015-10-03 | |
| 612341 | (missing) | 2015-08-05 | 2015-08-20 | |
| 612330 | (missing) | 2015-08-05 | 2015-09-05 | |
| 612238 | PROJECT NAME: Majestic Airport Center IV. COUNTY: Fulton. NEAREST NAMED WATERBODY: Big Branch. OVERALL PROJECT PURPOSE: To construct an industrial development | 2015-08-05 | 2015-09-04 | |
| 602208 | (missing) | 2015-06-29 | 2015-07-29 | |
| 602011 | (missing) | 2015-06-26 | 2015-07-27 | |
| 600861 | (missing) | 2015-06-18 | 2015-07-18 | |
| 600169 | (missing) | 2015-06-11 | 2015-07-11 | |
| 599906 | (missing) | 2015-06-09 | 2015-07-09 | |
| 590773 | (missing) | 2015-06-05 | 2015-07-05 | |
| 586692 | PROJECT NAME: U.S. Highway 84 | 2015-04-28 | 2015-05-28 | |
| 586381 | (missing) | 2015-04-23 | 2015-05-23 | |
| 586166 | (missing) | 2015-04-21 | 2015-05-21 | |
| 585341 | (missing) | 2015-04-17 | 2015-05-18 | |
| 584832 | (missing) | 2015-04-13 | 2015-05-13 | |
| 584698 | (missing) | 2015-04-10 | 2015-05-11 | |
| 583615 | (missing) | 2015-04-06 | 2015-05-06 | |
| 582119 | (missing) | 2015-03-31 | 2015-05-04 | |
| 581545 | (missing) | 2015-03-26 | 2015-04-25 | |
| 581264 | (missing) | 2015-03-23 | 2015-04-23 | |
| 580961 | (missing) | 2015-03-19 | 2015-03-18 | |
| 579148 | (missing) | 2015-03-07 | 2015-03-23 | |
| 578840 | (missing) | 2015-03-04 | 2015-04-04 | |
| 578809 | (missing) | 2015-03-04 | 2015-04-03 | |
| 571229 | PROJECT NAME: Belfast Commerce Centre COUNTY: Bryan NEAREST NAMED WATERWAY: Jerico River OVERALL PROJECT PURPOSE: To construct a mixed use commerce center dominated by heavy manufacturing | 2015-02-27 | 2015-03-30 | |
| 571173 | PROJECT NAME: US 78 Widening and Reconstruction | 2015-02-27 | 2015-03-30 | |
| 566557 | (missing) | 2015-02-18 | 2015-03-23 | |
| 566517 | (missing) | 2015-02-18 | 2015-03-23 | |
| 566415 | (missing) | 2015-02-18 | 2015-03-20 | |
| 565244 | PROJECT NAME: Clean Water Act Interpretive Rule for 404(f)(1)(a) Withdrawal. COUNTY: Georgia. NEAREST NAMED WATERWAY: N/A. OVERALL PROJECT PURPOSE: Attached to this message is a public notice for posting to help inform the public and agricultural | 2015-01-29 | 2020-01-29 | |
| 562270 | PROJECT NAME: Savannah Harbor Expansion Project - Raw Water Storage Impoundment. COUNTY: Chatham. NEAREST NAMED WATERWAY: Black Creek OVERALL PROJECT PURPOSE: To remove a 2.1 acre portion of wetland from an existing Restrictive Covenant in order to facilitate the future construction of a Raw Water Storage Impoundment | 2015-01-23 | 2015-02-07 | |
| 562266 | (missing) | 2015-01-23 | 2015-02-23 | |
| 559000 | PROJECT NAME: 2015 Monthly Agency Meetings. COUNTY: Georgia. NEAREST NAMED WATERWAY: N/A. OVERALL PROJECT PURPOSE: The 2015 schedule for the Savannah District's | 2015-01-05 | 2015-01-05 | |
| 558748 | (missing) | 2014-12-23 | 2015-01-30 | |
| 558559 | (missing) | 2014-12-19 | 2015-01-20 | |
| 565250 | (missing) | 2014-12-08 | 2019-12-09 | |
| 555346 | (missing) | 2014-12-03 | 2014-12-03 | |
| 555225 | (missing) | 2014-12-02 | 2015-01-02 | |
| 547811 | PROJECT NAME: Oakley Industrial Boulevard Extension. COUNTY: Fulton. NEAREST NAMED WATERWAY: Wyndham Creek. OVERALL PROJECT PURPOSE: To impact 290 linear feet of perennial | 2014-11-04 | 2014-12-06 | |
| 547517 | PROJECT NAME: R&B Landfill Expansion. COUNTY: Banks. NEAREST NAMED WATERBODY: Carlan and Webb Creeks. OVERALL PROJECT PURPOSE: The Applicant's stated overall purpose for the proposed expansion of the R&B Landfill is to provide for additional municipal soild waste disposal capacity within the existing landfill facility. The R&B Landfill has a remaining capacity of approximately 15 million cubic yards | 2014-10-30 | 2014-11-30 | |
| 526179 | (missing) | 2014-10-23 | 2014-11-24 | |
| 509899 | PROJECT NAME: Extend Comment Period for the Clean Water Act Proposed Rule for Definition of Water of the U.S. COUNTY: Georgia. NEAREST NAMED WATERWAY: N/A. OVERALL PROJECT PURPOSE: On 21 April 2014 | 2014-10-14 | 2014-11-14 | |
| 503467 | (missing) | 2014-10-08 | 2014-10-08 | |
| 496560 | PROJECT NAME: Newton County Bear Creek Reservoir. COUNTY: Newton. NEAREST NAMED WATERBODY: Bear Creek. OVERALL PROJECT PURPOSE: To provide a reliable supply of at least 25.75 million gallons per day of water | 2014-09-04 | 2014-09-19 | |
| 494926 | PROJECT NAME: IDI Industrial Park. COUNTY: Cobb. NEAREST NAMED WATERBODY: Sweetwater Creek. OVERALL PROJECT PURPOSE: the construction of approximately 540 | 2014-08-29 | 2014-09-29 | |
| 494600 | (missing) | 2014-08-22 | 2014-09-22 | |
| 494578 | PROJECT NAME: Regulatory List of Action for June and July 2014. COUNTY: Georgia. NEAREST NAMED WATERWAY: NA. OVERALL PROJECT PURPOSE: The list includes IPs | 2014-08-22 | 2014-08-22 | |
| 494121 | (missing) | 2014-08-12 | 2014-08-27 | |
| 493976 | On 10 June 2014 | 2014-08-07 | ||
| 493966 | 2014-WRRDA | 2014-08-07 | 2014-12-03 | |
| 493126 | (missing) | 2014-08-05 | 2014-09-04 | |
| 493125 | (missing) | 2014-08-01 | 2014-07-31 | |
| 493124 | (missing) | 2014-07-25 | 2014-08-24 | |
| 493123 | (missing) | 2014-07-08 | 2014-08-07 | |
| 493122 | (missing) | 2014-07-02 | 2014-08-02 | |
| 493121 | (missing) | 2014-07-02 | 2014-08-01 | |
| 493120 | (missing) | 2014-06-30 | 2014-07-30 | |
| 493119 | (missing) | 2014-06-27 | 2014-07-28 | |
| 493118 | (missing) | 2014-06-24 | 2014-07-23 | |
| 493117 | (missing) | 2014-06-16 | 2014-10-20 | |
| 493116 | (missing) | 2014-06-12 | 2014-07-12 | |
| 493114 | PROJECT NAME: Regulatory List of Actions. COUNTY: Georgia. NEAREST NAMED WATERWAY: N/A. OVERALL PROJECT PURPOSE: Actions include Individual Permits | 2014-06-09 | 2014-07-09 | |
| 493113 | PROJECT NAME: Regional Permit 84. COUNTY: Georgia. NEAREST WATERWAY: N/A. OVERALL PROJECT PURPOSE: Announcmenet of Proposed Issuance of Regional Permit 84: To Authorize Construction | 2014-06-06 | 2014-07-07 | |
| 493112 | (missing) | 2014-05-30 | 2014-06-30 | |
| 493111 | (missing) | 2014-05-28 | 2014-05-23 | |
| 493110 | (missing) | 2014-05-19 | 2014-06-16 | |
| 493108 | PROJECT: State Route 72 Widening COUNTY: Madison and Elbert Counties NEAREST NAMED WATERWAY: Broad River OVERALL PROJECT PURPOSE: To replace a bridge | 2014-05-18 | 2014-05-18 | |
| 493109 | PROJECT: State Route 72 Widening COUNTY: Madison and Elbert NEAREST NAMED WATERWAY: Broad River OVERALL PROJECT PURPOSE: To replace a bridge | 2014-04-30 | 2014-05-18 | |
| 493107 | PROJECT NAME: Clean Water Act Proposed Rule for Definition of Waters of the U.S. COUNTY: Georgia NEAREST NAMED WATERWAY: N/A OVERALL PROJECT PURPOSE: On April 21 | 2014-04-18 | 2014-07-21 | |
| 493106 | PROJECT NAME: Clean Water Act Interpretive Rule for 404(f)(1)(A) COUNTY: Georgia NEAREST NAMED WATERWAY: N/A OVERALL PROJECT PURPOSE: Although the interpretive rule was effective on April 03 | 2014-04-18 | 2014-06-05 | |
| 493105 | (missing) | 2014-03-12 | 2014-04-11 | |
| 493104 | (missing) | 2014-03-12 | 2014-04-11 | |
| 493103 | (missing) | 2014-02-28 | 2014-03-31 | |
| 493084 | PROJECT NAME: Carrollton Mills Mitigation Bank. COUNTY: Carroll. NEAREST NAMED WATERWAY: Whooping Creek / Cavender Creek. OVERALL PROJECT PURPOSE: To Modify the Carrollton Mills Mitigation Bank Final Banking Instrument Carroll County | 2014-02-21 | 2014-03-23 | |
| 493077 | (missing) | 2014-02-18 | 2014-03-20 | |
| 493026 | (missing) | 2014-01-24 | 2014-02-24 | |
| 493025 | (missing) | 2014-01-21 | 2014-03-21 | |
| 493024 | (missing) | 2014-01-09 | 2014-02-10 | |
| 493023 | PROJECT NAME: North Godley Industrial Park COUNTY: Chatham NEAREST NAMED WATERWAY: Black Creek OVERALL PROJECT PURPOSE: To construct a master planned industrial park in Chatham County | 2013-12-23 | 2014-01-22 | |
| 493022 | PROJECT NAME: Savannah District Regulatory CY2014 Agency Meetings. COUNTY: Georgia. NEAREST NAMED WATERWAY: N/A. OVERALL PROJECT PURPOSE: The 2014 schedule for the Savannah District's | 2013-12-11 | 2014-12-31 | |
| 493021 | (missing) | 2013-12-06 | 2014-01-06 | |
| 493020 | PROJECT NAME: List of Regulatory Action for months of October and November 2013. COUNTY: Georgia. OVERALL PROJECT PURPOSE: The list includes Individual Permits | 2013-12-03 | 2014-01-03 | |
| 493019 | (missing) | 2013-11-05 | 2013-12-05 | |
| 493017 | (missing) | 2013-10-22 | 2013-11-05 | |
| 493018 | PROJECT NAME: Regulatory List of Actions COUNTY: Georgia NEAREST NAMED WATERWAY: N/A OVERALL PROJECT PURPOSE: Actions include Individual Permits | 2013-10-21 | 2013-10-21 | |
| 493016 | PROJECT NAME: Jeff Davis Wood Pellet Mill and Infrastructure COUNTY: Jeff Davis NEAREST NAMED WATERWAY: Bishop Creek OVERALL PROJECT PURPOSE: To construct a Wood Pellet Fuel Manufacturing Plant and associated infrastructure. The infrastructure would include roadway | 2013-10-04 | 2013-11-04 | |
| 493015 | (missing) | 2013-10-03 | 2013-11-02 | |
| 493013 | PROJECT NAME: Gray North Bypass. COUNTY: Jones. NEAREST NAMED WATERBODY: Unnamed Tributaries to Mason Branch/Bray Branch. OVERALL PROJECT PURPOSE: To construct a 6-mile | 2013-10-02 | 2013-11-01 | |
| 493012 | (missing) | 2013-10-02 | 2013-11-01 | |
| 493011 | PROJECT NAME: Hal B. Wansley Power Plant Maintenance Dredging COUNTY: Heard. NEAREST NAMED WATERBODY: Chattahoochee River. OVERALL PROJECT PURPOSE: To perform routine maintenance dredging over the course of 10 years. To keep the intake structure clear of sediment | 2013-10-02 | 2013-11-03 | |
| 493010 | PROJECT NAME: ESi Ironman Triathlon. COUNTY: Richmond. NEAREST NAMED WATERWAY: Savannah River. OVERALL PROJECT PURPOSE: To conduct the swim leg of a triathlon in Richmond County | 2013-09-25 | 2013-09-29 | |
| 493009 | (missing) | 2013-09-23 | 2013-10-23 | |
| 493008 | (missing) | 2013-09-09 | 2013-10-08 | |
| 493007 | PROJECT NAME: Regulatory List of Actions COUNTY: Georgia NEAREST NAMED WATERWAY: OVERALL PROJECT PURPOSE: Actions include Individual Permits | 2013-08-13 | 2013-09-13 | |
| 493006 | (missing) | 2013-08-08 | 2013-09-07 | |
| 493005 | (missing) | 2013-07-31 | 2013-08-31 | |
| 493004 | PROJECT NAME: PGP0037 Inshore Artificial Reefs. COUNTY: Bryan | 2013-07-31 | ||
| 493003 | (missing) | 2013-07-11 | 2013-08-10 | |
| 493002 | PROJECT NAME: Bilbo Drainage Canal. COUNTY: Chatham. NEAREST NAMED WATERWAY: Savannah River. OVERALL PROJECT PURPOSE: Alleviate flooding to the Bilbo Drainage Basin | 2013-07-02 | 2013-08-01 | |
| 493001 | (missing) | 2013-07-02 | 2013-08-01 | |
| 493000 | PROJECT NAME: Programmatic General Permit No. 58 (PGP 58). COUNTIES: Crisp | 2013-07-01 | 2013-07-31 | |
| 492999 | PROJECT NAME: PGP for Lakes Hartwell | 2013-06-10 | ||
| 492998 | Savannah Regulatory Actions for February - May 2013 | 2013-06-04 | 2013-07-04 | |
| 492997 | (missing) | 2013-05-15 | 2013-06-14 | |
| 492996 | PROJECT NAME: Reissuance of Regional Permit 98 for private | 2013-05-15 | 2013-06-14 | |
| 492995 | (missing) | 2013-05-01 | 2013-05-31 | |
| 492994 | (missing) | 2013-04-24 | 2013-05-24 | |
| 492993 | (missing) | 2013-04-17 | 2013-05-17 | |
| 492992 | (missing) | 2013-04-17 | 2013-05-17 | |
| 492991 | (missing) | 2013-04-17 | 2013-05-17 | |
| 492990 | (missing) | 2013-04-17 | 2013-05-17 | |
| 492989 | (missing) | 2013-04-17 | 2013-05-17 | |
| 492988 | (missing) | 2013-04-17 | 2013-05-17 | |
| 492987 | (missing) | 2013-04-10 | 2013-05-10 | |
| 492986 | In an effort to reduce waste | 2013-04-03 | 2013-05-04 | |
| 492985 | (missing) | 2013-04-03 | 2013-05-03 | |
| 492984 | (missing) | 2013-04-03 | 2013-05-03 | |
| 492983 | (missing) | 2013-04-03 | 2013-05-03 | |
| 492981 | (missing) | 2013-03-20 | 2013-04-18 | |
| 492980 | (missing) | 2013-03-13 | 2013-04-11 | |
| 492979 | (missing) | 2013-03-13 | 2013-04-11 | |
| 492982 | PROJECT NAME: Regional General Permit 96. COUNTY: Georgia. NEAREST NAMED WATERWAY: Numerous. OVERALL PROJECT PURPOSE: Revise and reissue Regional General Permit 96 for maintenance | 2013-03-06 | 2013-04-04 | |
| 492978 | (missing) | 2013-03-06 | 2013-04-04 | |
| 492977 | (missing) | 2013-02-20 | 2013-03-22 | |
| 492976 | PROJECT NAME: Programmatic General Permits for Savannah District Corps Lakes. COUNTY: Various. NEAREST NAMED WATERWAY: Various. OVERALL PROJECT PURPOSE: Proposed modification | 2013-02-20 | 2013-03-22 | |
| 492975 | (missing) | 2013-02-06 | 2013-02-21 | |
| 492974 | (missing) | 2013-01-30 | 2013-03-01 | |
| 492973 | (missing) | 2013-01-23 | 2013-02-22 | |
| 492972 | (missing) | 2013-01-23 | 2013-02-22 | |
| 492971 | PROJECT NAME: Phinizy Swamp Mitigation Bank (expansion) Phase II. COUNTY: Richmond. NEAREST NAMED WATERWAY: Savannah River. OVERALL PROJECT PURPOSE: To establish | 2013-01-23 | 2013-02-22 | |
| 492970 | (missing) | 2013-01-23 | 2013-02-22 | |
| 492969 | (missing) | 2013-01-23 | 2013-02-22 | |
| 492968 | PROJECT NAME: Mando Automotive Facility. COUNTY: Meriwether. NEAREST NAMED WATERWAY: Blue Creek. OVERALL PROJECT PURPOSE: To expand a recently opened automotive parts manufacturing facility to include additional warehouse space for parts manufacturing | 2013-01-09 | 2013-02-08 | |
| 492967 | (missing) | 2013-01-09 | 2013-02-08 | |
| 493102 | (missing) | 2012-12-26 | 2013-01-26 | |
| 493101 | PROJECT NAME: Coffee Bluff Marina. COUNTY: Chatham. NEAREST WATERWAY: Forest River. OVERALL PROJECT PURPOSE: To modify an existing marina including the store | 2012-12-26 | 2013-01-26 | |
| 493100 | (missing) | 2012-12-26 | 2013-01-26 | |
| 493099 | PROJECT NAME: List of Action for September | 2012-12-26 | 2012-12-26 | |
| 492966 | (missing) | 2012-12-26 | 2013-01-25 | |
| 492965 | (missing) | 2012-12-26 | 2013-01-25 | |
| 492964 | PROJECT NAME: Coffee Bluff Marina. COUNTY: Chatham. NEAREST NAMED WATERBODY: Forest River. OVERALL PROJECT PURPOSE: To modify an existing marina including the store | 2012-12-26 | 2013-01-25 | |
| 493098 | PROJECT NAME: B. C. Waycross Associates. COUNTY: Ware. NEAREST WATERWAY: Mill Creek. OVERALL PROJECT PURPOSE: To extinguish a restrictive covenant on 0.657 acre of property located north of US Highway 1 and Morris Road | 2012-12-12 | 2013-01-12 | |
| 493097 | (missing) | 2012-12-05 | 2013-01-21 | |
| 493096 | (missing) | 2012-12-05 | 2012-12-05 | |
| 493095 | PROJECT NAME: Recreational Pond Regional Permit. COUNTY: Georgia. NEAREST WATERWAY: N/A. OVERALL PROJECT PURPOSE: Re-issuance of Regional Permit 90 for Private Single Family | 2012-11-14 | 2012-11-14 | |
| 493094 | (missing) | 2012-11-07 | 2012-11-07 | |
| 493093 | (missing) | 2012-11-07 | 2012-12-07 | |
| 493092 | PROJECT NAME: Broadhurst | 2012-11-07 | 2012-11-24 | |
| 493091 | (missing) | 2012-10-31 | 2012-10-31 | |
| 493090 | (missing) | 2012-10-31 | 2012-12-01 | |
| 493089 | PROJECT NAME: Wahoo Creek Mitigation Bank. COUNTY: Coweta. NEAREST WATERWAY: Wahoo Creek. OVERALL PROJECT PURPOSE: To develop a 107-acre wetland and stream commercial mitigation bank | 2012-10-24 | 2012-11-24 | |
| 493088 | PROJECT NAME: Savannah Steel Terminal Docking Facility. COUNTY: Chatham. NEAREST WATERWAY: Savannah River. OVERALL PROJECT PURPOSE: To annually dredge approximately 12 | 2012-10-17 | 2012-11-17 | |
| 493087 | (missing) | 2012-10-03 | 2012-11-03 | |
| 493086 | PROJECT NAME: List of Action for July and August. COUNTY: Georgia. NEAREST WATERWAY: N/A. OVERALL PROJECT PURPOSE: List includes Individual Permits | 2012-09-26 | 2012-09-26 | |
| 493085 | (missing) | 2012-09-19 | 2012-09-19 | |
| 493083 | (missing) | 2012-09-05 | 2012-10-05 | |
| 493082 | (missing) | 2012-09-05 | 2012-10-05 | |
| 493081 | (missing) | 2012-08-29 | 2012-09-29 | |
| 493080 | (missing) | 2012-08-22 | 2012-09-22 | |
| 493079 | (missing) | 2012-08-22 | 2012-09-22 | |
| 493075 | (missing) | 2012-08-22 | 2012-09-22 | |
| 493074 | (missing) | 2012-08-15 | 2012-09-15 | |
| 493073 | (missing) | 2012-08-13 | 2012-08-13 | |
| 493076 | (missing) | 2012-08-08 | 2012-09-08 | |
| 493072 | (missing) | 2012-08-01 | 2012-09-01 | |
| 493071 | (missing) | 2012-08-01 | 2012-09-01 | |
| 493070 | (missing) | 2012-08-01 | 2012-09-01 | |
| 493069 | (missing) | 2012-08-01 | 2012-08-15 | |
| 493068 | (missing) | 2012-08-01 | 2012-09-01 | |
| 493067 | (missing) | 2012-07-18 | 2012-07-18 | |
| 493066 | (missing) | 2012-07-11 | 2014-08-11 | |
| 493065 | PROJECT NAME: List of Actions for June. COUNTY: Georgia. NEAREST WATERWAY: NA. OVERALL PROJECT PURPOSE: The list includes Individual Permits | 2012-07-11 | 2012-07-11 | |
| 493078 | (missing) | 2012-07-04 | 2012-07-19 | |
| 493064 | (missing) | 2012-07-04 | 2012-07-04 | |
| 493063 | (missing) | 2012-06-20 | 2012-07-20 | |
| 493062 | (missing) | 2012-06-20 | 2012-07-20 | |
| 493061 | PROJECT NAME: North Point Industrical | 2012-06-20 | 2012-07-20 | |
| 493060 | PROJECT NAME: Messiers Creek Mitigation Bank. COUNTY: Coweta. NEAREST WATERWAY: Messiers Creek. OVERALL PROJECT PURPOSE: Proposes to develop a 239-acre wetland and stream commercial mitigation bank | 2012-06-13 | 2012-07-13 | |
| 493059 | PROJECT NAME: Berrien County Airport. COUNTY: Berrien. NEAREST WATERWAY: Wolfpen Branch. OVERALL PROJECT PURPOSE: Proposing to extend the existing runway 1 | 2012-06-13 | 2012-07-13 | |
| 493058 | (missing) | 2012-06-13 | 2012-07-13 | |
| 493057 | PROJECT NAME: Poor Robin Mitigation Bank by Riverland Ventures LLC. COUNTY: Screven. NEAREST WATERWAY: Savannah River. OVERALL PROJECT PURPOSE: The bank sponsor proposes to preserve | 2012-05-30 | 2012-06-30 | |
| 493056 | (missing) | 2012-05-23 | 2012-06-23 | |
| 493055 | (missing) | 2012-05-09 | 2012-06-09 | |
| 493054 | (missing) | 2012-05-09 | 2012-06-09 | |
| 493053 | (missing) | 2012-04-25 | 2012-05-25 | |
| 493052 | (missing) | 2012-04-25 | 2012-05-25 | |
| 493051 | (missing) | 2012-04-25 | 2012-05-25 | |
| 493050 | PROJECT NAME: List of Actions for March 2012. COUNTY: Georgia. NEAREST WATERWAY: NA. OVERALL PROJECT PURPOSE: The list includes Individual Permits | 2012-04-25 | 2012-04-25 | |
| 493049 | (missing) | 2012-04-11 | 2012-05-11 | |
| 493048 | (missing) | 2012-04-11 | 2012-05-11 | |
| 493047 | PROJECT NAME: Georgia Power Plant McManus Dredging. COUNTY: Glynn. NEAREST WATERWAY: Turtle River. OVERALL PROJECT PURPOSE: The proposed project is to annually dredge 9 | 2012-04-11 | 2012-05-11 | |
| 493046 | PROJECT NAME: 2012 Nation Wide Permits. COUNTY: Georgia. NEAREST WATERWAY: NA. OVERALL PROJECT PURPOSE: The reissuance of 48 of the 49 existing Nationwide Permits (NWPs) | 2012-03-30 | 2012-04-30 | |
| 493045 | (missing) | 2012-03-21 | 2012-04-21 | |
| 493039 | (missing) | 2012-03-15 | 2012-03-15 | |
| 493044 | (missing) | 2012-03-14 | 2012-04-14 | |
| 493043 | PROJECT NAME: Crockett Tract Mitigation Bank. COUNTY: Screven. NEAREST WATERWAY: Brier Creek. OVERALL PROJECT PURPOSE: Proposes to enhance areas of wetland (both vegetative and hydrologic) | 2012-03-07 | 2012-04-07 | |
| 493042 | (missing) | 2012-03-07 | 2012-04-07 | |
| 493041 | (missing) | 2012-03-07 | 2012-04-17 | |
| 493040 | PROJECT NAME: List of Actions for February. COUNTY: Georgia. NEAREST WATERWAY: NA. OVERALL PROJECT PURPOSE: List includes Individual Permits | 2012-03-07 | 2012-03-07 | |
| 493038 | (missing) | 2012-02-15 | 2012-03-15 | |
| 493037 | PROJECT NAME: List of Action for January 2012. COUNTY: Georgia. NEAREST WATERWAY: NA. OVERALL PROJECT PURPOSE: List includes Individual Permits | 2012-02-15 | 2012-02-15 | |
| 493036 | (missing) | 2012-01-25 | 2012-02-25 | |
| 493035 | (missing) | 2012-01-25 | 2012-02-25 | |
| 493034 | (missing) | 2012-01-25 | 2012-02-25 | |
| 493033 | (missing) | 2012-01-25 | 2012-01-25 | |
| 493032 | PROJECT NAME: SLNG Elba Island Maintanance Dredging. COUNTY: Chatham. NEAREST WATERWAY: Savannah River. OVERALL PROJECT PURPOSE: To annually dredge approximately 800 | 2012-01-25 | 2012-02-25 | |
| 493031 | (missing) | 2012-01-25 | 2013-02-25 | |
| 493030 | PROJECT NAME: SR 347/Friendship Road from I-985 to SR 211. COUNTY: Hall. NEAREST WATERWAY: Mitchell Creek OVERALL PROJECT PURPOSE: To impact 0.53 acre of wetlands/open water and 5 | 2012-01-18 | 2012-02-18 | |
| 493029 | PROJECT NAME: List of Actions. COUNTY: Georgia. NEAREST NAMED WATERWAY: NA. OVERALL PROJECT PURPOSE: List includes Individual Permits | 2012-01-18 | 2012-02-18 | |
| 493028 | (missing) | 2012-01-06 | 2012-02-06 | |
| 1989262 | (missing) | |||
| 1988903 | NOTICE OF RELOCATION OF THE PIEDMONT BRANCH FIELD OFFICE OF THE SAVANNAH DISTRICT | |||
| 1986142 | (missing) | |||
| 1984519 | (missing) | |||
| 1983734 | (missing) | |||
| 1962613 | Project Name: SAS-2018-00554 Twin Pines Minerals | |||
| 1962154 | On September 12 | |||
| 1959215 | (missing) | |||
| 1958790 | (missing) | |||
| 1958758 | City of Tybee Island | |||
| 1951365 | (missing) | |||
| 1949056 | Savannah Outreach Date Change-Sept. 10 | |||
| 1943441 | (missing) | |||
| 1933389 | (missing) | |||
| 1928478 | (missing) | |||
| 1928058 | (missing) | |||
| 1926928 | PROJECT NAME: Lake Blackshear PGP 58. COUNTY: Crisp | |||
| 1924640 | Savannah District Regulatory Outreach Event September 05 | |||
| 1924318 | (missing) | |||
| 1915526 | (missing) | |||
| 1911078 | (missing) | |||
| 1903832 | (missing) | |||
| 1903531 | (missing) | |||
| 1898376 | (missing) | |||
| 1891750 | (missing) | |||
| 1891748 | (missing) | |||
| 1889422 | (missing) | |||
| 1882534 | (missing) | |||
| 1876324 | (missing) | |||
| 1875794 | (missing) | |||
| 1874700 | (missing) | |||
| 1862527 | (missing) | |||
| 1862364 | PROJECT NAME: Thunderbolt Marine | |||
| 1844464 | PROJECT NAME: Altamaha WMA. COUNTY: McIntosh. NEAREST NAMED WATERWAY: Altamaha River. OVERALL PROJECT PURPOSE: To perform dike | |||
| 1844288 | (missing) | |||
| 1818156 | (missing) | |||
| 1814551 | Notice of Availability of a Draft Environmental Assessment (EA) and Draft Finding of No Significant Impact (FONSI) for 2019 Tybee Island Shore Protection Project (TISPP) | |||
| 1813185 | (missing) | |||
| 1795017 | (missing) | |||
| 1786803 | (missing) | |||
| 1778028 | Updated Certain Aspects of the E-Submittal Process: 1) Larger Application send in process easier | |||
| 1777102 | (missing) | |||
| 1774012 | PROJECT NAME: SAS-2019-00162. COUNTY: Hall. NEAREST NAMED WATERBODY: Suwanee Creek. OVERALL PROJECT PURPOSE: Construction of a distribution center composed of four (4) buildings totaling 658 | |||
| 1772484 | PROJECT NAME: SAS-2019-00153 COUNTY: Fulton NEAREST NAMED WATERBODY: South River OVERALL PROJECT PURPOSE: Expansion of an existing | |||
| 1771055 | County: Chatham Nearest Named Waterbody: Salt Creek Overall Project Purpose: a mixed use commercial | |||
| 1769672 | Notice of Availability of a Draft Integrated Post Authorization Analysis Report (PAAR) and Supplemental Environmental Assessment (SEA) | |||
| 1767795 | (missing) |
Data are available as CSV download in the following schemas
- Current version of the data, one row per public notice
- History of updates to the data, one row per updated field per public notice
- Historical versions of the data, with the aforementioned updates applied, one row per version per public notice