REQUESTED ALTERATION: The proposed modification is to rehabilitate the 5th
Street Bridge over the Savannah River. One of the tasks is to construct concrete steps
on the slope of the levee from Marina Road to the Access Road on top at approximate
levee station 164+75. The concrete steps will be constructed onto the grade of the
levee slope with no gaps between the steps and the levee surface. Erosion prevention
will be provided along the sides of the stairway. The stairway will have foundations
constructed directly on the levee soils. No change to the flow of the Savannah River
is anticipated because of the construction. No work in or on theĀ· River is planned.
No debris from construction activities on the bridge will be allowed to fall into the
river and containment systems will be used during bridge painting.
REQUESTED ALTERATION: The proposed modification is to rehabilitate the 5th
Street Bridge over the Savannah River. One of the tasks is to construct concrete steps
on the slope of the levee from Marina Road to the Access Road on top at approximate
levee station 164+75. The concrete steps will be constructed onto the grade of the
levee slope with no gaps between the steps and the levee surface. Erosion prevention
will be provided along the sides of the stairway. The stairway will have foundations
constructed directly on the levee soils. No change to the flow of the Savannah River
is anticipated because of the construction. No work in or on theĀ· River is planned.
No debris from construction activities on the bridge will be allowed to fall into the
river and containment systems will be used during bridge painting.